ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Original permit description:(com2015-01916) rehabilitation/renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water he Date: November 16, 2015Permit id: Com2015-26820 | |||||
Rehabilitation/renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and ele Date: August 18, 2015 Value: $11,337,965Permit id: Com2015-01916 | |||||
Swap 12 antennas install 9 rrhs as per plans and as per code. Date: December 10, 2014 Value: $5,000Permit id: Com2014-41962 | |||||
Run 2 conduit along 1st floor from mechanical room to exist sprint / nextel shelter to fiber control box. As per plan & as per code. If installing suppression system in equipment cabinet then a separate permit is required. Date: May 18, 2012 Value: $10,000Permit id: Com2012-10112 | |||||
Add wiring to 1 additional telecommunication cabinet; add 1 new circuit; all work will be done as per code. Date: September 28, 2011 Value: $1,250Permit id: Com2011-21158 | |||||
Request for time extension on permit # com2010-20178 issued on 09-16- with amended completion date of 09-09-11. Original permit description:(com2010-20178)exterior work - clean and apply coatings to existing balconies; remove and replace (278) windows a Date: September 14, 2011Permit id: Com2011-19902 | |||||
"remove and replace in kind one (1) 12"" od schedule existing rain leader. Rain leader is cracked and is in need of replacement at the rear of the building. Approximately 1 l. Ft. Work done to code." Date: July 18, 2011 Value: $18,000Permit id: Com2011-14622 | |||||
"replacing existing uf wire and install 1 3/4"" pvc conduit to (10) existing pole lights as per code. Same size and location" Date: July 8, 2011 Value: $2,500Permit id: Com2011-14858 | |||||
Request for time extension on permit com2010-20178 issued on 09/16/ with original completion date of 03/09/10. Original permit description:(com2010-20178)exterior work - clean and apply coatings to existing balconies; remove and replace (278) windows an Date: March 10, 2011Permit id: Com2011-05095 | |||||
Security devices Date: February 16, 2011Permit id: Ele2011-00061 | |||||
Exterior work - clean and apply coatings to existing balconies; remove and replace (278) windows and (192) sliding glass balcony doors; replace (9) hollow metal exit doors; apply new exterior insulation finish system over complete exterior of building. No Date: September 16, 2010 Value: $2,678,000Permit id: Com2010-20178 | |||||
Request for time extension on permit # com2010-02642 issued on 02-12- with original completion date of 08-12-10. Original permit description:(com2010-02642)replace low voltage devices for boiler room only as per code Date: August 10, 2010Permit id: Com2010-17644 | |||||
Request for time extension on permit com2009-13621 issued on 09/25/09 with original completion date of 03/25/10. Original permit description:(com2009-13621)propose addition of (3)2. 5 2 and 0. 5 mw dish antenna to existing rooftop telecom site as per pl Date: June 18, 2010Permit id: Com2010-13163 | |||||
Replace low voltage devices for boiler room only as per code Date: February 12, 2010 Value: $7,000Permit id: Com2010-02642 | |||||
Installation of three(3) new antennas in addition to the existing vzw installation on the rooftop of the existing building as per plans as per code. If installing suppression system in equipment cabinets then a separate permit is required. Date: October 19, 2009 Value: $7,000Permit id: Com2009-18937 | |||||
Propose addition of (3)2. 5 2 and 0. 5 mw dish antenna to existing rooftop telecom site as per plans as per code. If installing suppression system in equipment cabinets then a separate permit will be required. Date: September 25, 2009 Value: $10,000Permit id: Com2009-13621 | |||||
Exterior work to replace old light fixture with new energy saving light fixtures as per code. Date: September 2, 2009 Value: $31,000Permit id: Com2009-20584 | |||||
(15) cameras interior (1) ptz camera (1) ptz pwr supply (11) camera pwr supplies and (1) digital recorder (low voltage) as per code. Date: May 1, 2008 Value: $40,925Permit id: Com2008-12276 | |||||
Request for time extension on permit# com2007-13018 issued on 4/27/07 with original completion date of 10/26/07. Date: November 5, 2007Permit id: Com2007-33983 | |||||
Ufas and ada modificationsinterior renovations to (20) dwelling units. Unit number are 105 205 305 405 505 103 203 303 101 201 301 401 501 104 204 304 404 405 403 & 503. Renovation shall consist of new kitchen cabinets counter tops and Date: April 27, 2007 Value: $650,000Permit id: Com2007-13018 | |||||
Nextel/sprint intends to replace all of the existing antennas located in sector (2) with new antennas that are 96 inches tall by 20. 5 inches wide and 9 inches deep. The new antennas will not exceed the height of the existing antennas. Nextel also intends Date: March 2, 2007 Value: $2,180Permit id: Com2007-02405 | |||||
