Property line adjustment at lots 2 and 3 Permit type: Land use review | Permit status: Closed | Completion date: November 24, 2014 | Permit id: 2014-241560-000 | |||||
Property line adjustment at lots 2 and 3 Permit type: Land use review | Permit status: Approved | Completion date: January 16, 2015 | Permit id: 2014-241560-000 | |||||
Property line adjustment at lots 2 and 3 Permit type: Land use review | Permit status: Closed | Completion date: January 26, 2015 | Permit id: 2014-241560-000 | |||||
Property line adjustment at lots 2 and 3 Permit type: Life safety | Permit status: Response sent | Completion date: December 11, 2014 | Permit id: 2014-241560-000 | |||||
Property line adjustment at lots 2 and 3 Permit type: Environmental services | Permit status: Response sent | Completion date: December 16, 2014 | Permit id: 2014-241560-000 | |||||
Property line adjustment at lots 2 and 3 Permit type: Transportation | Permit status: Closed | Completion date: December 30, 2014 | Permit id: 2014-241560-000 | |||||
Property line adjustment at lots 2 and 3 Permit type: Water bureau review | Permit status: Response sent | Completion date: December 17, 2014 | Permit id: 2014-241560-000 | |||||
Temporary power underground conduits Date: February 9, 2015Permit type: Intake | Permit status: Closed | Completion date: February 9, 2015 | Permit id: 2015-116690-000 | |||||
1 hour inspection for underground pipe with electrical serving sump pumps in northeast corner of site Date: March 3, 2015Permit type: Intake | Permit status: Closed | Completion date: March 3, 2015 | Permit id: 2015-127825-000 | |||||
1 hour inspection for underground pipe with electrical serving sump pumps in west side of site Date: March 3, 2015Permit type: Intake | Permit status: Closed | Completion date: March 3, 2015 | Permit id: 2015-127833-000 | |||||
(6) floor drains, (6) sumps, and 1 feet of drainage piping for foundation Date: March 4, 2015Permit type: Intake | Permit status: Closed | Completion date: March 4, 2015 | Permit id: 2015-128098-000 | |||||
Sprinkler-complete wet, dry, stanpipe system Date: June 26, 2015Permit type: Intake | Permit status: Approved | Completion date: March 17, 2015 | Permit id: 2015-135146-000 | |||||
1 hour inspection for underslab conduit Date: May 12, 2015Permit type: Intake | Permit status: Closed | Completion date: May 12, 2015 | Permit id: 2015-169564-000 | |||||
75 unit building. Largest unit is 11 sqft - oar 918 reduced fees apply only to residential units. Permit type: Intake | Permit status: Closed | Completion date: May 19, 2015 | Permit id: 2015-172840-000 | |||||
It is the decision of the design commission to approve design review for a new 10-story mixed-use building at block 75; 131,158 square feet in area (148,997 square feet in area including the below-grade parking), 104-4 tall; with below-grade parking stalls and two below-grade loading spaces, ground-floor retail space, about 32,0 square feet of office space, and 75 housing units; with an east-west pedestrian path along the north edge of the building, located in the central eastside subdistrict of the central city plan district. Approval of the following modification request: 1. To provide two on-site loading spaces that are each 18 feet long x 9 feet wide, with a clearance of 9 feet (pzc section 33. 266. 310. D: loading standards; size of loading spaces). Approvals per exhibits c. 1-c-89, signed, stamped, and dated august 21, 2014, subject to the following conditions: Date: July 1, 2015Permit type: Land use review | Permit status: Completed | Completion date: June 3, 2014 | Permit id: 2014-163479-000 | |||||
New story mixed use building with below grade parking and building services. Retail at ground floor, 3 stories of commercial office and 75 residential units Date: March 18, 2015Permit type: Application | Permit status: Approved | Completion date: September 22, 2014 | Permit id: 2014-168827-000 | |||||
Dfs for post tension cables - floors 1-3 Date: May 8, 2015Permit type: Application | Permit status: Approved | Completion date: April 8, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for embeds for curtainwall system Permit type: Application | Permit status: Approved | Completion date: April 17, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for embeds for curtainwall system Permit type: Issuance/intake | Permit status: Intake | Completion date: April 17, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for embeds for curtainwall system Permit type: Life safety | Permit status: Not reqd | Completion date: April 23, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for metal stairs Date: June 3, 2015Permit type: Application | Permit status: Approved | Completion date: April 27, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for post tension cables - floors 4-11(roof) Date: June 12, 2015Permit type: Application | Permit status: Approved | Completion date: May 8, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for curtain walls Permit type: Application | Permit status: Approved | Completion date: June 30, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for curtain walls Permit type: Issuance/intake | Permit status: Intake | Completion date: July 1, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for curtain walls Permit type: Process management | Permit status: Closed | Completion date: July 1, 2015 | Permit id: 2014-168827-Dfs | |||||
