ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Complaint received: leaves and vegetation on sidewalk. Slip hazard. Photo in trackit Date: May 4, 2015Permit type: Request | Permit status: Closed | Completion date: May 4, 2015 | Permit id: 2015-157918-000 | |||||
It is the decision of the design commission to approve design review for the renovation of the existing ymca building in the terwilliger parkway design district, per exhibits c-1 through c-43 and including the following verbal agreements and changes to the exhibits: the proposed paint color and integral cement plaster finish color will be a dark green-ish color rather than the dark gray specified in the c exhibits; the proposed vertical wood fins that will enclose the parking level will be angled on their vertical axis as necessary to prevent views into the parking lot from the sidewalk on sw barbur blvd and from duniway park; the proposed vertical wood fins will extend south along the new concrete wall which will help to enclose a portion of the parking garage near the new entry vestibule on the east faade; the applicant will explore methods to incorporate bird-friendly design features in the proposed glazed curtain wall system and in other new windows; and, should activities related Date: October 29, 2015Permit type: Land use review | Permit status: Completed | Completion date: July 24, 2015 | Permit id: 2015-205150-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Application | Permit status: Approved | Completion date: November 10, 2015 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Issuance/intake | Permit status: Intake | Completion date: November 10, 2015 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Process management | Permit status: Closed | Completion date: March 11, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Process management | Permit status: Closed | Completion date: April 13, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Process management | Permit status: Closed | Completion date: April 8, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Planning and zoning | Permit status: Approved | Completion date: March 18, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Life safety | Permit status: Required | Completion date: April 11, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Life safety | Permit status: Approved | Completion date: April 14, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Life safety | Permit status: Not reqd | Completion date: November 20, 2015 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Structural | Permit status: Required | Completion date: April 11, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Structural | Permit status: Required | Completion date: April 19, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Special inspections review | Permit status: Approved | Completion date: April 13, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Fire bureau | Permit status: Approved | Completion date: April 14, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Environmental services | Permit status: Approved | Completion date: April 14, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby/bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Transportation | Permit status: Approved | Completion date: November 23, 2015 | Permit id: 2015-250848-000 | |||||
Dfs for aluminium framed storefront and doors and aluminium curtainwall. Permit type: Application | Permit status: Approved | Completion date: March 30, 2016 | Permit id: 2015-250848-Dfs | |||||
Dfs for aluminium framed storefront and doors and aluminium curtainwall. Permit type: Issuance/intake | Permit status: Intake | Completion date: March 30, 2016 | Permit id: 2015-250848-Dfs | |||||
Dfs for aluminium framed storefront and doors and aluminium curtainwall. Permit type: Process management | Permit status: Admin hold | Completion date: March 31, 2016 | Permit id: 2015-250848-Dfs | |||||
Partial - a) demolition of exterior east and north facades; b) demolition of interior partitions and casework; and c) demolition of exterior site elements to the east and north of the building. Mechanical, electrical and plumbing contractors to obtain separate demolition permits.) no occupancy during construction. Date: December 7, 2015Permit type: Application | Permit status: Approved | Completion date: October 21, 2015 | Permit id: 2015-250848-Dmo | |||||
Revision - remove a 12 maple that is in conflict with a new structural footing Date: March 30, 2016Permit type: Application | Permit status: Approved | Completion date: March 24, 2016 | Permit id: 2015-250848-Rev | |||||
Revision - revised survey of existing tree to be removed from 12 to actual 37 diameter and pruning specification Date: April 12, 2016Permit type: Application | Permit status: Approved | Completion date: April 12, 2016 | Permit id: 2015-250848-Rev | |||||
Intake pw Permit status: Assigned | Completion date: February 14, 2016 | Permit id: 2016-113009-000 | |||||
Intake pw Permit status: Assigned | Completion date: February 6, 2016 | Permit id: 2016-113009-000 | |||||
Pre-design pw Permit status: Not reqd | Completion date: February 6, 2016 | Permit id: 2016-113009-000 | |||||
Pre-design pw Permit status: Received | Completion date: January 28, 2016 | Permit id: 2016-113009-000 | |||||
Pre-design pw Permit status: Accepted for review | Completion date: February 10, 2016 | Permit id: 2016-113009-000 | |||||
