ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Approval of the demolition of the existing student center, the renovation of the existing library including a new faade and the addition of a new vestibule to the existing student services building per the approved site plans, exhibits c-1 through c-16, signed and dated february 10, 2015 subject to the following conditions:a. As part of the building permit application submittal, each of the 4 required site plans and any additional drawings must reflect the information and design approved by this land use review as indicated in exhibits c. 1-c. 16. The sheets on which this information appears must be labeled, proposal and design as approved in case file # lu 14-251504 dz. No field changes allowed. Date: February 11, 2015Permit type: Land use review | Permit status: Completed | Completion date: December 22, 2014 | Permit id: 2014-251504-000 | |||||
Remove and replace electrical for rooftop ahu and cu. Associated with mechanical permit 14-251905-000-00-mt Date: December 29, 2014Permit type: Electrical inspections | Permit status: Approved | Completion date: May 12, 2015 | Permit id: 2014-254111-000 | |||||
Power and data for new work stations in room 215pr # mab rm 215 Date: January 8, 2015Permit type: Reviews | Permit status: Approved | Completion date: January 8, 2015 | Permit id: 2015-102640-000 | |||||
Pwr- power for new work stations in room 215 - pwr Date: January 8, 2015Permit type: Intake | Permit status: Closed | Completion date: January 8, 2015 | Permit id: 2015-102645-000 | |||||
Data - data for new work stations in room 215 - data Date: January 8, 2015Permit type: Intake | Permit status: Closed | Completion date: January 8, 2015 | Permit id: 2015-102649-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Application | Permit status: Approved | Completion date: May 22, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Issuance/intake | Permit status: Intake | Completion date: May 22, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Process management | Permit status: Closed | Completion date: May 27, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Process management | Permit status: Closed | Completion date: June 26, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Planning and zoning | Permit status: Approved | Completion date: June 8, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Erosion control | Permit status: Approved | Completion date: June 9, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Site development | Permit status: Required | Completion date: June 9, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Site development | Permit status: Approved | Completion date: June 9, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Structural | Permit status: Required | Completion date: June 16, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Commercial plumbing | Permit status: Not reqd | Completion date: June 9, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Special inspections review | Permit status: Approved | Completion date: June 19, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Transportation | Permit status: Approved | Completion date: June 3, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Transportation | Permit status: Approved | Completion date: May 29, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Transportation | Permit status: Closed | Completion date: May 29, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Water bureau review | Permit status: Approved | Completion date: June 16, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Water bureau review | Permit status: Approved | Completion date: June 30, 2015 | Permit id: 2015-174597-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Permit type: Parks bureau | Permit status: Approved | Completion date: June 1, 2015 | Permit id: 2015-174597-000 | |||||
130t chiller, four mini-splits, restroomo exhaust, terminal units on existing vav, plans w/co Permit type: Intake | Permit status: Closed | Completion date: May 26, 2015 | Permit id: 2015-174599-000 | |||||