Amend permit com2006-21865 issued on 08/17/06 with plans #2006-1177 to add contractor as listed above. Original permit description:(com2006-21865)relocat three antennas and replace three antennas using existing roof top mounts (structure height will not Date: January 12, 2007Permit id: Com2007-01286 | |||||
Relocat three antennas and replace three antennas using existing roof top mounts (structure height will not change) as per plans and code. Date: August 17, 2006 Value: $25,000Permit id: Com2006-21865 | |||||
Reinstate permit # com2004-26744 for final inspection Date: November 29, 2005Permit id: Com2005-36834 | |||||
Install fm-2 clean agent fire suppression system in the unmanned equipment room in the penthouse. Detection & activation circuits by others. Date: February 9, 2005 Value: $17,923Permit id: Com2005-02230 | |||||
Raise exist 7 head sprinkler system to reflect removal of drop ceiling. Date: February 9, 2005 Value: $3,820Permit id: Com2005-03445 | |||||
Amend permit #com2002-05039 issued 3/5/04 w/plans #2002742 to add electrical contactor as stated above. Date: January 21, 2005Permit id: Com2005-01789 | |||||
Disconnect & refeed (3) elevators with existing circuitreplace gfi typ of 3install 5 lights (remove & replaceprovide amp circuit for a/c unit(1) exhaust fan Date: October 26, 2004 Value: $20,000Permit id: Com2004-26744 | |||||
Amend permit #com2002-05039 issued 3/5/04 to change the construction of the proposed generator building from prefabicated to masonry per plans. Date: September 21, 2004 Value: $5,500Permit id: Com2004-21384 | |||||
Exterior work - clean and apply coatings to existing balconies; remove and replace (278) windows and (192) sliding glass balcony doors; replace (9) hollow metal exit doors; apply new exterior insulation finish system over complete exterior of building. No new electrical mechanical or plumbing work involved as per code. Date: September 16, 2010 Value: $2,678,000Expiration date: March 9, 2011 | Permit id: Com2010-20178 | |||||
Request for time extension on permit com2009-13621 issued on 09/25/09 with original completion date of 03/25/10. Original permit description:(com2009-13621)propose addition of (3)2. 5 2 and 0. 5 mw dish antenna to existing rooftop telecom site as per plans as per code. If installing suppression system in equipment cabinets then a separate permit will be required. Date: June 18, 2010Expiration date: December 18, 2010 | Permit id: Com2010-13163 | |||||
Request for time extension on permit com2010-20178 issued on 09/16/ with original completion date of 03/09/10. Original permit description:(com2010-20178)exterior work - clean and apply coatings to existing balconies; remove and replace (278) windows and (192) sliding glass balcony doors; replace (9) hollow metal exit doors; apply new exterior insulation finish system over complete exterior of building. No new electrical mechanical or plumbing work involved as per code. Date: March 10, 2011Expiration date: September 9, 2011 | Permit id: Com2011-05095 | |||||
Amend permit com2006-21865 issued on 08/17/06 with plans #2006-1177 to add contractor as listed above. Original permit description:(com2006-21865)relocat three antennas and replace three antennas using existing roof top mounts (structure height will not change) as per plans and code. Date: January 12, 2007Expiration date: February 17, 2007 | Permit id: Com2007-01286 | |||||
Nextel/sprint intends to replace all of the existing antennas located in sector (2) with new antennas that are 96 inches tall by 20. 5 inches wide and 9 inches deep. The new antennas will not exceed the height of the existing antennas. Nextel also intends to re-orient all of the sector (1) antennas on azimuth of 45 degrees and sector (3) antennas on an azimuth of 288 degress as per plans and codeper bmza 89-01 approved 5/15/01amended dec. 5 2006 Date: March 2, 2007 Value: $2,180Expiration date: September 2, 2007 | Permit id: Com2007-02405 | |||||
Remove and replace in kind one (1) 12" od schedule existing rain leader. Rain leader is cracked and is in need of replacement at the rear of the building. Approximately 1 l. Ft. Work done to code. Date: July 18, 2011 Value: $18,000Expiration date: January 16, 2012 | Permit id: Com2011-14622 | |||||
Replacing existing uf wire and install 1 3/4" pvc conduit to (10) existing pole lights as per code. Same size and location Date: July 8, 2011 Value: $2,500Expiration date: January 8, 2012 | Permit id: Com2011-14858 | |||||
