Exterior lighting upgrade Date: March 11, 2015Permit type: Electrical inspections | Permit status: Approved | Completion date: March 19, 2015 | Permit id: 2015-132208-000 | |||||
Excavation of contaminated soils and replace with clean fill, remove and replace existing asphalt parking lot Date: September 13, 2012Permit type: Application | Permit status: Approved | Completion date: August 7, 2012 | Permit id: 2012-169324-000 | |||||
Install storm water harvest system / refund request routed to mliefeld 9/10/2014 / Date: August 5, 2014Permit type: Application | Permit status: Approved | Completion date: May 13, 2014 | Permit id: 2014-156242-000 | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Application | Permit status: Approved | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Issuance/intake | Permit status: Approved to issue | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Plan review | Permit status: Closed | Completion date: September 10, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Process management | Permit status: Closed | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Addressing | Permit status: Not reqd | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Planning and zoning | Permit status: Approved | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Erosion control | Permit status: Not reqd | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Site development | Permit status: Approved | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Fire bureau | Permit status: Approved | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Environmental services | Permit status: Approved | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Value added revision to add 8 storm line and adjust pipe size per field conditions Permit type: Multnomah drainage districts | Permit status: Approved | Completion date: September 9, 2014 | Permit id: 2014-156242-Rev | |||||
Install waterharvest system/ add (3) catch basins and (1) backflow device 10/23/14 Date: September 10, 2014Permit type: Intake | Permit status: Closed | Completion date: September 10, 2014 | Permit id: 2014-210546-000 | |||||