130t chiller, four mini-splits, restroomo exhaust, terminal units on existing vav, plans w/co Permit type: Life safety | Permit status: Not reqd | Completion date: May 26, 2015 | Permit id: 2015-174599-000 | |||||
130t chiller, four mini-splits, restroomo exhaust, terminal units on existing vav, plans w/co Permit type: Mechanical review | Permit status: Approved | Completion date: May 26, 2015 | Permit id: 2015-174599-000 | |||||
130t chiller, four mini-splits, restroomo exhaust, terminal units on existing vav, plans w/co Permit type: Fire bureau | Permit status: Not reqd | Completion date: May 26, 2015 | Permit id: 2015-174599-000 | |||||
F 11/ pcc student services building 2 story interior renovation, new walls and partitions for offices, lobby areas, conference rooms and call centers, remove portion of sidewalk and face-brick storefront for new entry vestibule south side of building Date: May 26, 2015Permit type: Reviews | Permit status: Approved | Completion date: May 26, 2015 | Permit id: 2015-175609-000 | |||||
F 11/ pcc student services building 2 story interior renovation - split air sytsem with rtu, vav unit, diffusers & grilles, unit heater and ductwork Date: July 6, 2015Permit type: Intake | Permit status: Closed | Completion date: May 26, 2015 | Permit id: 2015-175620-000 | |||||
Dfs for fnd-01 - design and engineering for underground drywells Date: April 26, 2013Permit type: Application | Permit status: Approved | Completion date: March 15, 2013 | Permit id: 2012-184939-Dfs | |||||
Mass excavation and shoring for new parking garage with two academic towers Date: December 21, 2012Permit type: Application | Permit status: Approved | Completion date: September 21, 2012 | Permit id: 2012-184939-Exc | |||||
One level underground garage including foundations, slab on grade, shoring walls, post-tension concrete lid, incoming utilty connections, storm-filters and drywells and other mechanical, electrical, tel/data for a complete and operational garage. Date: February 11, 2013Permit type: Application | Permit status: Approved | Completion date: November 21, 2012 | Permit id: 2012-184939-Fnd | |||||
Revise location of stormfilters and drywells located underneath the slab of the garage (revision to 12-184969-fnd-01-co) Date: April 18, 2013Permit type: Application | Permit status: Approved | Completion date: April 2, 2013 | Permit id: 2012-184939-Rev | |||||
Structural steel and concrete Date: April 12, 2013Permit type: Application | Permit status: Approved | Completion date: February 11, 2013 | Permit id: 2012-184939-Str | |||||
Ab:three total 75-ton, 45-zone vrv, three 3-ton ductless splits, 166 cfm doas, three 55 cfm efssc: four total 75-ton, 40-zone vrv, three 3-ton ductless splits, 86 cfn hrv, two 65 mau, plans w/co Date: June 28, 2013Permit type: Intake | Permit status: Closed | Completion date: March 28, 2013 | Permit id: 2013-129893-000 | |||||
Sprinkler - 3 dry fire sprinkler systems in new parking garageunderground by city on property line5/24/13 ot plan review paid5/2/13 recd revisions - 5/21/2013 - additional plan review fees - 2 hrs per mike olley Date: April 11, 2013Permit type: Intake | Permit status: Approved | Completion date: April 2, 2013 | Permit id: 2013-134371-000 | |||||
F2/ small fan unit at platform lift Date: March 19, 2014Permit type: Intake | Permit status: Closed | Completion date: November 8, 2013 | Permit id: 2013-226283-000 | |||||
Ada upgrade; new lift and ramp, w side, remove stairs, railing, exterior door and portion of wall, replace with new stairs, railing, ramp, grade landscaping in front for pedestrian ramp, excavate down to lecture floor level, shoring, ceiling, elecpr# dist-ada-proj. Date: November 23, 2013Permit type: Intake | Permit status: Closed | Completion date: November 23, 2013 | Permit id: 2013-231751-000 | |||||
Construct approximately 205 sf covered bike shelter Date: August 26, 2014Permit type: Application | Permit status: Approved | Completion date: January 14, 2014 | Permit id: 2014-104402-000 | |||||