Request for time extension on permit # com2010-20178 issued on 09-16- with amended completion date of 09-09-11. Original permit description:(com2010-20178)exterior work - clean and apply coatings to existing balconies; remove and replace (278) windows and (192) sliding glass balcony doors; replace (9) hollow metal exit doors; apply new exterior insulation finish system over complete exterior of building. No new electrical mechanical or plumbing work involved as per code. Date: September 14, 2011Expiration date: March 14, 2012 | Permit id: Com2011-19902 | |||||
Ufas and ada modificationsinterior renovations to (20) dwelling units. Unit number are 105 205 305 405 505 103 203 303 101 201 301 401 501 104 204 304 404 405 403 & 503. Renovation shall consist of new kitchen cabinets counter tops and appliances. Repair and replace existing plumbing fixtures. Replace vct flooring. Replace interior/exterior doors and windows as required. Repair and replace drywall. Replace heating units. Relocate electrical panel. All work listed be per building code. Date: April 27, 2007 Value: $650,000Expiration date: October 26, 2007 | Permit id: Com2007-13018 | |||||
Rehabilitation/renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and electrical devices and controls roofing system with membrane roofing over rigid insulation board project accessibility upgrades include (20) apartment units to comply with full ufas requirements and (5) apartment units to comply with visual/hearing impairment (vhi) requirements common areas will be outfitted with new finishes throughout with the exception of the exisitng corridor resilient finish flooring reconfigured program includes conversion of the medical office suite on the first floor to (2) apartment units creation of a new fitness room resident services office tenant council office and computer room apartment units will be upgraded with new appliances and fixtures new finish flooring and painting new kitchen and bathroom cabinetry and cou Date: August 18, 2015 Value: $11,337,965Expiration date: August 18, 2017 | Permit id: Com2015-01916 | |||||
Original permit description:(com2015-01916) rehabilitation/renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and electrical devices and controls roofing system with membrane roofing over rigid insulation board project accessibility upgrades include (20) apartment units to comply with full ufas requirements and (5) apartment units to comply with visual/hearing impairment (vhi) requirements common areas will be outfitted with new finishes throughout with the exception of the exisitng corridor resilient finish flooring reconfigured program includes conversion of the medical office suite on the first floor to (2) apartment units creation of a new fitness room resident services office tenant council office and computer room apartment units will be upgraded with new appliances and fixtures new finish flooring and paintin Date: November 6, 2015Expiration date: August 18, 2017 | Permit id: Com2015-26607 | |||||
Original permit description:(com2015-01916) rehabilitation/renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and electrical devices and controls roofing system with membrane roofing over rigid insulation board project accessibility upgrades include (20) apartment units to comply with full ufas requirements and (5) apartment units to comply with visual/hearing impairment (vhi) requirements common areas will be outfitted with new finishes throughout with the exception of the exisitng corridor resilient finish flooring reconfigured program includes conversion of the medical office suite on the first floor to (2) apartment units creation of a new fitness room resident services office tenant council office and computer room apartment units will be upgraded with new appliances and fixtures new finish flooring and paintin Date: January 27, 2016Expiration date: August 18, 2017 | Permit id: Com2016-01889 | |||||
Construct unmanned equipment room in penthouse of existing building and install 12 antennas on a feet high triangular mounting frame with brick screen wall on all sides match existing brick on the roof of the existing building and construct a generator building with an above gound diesel tank located beneath the proposed generator as per plans. Per bmza 255-03 approved 10/28/03 Date: March 5, 2004 Value: $70,000Expiration date: March 5, 2005 | Permit id: Com2002-05039 | |||||
Install 1 additional equipment cabinet on exist rooftop platform and remove and replace antennas as per plans Date: May 23, 2003 Value: $28,000Expiration date: November 23, 2003 | Permit id: Com2003-25790 | |||||
Furnish and install firef service opertions phase 1 and phase 2 on 3 elevators low voltage wiring Date: June 4, 2003 Value: $45,000Expiration date: December 4, 2003 | Permit id: Com2003-29421 | |||||
Amend permit#com2003-257 issued on 5-23-03 with plans# 2003-528 to name prime and electrical contractor as named above. Date: July 30, 2003Expiration date: January 30, 2004 | Permit id: Com2003-33696 | |||||