Excavation and shoring for 9 story multi use apartment building Date: September 15, 2014Permit type: Application | Permit status: Approved | Completion date: June 30, 2014 | Permit id: 2014-168827-Exc | |||||
Foundation, structural wall and columns up to pt Date: February 19, 2015Permit type: Application | Permit status: Approved | Completion date: February 17, 2015 | Permit id: 2014-168827-Fnd | |||||
Revision 1- revision to shoring drawings, a portion of the cantilevered shoring has been replaced by ultrablock where the retained height is less than 3-0. Date: January 30, 2015Permit type: Application | Permit status: Approved | Completion date: December 24, 2014 | Permit id: 2014-168827-Rev | |||||
Rev 2 - 2 slab elevations at level 01 are revised due to grading issues and to remove ramps at east retail entries. Drop band depths and stairs to these floors. Levels 02 and 03 have slab edge revisions that effect the pt tendon elevations at edge of slab. Slab in nw plaza stepped and beam added to match arch Date: April 27, 2015Permit type: Application | Permit status: Approved | Completion date: March 27, 2015 | Permit id: 2014-168827-Rev | |||||
Rev 3 - pge transformer vault is revised to be a class a vault with access from the basement. Date: June 12, 2015Permit type: Application | Permit status: Approved | Completion date: May 18, 2015 | Permit id: 2014-168827-Rev | |||||
Three 10-ton and one 7. 5-ton gas packs for corridors & apt mua w/fds at apt walls, vrf for commercial spaces, ductless splits for misc common spaces, garage exhaust, elev & stair pressurization, apt bath, kit & dryer subduct on epwr, plans w/co Date: March 18, 2015Permit type: Intake | Permit status: Closed | Completion date: September 23, 2014 | Permit id: 2014-216297-000 | |||||
Rev 1- hvac changesone 10t hru/gp, one-10t doas/gp and one 4t doas/gp, three 30t and one 14t vrv for commercial spaces, hp splits for apts, subduct on epwr, elev & stair pressure fans on epwr, garage exhaust Date: June 16, 2015Permit type: Intake | Permit status: Closed | Completion date: May 18, 2015 | Permit id: 2014-216297-Rev | |||||
Plumbing for new story mixed use building Date: October 16, 2015Permit type: Intake | Permit status: Closed | Completion date: October 16, 2015 | Permit id: 2015-251833-000 | |||||
Gas piping for story building, plans w/co Date: January 6, 2016Permit type: Intake | Permit status: Closed | Completion date: October 16, 2015 | Permit id: 2015-251857-000 | |||||
Alarm - fire alarm installation for new building Date: November 10, 2015Permit type: Intake | Permit status: Approved | Completion date: October 30, 2015 | Permit id: 2015-258635-000 | |||||
Install t-stats and wiring for 3 new roof top units, 4 vrv systems and 12 split systems, limited energy only. Date: November 2, 2015Permit type: Intake | Permit status: Closed | Completion date: November 2, 2015 | Permit id: 2015-259300-000 | |||||
Install captive air type one duct for future tenant Date: December 1, 2015Permit type: Intake | Permit status: Closed | Completion date: December 1, 2015 | Permit id: 2015-271060-000 | |||||
Alarm - installation of das system Date: February 10, 2016Permit type: Intake | Permit status: Approved | Completion date: January 13, 2016 | Permit id: 2016-105294-000 | |||||
First time ti for new office tenant on levels two and three; new offices, meeting rooms, common area and lobby areas Date: April 20, 2016Permit type: Application | Permit status: Approved | Completion date: February 3, 2016 | Permit id: 2016-115854-000 | |||||
Add a third grease duct to existing grease duct shaft, fire wrapped Date: February 9, 2016Permit type: Intake | Permit status: Closed | Completion date: February 9, 2016 | Permit id: 2016-118424-000 | |||||
It is the decision of the design commission to approve design review for a new 10-story mixed-use building at block 75; 131,158 square feet in area (148,997 square feet in area including the below-grade parking), 104-4 tall; with below-grade parking stalls and two below-grade loading spaces, ground-floor retail space, about 32,0 square feet of office space, and 75 housing units; with an east-west pedestrian path along the north edge of the building, located in the central eastside subdistrict of the central city plan district. Approval of the following modification request: 1. To provide two on-site loading spaces that are each 18 feet long x 9 feet wide, with a clearance of 9 feet (pzc section 33. 266. 310. D: loading standards; size of loading spaces). Approvals per exhibits c. 1-c-89, signed, stamped, and dated august 21, 2014, subject to the following conditions: Date: September 5, 2014Permit type: Land use review | Permit status: Completed | Completion date: June 3, 2014 | Permit id: 2014-163479-000 | |||||