B1/ teb classroom remodel, patch & repair walls & floors, new corner wall for sprinkler system, partial suspended act grid ceiling Date: May 30, 2014Permit type: Intake | Permit status: Closed | Completion date: May 22, 2014 | Permit id: 2014-160321-000 | |||||
B1/ teb classroom remodel - adjust existing hvac system for remodel Date: May 30, 2014Permit type: Intake | Permit status: Closed | Completion date: May 22, 2014 | Permit id: 2014-160325-000 | |||||
B1/ jh classroom remodel, remove, patch & repair walls & floors, partial suspended act grid ceiling Date: May 30, 2014Permit type: Intake | Permit status: Closed | Completion date: May 22, 2014 | Permit id: 2014-160358-000 | |||||
B1/ jh classroom remodel - adjust existing hvac systems for remodel Date: May 30, 2014Permit type: Intake | Permit status: Closed | Completion date: May 22, 2014 | Permit id: 2014-160360-000 | |||||
Power - jh classroom remodel, remove, patch & repair walls & floors, partial suspended act grid ceiling Date: May 30, 2014Permit type: Intake | Permit status: Closed | Completion date: May 30, 2014 | Permit id: 2014-162415-000 | |||||
Power - teb classroom remodel, patch & repair walls & floors, new corner wall for sprinkler system, partial suspended act grid ceiling Date: May 30, 2014Permit type: Intake | Permit status: Closed | Completion date: May 30, 2014 | Permit id: 2014-163009-000 | |||||
Plumbing renovation at pcc cascade teb. Demo 3 sinks, 5 eew Date: August 25, 2014Permit type: Intake | Permit status: Closed | Completion date: June 2, 2014 | Permit id: 2014-164004-000 | |||||
Installation of 4 ansull r-102 systems onto pre piped hoods--3 sets of plans Date: June 5, 2014Permit type: Intake | Permit status: Closed | Completion date: June 5, 2014 | Permit id: 2014-165390-000 | |||||
Remove uprightsadd pendents for new ceilins in classroom remodels---3 sets of plans Date: July 2, 2014Permit type: Intake | Permit status: Closed | Completion date: July 2, 2014 | Permit id: 2014-178532-000 | |||||
Voice/data - teb classroom remodel, patch & repair walls & floors, new corner wall for sprinkler system, partial suspended act grid ceiling Date: July 7, 2014Permit type: Intake | Permit status: Closed | Completion date: July 7, 2014 | Permit id: 2014-180096-000 | |||||
Install 2 155 degrees qr fire sprinkler heads for ada upgrade---3 sets of plans Date: July 11, 2014Permit type: Intake | Permit status: Closed | Completion date: July 11, 2014 | Permit id: 2014-182667-000 | |||||
Fire alarm-emergency responder radio system-installing das system Date: February 10, 2015Permit type: Intake | Permit status: Approved | Completion date: August 13, 2014 | Permit id: 2014-196751-000 | |||||
B2/ kiln vent and ductwork replacement Date: August 27, 2014Permit type: Reviews | Permit status: Approved | Completion date: August 27, 2014 | Permit id: 2014-204858-000 | |||||
Pwr - kiln vent and ductwork replacement - pwr Date: September 16, 2014Permit type: Intake | Permit status: Closed | Completion date: September 16, 2014 | Permit id: 2014-213690-000 | |||||
Electrical for replacement generators Date: August 3, 2015Permit type: Intake | Permit status: Closed | Completion date: July 20, 2015 | Permit id: 2015-204214-000 | |||||
Plumbing renovation at pcc cascade student servicesmop sink, df, hb Date: August 6, 2015Permit type: Intake | Permit status: Closed | Completion date: August 6, 2015 | Permit id: 2015-212790-000 | |||||
Alarm - partial remodel of the 1st and 2nd floors. All of the head in equipment is existing. Relocate devices from demolished dining hall Date: August 21, 2015Permit type: Intake | Permit status: Approved | Completion date: August 6, 2015 | Permit id: 2015-212822-000 | |||||
Pcc student services building-tenant improvement of sprinkler system Date: August 27, 2015Permit type: Intake | Permit status: Closed | Completion date: August 7, 2015 | Permit id: 2015-213687-000 | |||||
Install (4) 200amp service and (1) 400amp services; existing generator serving the moriarty building shall be removed and replaced by a large generator Date: August 28, 2015Permit type: Intake | Permit status: Closed | Completion date: August 13, 2015 | Permit id: 2015-217646-000 | |||||