Replace of old elevator equipment as per plans Date: June 11, 2004 Value: $259,765Expiration date: December 11, 2005 | Permit id: Com2004-11088 | |||||
Replace existing fire alarm panel with new fire alarm panel ( all other fire alarm work by others ) as per plans and as per code. Date: June 13, 2016 Value: $39,465Expiration date: December 13, 2016 | Permit id: Com2015-28503 | |||||
Rehabilitation renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and electrical devices and controls roofing system with membrane roofing over rigid insulation board project accessibility upgrades include (20) apartment units to comply with full ufas requirements and (5) apartment units to comply with visual hearing impairment (vhi) requirements common areas will be outfitted with new finishes throughout with the exception of the exisitng corridor resilient finish flooring reconfigured program includes conversion of the medical office suite on the first floor to (2) apartment units creation of a new fitness room resident services office tenant council office and computer room apartment units will be upgraded with new appliances and fixtures new finish flooring and painting new kitchen and bathroom cabinetry and cou Date: August 18, 2015 Value: $11,337,965Expiration date: August 18, 2017 | Permit id: Com2015-01916 | |||||
Original permit description:(com2015-01916) rehabilitation renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and electrical devices and controls roofing system with membrane roofing over rigid insulation board project accessibility upgrades include (20) apartment units to comply with full ufas requirements and (5) apartment units to comply with visual hearing impairment (vhi) requirements common areas will be outfitted with new finishes throughout with the exception of the exisitng corridor resilient finish flooring reconfigured program includes conversion of the medical office suite on the first floor to (2) apartment units creation of a new fitness room resident services office tenant council office and computer room apartment units will be upgraded with new appliances and fixtures new finish flooring and paintin Date: November 16, 2015Expiration date: August 18, 2017 | Permit id: Com2015-26820 | |||||
Original permit description:(com2015-01916) rehabilitation renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and electrical devices and controls roofing system with membrane roofing over rigid insulation board project accessibility upgrades include (20) apartment units to comply with full ufas requirements and (5) apartment units to comply with visual hearing impairment (vhi) requirements common areas will be outfitted with new finishes throughout with the exception of the exisitng corridor resilient finish flooring reconfigured program includes conversion of the medical office suite on the first floor to (2) apartment units creation of a new fitness room resident services office tenant council office and computer room apartment units will be upgraded with new appliances and fixtures new finish flooring and paintin Date: January 27, 2016Expiration date: August 18, 2017 | Permit id: Com2016-01889 | |||||
Extend original permit.(original permit:com2015-01916:original permit description:(com2015-01916) rehabilitation renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and electrical devices and controls roofing system with membrane roofing over rigid insulation board project accessibility upgrades include (20) apartment units to comply with full ufas requirements and (5) apartment units to comply with visual hearing impairment (vhi) requirements common areas will be outfitted with new finishes throughout with the exception of the exisitng corridor resilient finish flooring reconfigured program includes conversion of the medical office suite on the first floor to (2) apartment units creation of a new fitness room resident services office tenant council office and computer room apartment units will be upgraded with new a Date: September 13, 2017Expiration date: March 12, 2018 | Permit id: Com2017-60152 | |||||
Extend original permit.(original permit:com2015-01916: rehabilitation renovation of a five-story apartment building systems will be updated replacement all common space and apartment unit hvac equipment domestic water piping (mains laterals and risers) water heating plumbing fixtures lighting and electrical devices and controls roofing system with membrane roofing over rigid insulation board project accessibility upgrades include (20) apartment units to comply with full ufas requirements and (5) apartment units to comply with visual hearing impairment (vhi) requirements common areas will be outfitted with new finishes throughout with the exception of the exisitng corridor resilient finish flooring reconfigured program includes conversion of the medical office suite on the first floor to (2) apartment units creation of a new fitness room resident services office tenant council office and computer room apartment units will be upgraded with new appliances and fixtures new finish flooring Date: September 13, 2017Expiration date: March 13, 2018 | Permit id: Com2017-61475 | |||||
