ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Demolition/rebuild Date: May 28, 2015Permit type: Demolition or move p | Permit status: Finaled | Completion date: July 21, 2015 | Current use: Single family dwelling | Permit id: 701329 | |||||
Please do not request inspections under this permit until 2 business days after permit issuance. Date: October 31, 2014Permit type: Electrical permit | Permit status: Finaled | Completion date: November 5, 2014 | Current use: Single family dwelling | Permit id: 693371 | |||||
Please do not request inspections under this permit until 2 business days after permit issuance. Date: September 29, 2015Permit type: Electrical permit | Permit status: Issued | Current use: Single family dwelling | Permit id: 730351 | |||||
Residential demo/rebuild - new heating/cooling equipment & ductwork Date: October 22, 2015Permit type: Mechanical permit | Permit status: Issued | Current use: Single family dwelling | Permit id: 733351 | |||||
Demo/rebuild Date: May 28, 2015 Value: $800,000Permit type: Building residential | Permit status: Issued | Current use: Single family dwelling | Permit id: 706564 | |||||
80amp generator Date: May 19, 2016Permit type: Electrical permit | Permit status: Finaled | Current use: Single family dwelling | Permit id: 756275 | |||||
Install riser and cable to provide 4 amp underground service to new single family home, install cable and associated equipmentin accordance with pepco plan no. 3484736. Work shall comply with montgomery county specifications for utility construction permit, the direction of the dps inspector and in accordance with the public right-of-way accessibility guidelines (prowag). A mill and overlay shall be required should the patch not meet the specifications as set forth by the current county specifications for utility construction permit and as directed by the dps row inspector. All lane closures/traffic controls shall comply with the mcdot approved traffic control plans, work zone temporary traffic control standards and directions of the dps row inspector. Must check mcdot paving project schedule and have preconstruction meeting with dps row inspector prior to beginning of construction work. Date: August 25, 2015Permit type: Public right of way | Permit status: Issued | Current use: Public utility | Permit id: 343271 | |||||
Dw permit (residential) remove existing driveway and construct mc-301. 05 type driveway in accordance with montgomery county standards and specifications. Work shall be complete as directed by the dps row inspector and in accordance with the public right-of-way accessibility guidelines (prowag). Complete repair (restoration of right of way) shall be made of any and all damages done to existing improvements in the public right of way caused by construction operations on this site. All lane and sidewalk closures/traffic controls shall comply with the mcdot approved traffic control plans, work zone temporary traffic control standards and directions of the dps row inspector. (maryland dnr permit is required prior to remove/impact street trees. Complete tree protection and replanting per mc dps approved tree protection plan.) see tree protection plan fortree protectionmeasures that are to be used on row trees. Date: May 28, 2015Permit type: Public right of way | Permit status: Completed | Current use: Driveway | Permit id: 333108 | |||||
Abandon and install gas service in accordance with washington gas plan no. 507573. Work shall comply with montgomery county specifications for utility construction permit, the direction of the dps inspector and in accordance with the public right-of-way accessibility guidelines (prowag). A mill and overlay shall be required should the patch not meet the specifications as set forth by the current county specifications for utility construction permit and as directed by the dps row inspector. All lane closures/traffic controls shall comply with the mcdot approved traffic control plans, work zone temporary traffic control standards and directions of the dps row inspector. Permittee must check and coordinate with mcdot paving project schedule and have preconstruction meeting with dps row inspector prior to beginning of construction work. Date: March 26, 2015Permit type: Public right of way | Permit status: Issued | Current use: Public utility | Permit id: 333293 |