Ti for existing space Date: September 3, 2015Permit type: Intake | Permit status: Closed | Completion date: September 3, 2015 | Permit id: 2015-230937-000 | |||||
Private property tree removal permit Date: October 27, 2015Permit type: A - research | Permit status: Title 11 permit required | Completion date: September 21, 2015 | Permit id: 2015-239747-000 | |||||
Install a 2 water line feet pcv pipe plus 2 2 back flow devices Date: September 30, 2015Permit type: Plumbing inspections | Permit status: Approved | Completion date: October 1, 2015 | Permit id: 2015-244275-000 | |||||
Installing new sanitary and storm piping form the row to building Date: October 1, 2015Permit type: Intake | Permit status: Closed | Completion date: October 1, 2015 | Permit id: 2015-244817-000 | |||||
Sprinkler - fire sprinkler remodel for library ti Date: November 17, 2015Permit type: Intake | Permit status: Approved | Completion date: October 28, 2015 | Permit id: 2015-256850-000 | |||||
Plumbing renovation at pcc cascade student services buildingrain drain Date: December 8, 2015Permit type: Intake | Permit status: Closed | Completion date: December 8, 2015 | Permit id: 2015-274473-000 | |||||
Hazardous-replacing generator for building peb Date: March 4, 2016Permit type: Intake | Permit status: Approved | Completion date: February 5, 2016 | Permit id: 2016-116395-000 | |||||
Hazardous-replacing generator for building teb Date: March 4, 2016Permit type: Intake | Permit status: Approved | Completion date: February 5, 2016 | Permit id: 2016-116399-000 | |||||
Hazardous-replacing generator for library building. Date: March 4, 2016Permit type: Intake | Permit status: Approved | Completion date: February 12, 2016 | Permit id: 2016-116403-000 | |||||
Hazardous-replacing generator for building pseb Date: March 10, 2016Permit type: Intake | Permit status: Approved | Completion date: February 5, 2016 | Permit id: 2016-116409-000 | |||||
Hazardous-replacing generator for building mahb Date: February 29, 2016Permit type: Intake | Permit status: Approved | Completion date: February 5, 2016 | Permit id: 2016-116415-000 | |||||
Underground - installation of 6 fireline to new addition Date: February 25, 2016Permit type: Intake | Permit status: Approved | Completion date: February 17, 2016 | Permit id: 2016-121504-000 | |||||
Install main distribution panel Date: April 5, 2016Permit type: Intake | Permit status: Closed | Completion date: February 25, 2016 | Permit id: 2016-126526-000 | |||||
Low voltage irrigation timerfaxed Date: April 7, 2014Permit type: Intake | Permit status: Closed | Completion date: April 7, 2014 | Permit id: 2014-136745-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices/classrooms/study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Date: August 3, 2015Permit type: Application | Permit status: Approved | Completion date: May 22, 2015 | Permit id: 2015-174597-000 | |||||
Dfs exterior curtainwall and interior glazing systems Date: December 30, 2015Permit type: Application | Permit status: Approved | Completion date: November 6, 2015 | Permit id: 2015-174597-Dfs | |||||
Dfs - acoustical ceilings Date: April 11, 2016Permit type: Application | Permit status: Approved | Completion date: February 8, 2016 | Permit id: 2015-174597-Dfs | |||||
Added value revision to removed restrooms on the third floor Date: October 21, 2015Permit type: Application | Permit status: Approved | Completion date: October 21, 2015 | Permit id: 2015-174597-Rev | |||||
130t chiller, four mini-splits, restroomo exhaust, terminal units on existing vav, plans w/co Date: August 3, 2015Permit type: Intake | Permit status: Closed | Completion date: May 26, 2015 | Permit id: 2015-174599-000 | |||||
B2/ dfs for temporary egress during construction Date: July 15, 2015Permit type: Intake | Permit status: Closed | Completion date: July 9, 2015 | Permit id: 2015-175611-Dfs | |||||
F 11/ rev 01/ pcc student services building - add notation to drawings for existing and new fire and smoke dampers at rated walls. Date: August 26, 2015Permit type: Intake | Permit status: Closed | Completion date: August 19, 2015 | Permit id: 2015-175611-Rev | |||||
