ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Demolish sfr, cap sewer, remove all debris, no fill greater than 24, subject to 35 day demo delay. No fill greater than 24. Date: December 4, 2015Permit type: Application | Permit status: Approved | Completion date: October 28, 2015 | Permit id: 2015-257565-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Request | Permit status: Closed | Completion date: February 8, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Application | Permit status: Approved | Completion date: November 6, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Issuance/intake | Permit status: Intake | Completion date: November 6, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: November 12, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 4, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 3, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 17, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 19, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: January 7, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: January 14, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: December 2, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: March 31, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: March 18, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 24, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: March 11, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Addressing | Permit status: Approved | Completion date: December 9, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Planning and zoning | Permit status: Approved | Completion date: February 25, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Planning and zoning | Permit status: Approved | Completion date: February 22, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Planning and zoning | Permit status: Approved | Completion date: February 8, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Planning and zoning | Permit status: Approved | Completion date: March 21, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Erosion control | Permit status: Approved | Completion date: January 27, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Site development | Permit status: Required | Completion date: January 27, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Site development | Permit status: Approved | Completion date: January 27, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Life safety | Permit status: Approved | Completion date: December 15, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Life safety | Permit status: Approved | Completion date: January 7, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Structural | Permit status: Required | Completion date: February 8, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Structural | Permit status: Approved | Completion date: February 23, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Commercial plumbing | Permit status: Approved | Completion date: January 15, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Special inspections review | Permit status: Approved | Completion date: February 3, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Special inspections review | Permit status: Approved | Completion date: April 4, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Fire bureau | Permit status: Approved | Completion date: April 1, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Environmental services | Permit status: Approved | Completion date: January 22, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Transportation | Permit status: Approved | Completion date: December 7, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Transportation | Permit status: Approved | Completion date: January 26, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Transportation | Permit status: Approved | Completion date: January 19, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Water bureau review | Permit status: Approved | Completion date: February 19, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Water bureau review | Permit status: Approved | Completion date: February 10, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Parks bureau | Permit status: Approved | Completion date: December 28, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Parks bureau | Permit status: Approved | Completion date: February 8, 2016 | Permit id: 2015-261905-000 | |||||
Venting of all bathrooms fans, range and dryer for each apartment unit(23) vent in fresh air for common area one ptac 15 btu for each apartment. Heating all the common areas with the ductless minisplit Date: January 7, 2016Permit type: Intake | Permit status: Closed | Completion date: January 7, 2016 | Permit id: 2016-101796-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Request | Permit status: Closed | Completion date: February 8, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Application | Permit status: Approved | Completion date: November 6, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Issuance/intake | Permit status: Intake | Completion date: November 6, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: November 12, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 4, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 3, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 17, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 19, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: January 7, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: January 14, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: December 2, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: March 31, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: March 18, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: February 24, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Process management | Permit status: Closed | Completion date: March 11, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Addressing | Permit status: Approved | Completion date: December 9, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Planning and zoning | Permit status: Approved | Completion date: February 25, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Planning and zoning | Permit status: Approved | Completion date: February 22, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Planning and zoning | Permit status: Approved | Completion date: February 8, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Planning and zoning | Permit status: Approved | Completion date: March 21, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Erosion control | Permit status: Approved | Completion date: January 27, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Site development | Permit status: Required | Completion date: January 27, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Site development | Permit status: Approved | Completion date: January 27, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Life safety | Permit status: Approved | Completion date: December 15, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Life safety | Permit status: Approved | Completion date: January 7, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Structural | Permit status: Required | Completion date: February 8, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Structural | Permit status: Approved | Completion date: February 23, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Commercial plumbing | Permit status: Approved | Completion date: January 15, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Special inspections review | Permit status: Approved | Completion date: February 3, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Special inspections review | Permit status: Approved | Completion date: April 4, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Fire bureau | Permit status: Approved | Completion date: April 1, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Environmental services | Permit status: Approved | Completion date: January 22, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Transportation | Permit status: Approved | Completion date: December 7, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Transportation | Permit status: Approved | Completion date: January 26, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Transportation | Permit status: Approved | Completion date: January 19, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Water bureau review | Permit status: Approved | Completion date: February 19, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Water bureau review | Permit status: Approved | Completion date: February 10, 2016 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Parks bureau | Permit status: Approved | Completion date: December 28, 2015 | Permit id: 2015-261905-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Permit type: Parks bureau | Permit status: Approved | Completion date: February 8, 2016 | Permit id: 2015-261905-000 | |||||
Demolish sfr, cap sewer, remove all debris, no fill greater than 24", subject to 35 day demo delay. No fill greater than 24". Date: December 4, 2015Client: North Portland Neighborhood Services | Permit type: Demolition | Permit status: Under inspection | Current use: Single family dwelling | Permit id: 2015-257565-000 | |||||
New construction of three story, 23-unit apartment complex; no on-site parking Date: July 15, 2016Client: North Portland Neighborhood Services | Permit type: New construction | Permit status: Under inspection | Current use: Apartments/condos (3 or more units) | Permit id: 2015-261905-000 |