Dfs for curtain walls Date: January 29, 2016Permit type: Application | Permit status: Approved | Completion date: June 30, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for roof tie back safety system Date: November 9, 2015Permit type: Application | Permit status: Approved | Completion date: October 9, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for exterior glass guardrails Date: December 23, 2015Permit type: Application | Permit status: Approved | Completion date: November 4, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for mechanical roof rack attachments Date: March 4, 2016Permit type: Application | Permit status: Approved | Completion date: December 30, 2015 | Permit id: 2014-168827-Dfs | |||||
Dfs for plaza stairs Date: March 30, 2016Permit type: Application | Permit status: Approved | Completion date: January 15, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs for exterior aluminum panels Date: March 30, 2016Permit type: Application | Permit status: Approved | Completion date: January 15, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs for roof hatch and ships ladder Permit type: Application | Permit status: Approved | Completion date: March 25, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs for roof hatch and ships ladder Permit type: Issuance/intake | Permit status: Intake | Completion date: March 25, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs for roof hatch and ships ladder Permit type: Structural | Permit status: Approved | Completion date: April 22, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs rooftop mechanical screen panels Permit type: Application | Permit status: Approved | Completion date: April 15, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs rooftop mechanical screen panels Permit type: Issuance/intake | Permit status: Intake | Completion date: April 15, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs rooftop mechanical screen panels Permit type: Process management | Permit status: Closed | Completion date: April 24, 2016 | Permit id: 2014-168827-Dfs | |||||
Rev 04- second means of egress from comercial lobby revised. Amenity spaces added to floors 5, 6, 7. Units 500,501,600,601,700,701 adjusted for amenity space. Unit 800,900,10 bathroom revised due to changes on floors below. Step at roof door threshold added to accommodate insulation thickness. Structural stud gauge revised. Date: March 25, 2016Permit type: Application | Permit status: Approved | Completion date: October 29, 2015 | Permit id: 2014-168827-Rev | |||||
75 unit building. Largest unit is 11 sqft - oar 918 reduced fees apply only to residential units. Date: December 15, 2015Permit type: Intake | Permit status: Closed | Completion date: May 19, 2015 | Permit id: 2015-172840-000 | |||||
Gas piping for story building, plans w co Date: January 6, 2016Permit type: Intake | Permit status: Closed | Completion date: October 16, 2015 | Permit id: 2015-251857-000 | |||||
Dfs for roof hatch and ships ladder Permit type: Application | Permit status: Approved | Completion date: March 25, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs for roof hatch and ships ladder Permit type: Issuance/intake | Permit status: Intake | Completion date: March 25, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs for roof hatch and ships ladder Permit type: Structural | Permit status: Approved | Completion date: April 22, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs rooftop mechanical screen panels Permit type: Application | Permit status: Approved | Completion date: April 15, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs rooftop mechanical screen panels Permit type: Issuance/intake | Permit status: Intake | Completion date: April 15, 2016 | Permit id: 2014-168827-Dfs | |||||
Dfs rooftop mechanical screen panels Permit type: Process management | Permit status: Closed | Completion date: April 24, 2016 | Permit id: 2014-168827-Dfs | |||||
Three 10-ton and one 7. 5-ton gas packs for corridors & apt mua w fds at apt walls, vrf for commercial spaces, ductless splits for misc common spaces, garage exhaust, elev & stair pressurization, apt bath, kit & dryer subduct on epwr, plans w co Date: March 18, 2015Permit type: Intake | Permit status: Closed | Completion date: September 23, 2014 | Permit id: 2014-216297-000 | |||||
Rev 1- hvac changesone 10t hru gp, one-10t doas gp and one 4t doas gp, three 30t and one 14t vrv for commercial spaces, hp splits for apts, subduct on epwr, elev & stair pressure fans on epwr, garage exhaust Date: June 16, 2015Permit type: Intake | Permit status: Closed | Completion date: May 18, 2015 | Permit id: 2014-216297-Rev | |||||
Ti for new tenant; add new walls to create new restroom, changing room, storage room, surfboard repair room, cafe prep area, and retail area. Modify sprinkler system. Date: September 2, 2016Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: November 18, 2016 | Current use: Mercantile | Permit id: 2016-167053-000 | |||||
Exterior landscaped plaza with integrated seating and planters in the vacated portion of ne couch street Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Approved to issue | Current use: Apartments/condos (3 or more units) | Permit id: 2016-288763-000 |