Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 New industrial shell bldg w/office & restrm 10,423 sq ft bldg 25 Applicant: Fuentes Manuel | Permit status: Finaled | Completion date: May 12, 2006 | Permit id: 0412270013 | |||||
SCORE 90 Fire sprinklers 132 heads 10423 sq ft Applicant: Jm Carden Sprinkler Co | Permit status: Finaled | Completion date: May 12, 2006 | Permit id: 0508090096 | |||||
SCORE 98 Electrical for new industrial shell bldg w/office & restrm bldg 25 Date: August 25, 2005 Contractor: Southern Power Inc Applicant: Southern Power Inc | Permit status: Finaled | Completion date: May 12, 2006 | Permit id: 0508250042 | |||||
SCORE 91 Elect for machining equipment Date: July 5, 2006 Contractor: Maxwell Electric Applicant: Maxwell Electric | Permit status: Finaled | Completion date: August 10, 2006 | Permit id: 0606290054 | |||||
SCORE 91 New elect for additional machining equipment Date: August 21, 2006 Contractor: Maxwell Electric Applicant: Maxwell Electric | Permit status: Finaled | Completion date: July 20, 2007 | Permit id: 0608210011 | |||||
SCORE 99 Install htng vent a/c system Date: August 25, 2005 Contractor: Wittler Young Co. Inc Applicant: Wittler Young Co.,Inc Frank | Permit status: Finaled | Completion date: May 12, 2006 | Permit id: 0508250034 | |||||
SCORE 98 Plumb. For new comm bldg Date: August 17, 2005 Contractor: Andersen Commercial Plumbing Applicant: Andersen Commercial Plumbing Inc | Permit status: Finaled | Completion date: May 12, 2006 | Permit id: 0508170013 | |||||
Install new gas line for t-shirt dryer Date: August 3, 2006 Applicant: Jacoby Eric/jennifer | Permit status: Finaled | Completion date: August 10, 2006 | Permit id: 0608030008 |