Pre-design pw Permit status: Completed | Completion date: April 12, 2016 | Permit id: 2016-113009-000 | |||||
Plan review pw Permit status: Corrections required | Completion date: March 2, 2016 | Permit id: 2016-113009-000 | |||||
Plan review pw Permit status: Approved | Completion date: April 12, 2016 | Permit id: 2016-113009-000 | |||||
Pre-issuance pw Permit status: Not reqd | Completion date: February 14, 2016 | Permit id: 2016-113009-000 | |||||
Install new service and connect core and shell equipment Date: April 14, 2016Permit type: Intake | Permit status: Closed | Completion date: February 1, 2016 | Permit id: 2016-114071-000 | |||||
Plumbing fixtures-6 fixture caps, 1 floor drains, 1 hose bib, interior piping, water heater and expansion tank Date: March 10, 2016Permit type: Intake | Permit status: Closed | Completion date: March 10, 2016 | Permit id: 2016-133345-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Application | Permit status: Approved | Completion date: November 10, 2015 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Issuance/intake | Permit status: Intake | Completion date: November 10, 2015 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Process management | Permit status: Closed | Completion date: March 11, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Process management | Permit status: Closed | Completion date: April 13, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Process management | Permit status: Closed | Completion date: April 8, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Planning and zoning | Permit status: Approved | Completion date: March 18, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Life safety | Permit status: Required | Completion date: April 11, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Life safety | Permit status: Approved | Completion date: April 14, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Life safety | Permit status: Not reqd | Completion date: November 20, 2015 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Structural | Permit status: Required | Completion date: April 11, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Structural | Permit status: Required | Completion date: April 19, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Special inspections review | Permit status: Approved | Completion date: April 13, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Fire bureau | Permit status: Approved | Completion date: April 14, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Environmental services | Permit status: Approved | Completion date: April 14, 2016 | Permit id: 2015-250848-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Permit type: Transportation | Permit status: Approved | Completion date: November 23, 2015 | Permit id: 2015-250848-000 | |||||
Dfs for aluminium framed storefront and doors and aluminium curtainwall. Permit type: Application | Permit status: Approved | Completion date: March 30, 2016 | Permit id: 2015-250848-Dfs | |||||
Dfs for aluminium framed storefront and doors and aluminium curtainwall. Permit type: Issuance/intake | Permit status: Intake | Completion date: March 30, 2016 | Permit id: 2015-250848-Dfs | |||||
Dfs for aluminium framed storefront and doors and aluminium curtainwall. Permit type: Process management | Permit status: Admin hold | Completion date: March 31, 2016 | Permit id: 2015-250848-Dfs | |||||
Intake pw Permit status: Assigned | Completion date: February 14, 2016 | Permit id: 2016-113009-000 | |||||
Intake pw Permit status: Assigned | Completion date: February 6, 2016 | Permit id: 2016-113009-000 | |||||
Pre-design pw Permit status: Not reqd | Completion date: February 6, 2016 | Permit id: 2016-113009-000 | |||||
Pre-design pw Permit status: Received | Completion date: January 28, 2016 | Permit id: 2016-113009-000 | |||||
Pre-design pw Permit status: Accepted for review | Completion date: February 10, 2016 | Permit id: 2016-113009-000 | |||||
Pre-design pw Permit status: Completed | Completion date: April 12, 2016 | Permit id: 2016-113009-000 | |||||
Plan review pw Permit status: Corrections required | Completion date: March 2, 2016 | Permit id: 2016-113009-000 | |||||
Plan review pw Permit status: Approved | Completion date: April 12, 2016 | Permit id: 2016-113009-000 | |||||
Pre-issuance pw Permit status: Not reqd | Completion date: February 14, 2016 | Permit id: 2016-113009-000 | |||||
Core and shell renovation including demolition of interior partitions, casework and mep systems. Installation of new curatin wall system at north curved facade, barbur entry revisions and parking lobby bike parking renovations. Mech, elect, plumibng and fire protection under separate permit and are not being reviewed under this permit, including the demolition work. Date: June 3, 2016Client: Southwest Neighborhoods, Inc. | Permit type: Alteration | Permit status: Under inspection | Current use: Business | Permit id: 2015-250848-000 | |||||
Ti for new tenant; new offices, meeting spaces, workshops, gyms, stairs and associated support spaces; renovations to the parking level include the addition of access control equipment and visitor area partitions Date: December 7, 2016Client: Southwest Neighborhoods, Inc. | Permit type: Alteration | Permit status: Issued | Current use: Business | Permit id: 2016-209258-000 |