Revision to add plan review no change in the scope of work upgrade to the existing generator Date: August 3, 2015Permit type: Intake | Permit status: Closed | Completion date: July 20, 2015 | Permit id: 2015-199055-Rev | |||||
Pwr - pcc student services building 2 story interior renovation - pwr Date: July 14, 2015Permit type: Intake | Permit status: Closed | Completion date: July 14, 2015 | Permit id: 2015-201349-000 | |||||
Voice/data - pcc student services building 2 story interior renovation, - voice/data Date: July 14, 2015Permit type: Intake | Permit status: Closed | Completion date: July 14, 2015 | Permit id: 2015-201352-000 | |||||
Student services- alteration to the fire alarm as needed for t. I.- 9 devices total 7- h/s, 2- pull stations Date: July 20, 2015Permit type: Intake | Permit status: Closed | Completion date: July 20, 2015 | Permit id: 2015-203864-000 | |||||
Demolition of existing student center attached to library, reclad newly exposed facade of library, reconfigure entry, interior renovation and addition of restrooms on 1st and 2nd floor, new offices classrooms study areas; addition of new plaza where existing student center was, includes landscaping, concrete work, seating, stormwater facilities; sidewalk and curb improvements to kirby Date: August 3, 2015Permit type: Application | Permit status: Approved | Completion date: May 22, 2015 | Permit id: 2015-174597-000 | |||||
130t chiller, four mini-splits, restroomo exhaust, terminal units on existing vav, plans w co Date: August 3, 2015Permit type: Intake | Permit status: Closed | Completion date: May 26, 2015 | Permit id: 2015-174599-000 | |||||
F 11 pcc student services building 2 story interior renovation, new walls and partitions for offices, lobby areas, conference rooms and call centers, remove portion of sidewalk and face-brick storefront for new entry vestibule south side of building Date: May 26, 2015Permit type: Reviews | Permit status: Approved | Completion date: May 26, 2015 | Permit id: 2015-175609-000 | |||||
B2 dfs for temporary egress during construction Date: July 15, 2015Permit type: Intake | Permit status: Closed | Completion date: July 9, 2015 | Permit id: 2015-175611-Dfs | |||||
F 11 rev 01 pcc student services building - add notation to drawings for existing and new fire and smoke dampers at rated walls. Date: August 26, 2015Permit type: Intake | Permit status: Closed | Completion date: August 19, 2015 | Permit id: 2015-175611-Rev | |||||
F 11 pcc student services building 2 story interior renovation - split air sytsem with rtu, vav unit, diffusers & grilles, unit heater and ductwork Date: July 6, 2015Permit type: Intake | Permit status: Closed | Completion date: May 26, 2015 | Permit id: 2015-175620-000 | |||||
Voice data - pcc student services building 2 story interior renovation, - voice data Date: July 14, 2015Permit type: Intake | Permit status: Closed | Completion date: July 14, 2015 | Permit id: 2015-201352-000 | |||||
Student services- alteration to the fire alarm as needed for t. I.- 9 devices total 7- h s, 2- pull stations Date: July 20, 2015Permit type: Intake | Permit status: Closed | Completion date: July 20, 2015 | Permit id: 2015-203864-000 | |||||
Install new suspended cieling Date: April 17, 2000Client: Northeast Coalition Of Neighbors | Permit type: Alteration | Permit status: Final | Completion date: June 8, 2000 | Current use: Institutional | Permit id: 2000-143022-000 | |||||
Continued plaza improvement completion phase --to include storm water facility and light posts and landscaping Date: May 25, 2006Client: Northeast Coalition Of Neighbors | Permit type: Alteration | Permit status: Final | Completion date: September 15, 2006 | Current use: Educational | Permit id: 2006-117440-000 | |||||
Remove & replace existing exterior terrace. Add a new accessible elevator. Date: June 15, 2006Client: Northeast Coalition Of Neighbors | Permit type: Alteration | Permit status: Final | Completion date: September 15, 2006 | Current use: Business | Permit id: 2006-102169-000 |