Amend permit com2006-21865 issued on 08 17 06 with plans #2006-1177 to add contractor as listed above. Original permit description:(com2006-21865)relocat three antennas and replace three antennas using existing roof top mounts (structure height will not change) as per plans and code. Date: January 12, 2007Expiration date: February 17, 2007 | Permit id: Com2007-01286 | |||||
Nextel sprint intends to replace all of the existing antennas located in sector (2) with new antennas that are 96 inches tall by 20. 5 inches wide and 9 inches deep. The new antennas will not exceed the height of the existing antennas. Nextel also intends to re-orient all of the sector (1) antennas on azimuth of 45 degrees and sector (3) antennas on an azimuth of 288 degress as per plans and codeper bmza 89-01 approved 5 15 01amended dec. 5 2006 Date: March 2, 2007 Value: $2,180Expiration date: September 2, 2007 | Permit id: Com2007-02405 | |||||
Ufas and ada modificationsinterior renovations to (20) dwelling units. Unit number are 105 205 305 405 505 103 203 303 101 201 301 401 501 104 204 304 404 405 403 & 503. Renovation shall consist of new kitchen cabinets counter tops and appliances. Repair and replace existing plumbing fixtures. Replace vct flooring. Replace interior exterior doors and windows as required. Repair and replace drywall. Replace heating units. Relocate electrical panel. All work listed be per building code. Date: April 27, 2007 Value: $650,000Expiration date: October 26, 2007 | Permit id: Com2007-13018 | |||||
Request for time extension on permit# com2007-13018 issued on 4 27 07 with original completion date of 10 26 07. Date: November 5, 2007Permit id: Com2007-33983 | |||||
Amend permit #com2002-05039 issued 3 5 04 to change the construction of the proposed generator building from prefabicated to masonry per plans. Date: September 21, 2004 Value: $5,500Expiration date: March 21, 2005 | Permit id: Com2004-21384 | |||||
Disconnect & refeed (3) elevators with existing circuitreplace gfi typ of 3install 5 lights (remove & replaceprovide amp circuit for a c unit(1) exhaust fan Date: October 26, 2004 Value: $20,000Expiration date: April 26, 2005 | Permit id: Com2004-26744 | |||||
Amend permit #com2002-05039 issued 3 5 04 w plans #2002742 to add electrical contactor as stated above. Date: January 21, 2005Expiration date: July 21, 2005 | Permit id: Com2005-01789 | |||||
Replacing existing uf wire and install 1 3 4" pvc conduit to (10) existing pole lights as per code. Same size and location Date: July 8, 2011 Value: $2,500Expiration date: January 8, 2012 | Permit id: Com2011-14858 | |||||
Run 2 conduit along 1st floor from mechanical room to exist sprint nextel shelter to fiber control box. As per plan & as per code. If installing suppression system in equipment cabinet then a separate permit is required. Date: May 18, 2012 Value: $10,000Expiration date: May 18, 2013 | Permit id: Com2012-10112 | |||||
Request for time extension on permit com2009-13621 issued on 09 25 09 with original completion date of 03 25 10. Original permit description:(com2009-13621)propose addition of (3)2. 5 2 and 0. 5 mw dish antenna to existing rooftop telecom site as per plans as per code. If installing suppression system in equipment cabinets then a separate permit will be required. Date: June 18, 2010Expiration date: December 18, 2010 | Permit id: Com2010-13163 | |||||
Construct unmanned equipment room in penthouse of existing building and install 12 antennas on a feet high triangular mounting frame with brick screen wall on all sides match existing brick on the roof of the existing building and construct a generator building with an above gound diesel tank located beneath the proposed generator as per plans. Per bmza 255-03 approved 10 28 03 Date: March 5, 2004 Value: $70,000Expiration date: March 5, 2005 | Permit id: Com2002-05039 | |||||
Request for time extension on permit com2010-20178 issued on 09 16 with original completion date of 03 09 10. Original permit description:(com2010-20178)exterior work - clean and apply coatings to existing balconies; remove and replace (278) windows and (192) sliding glass balcony doors; replace (9) hollow metal exit doors; apply new exterior insulation finish system over complete exterior of building. No new electrical mechanical or plumbing work involved as per code. Date: March 10, 2011Expiration date: September 9, 2011 | Permit id: Com2011-05095 |