Approval of design review for alterations to existing development at the pine street studios building in the central eastside subdistrict of the central city plan district, to include the following: restriping of the parking lot from 13 spaces to spaces; addition of a 6 wide concrete pedestrian walkway from the west entry to se pine street; new larger steel panel-enclosed, flat-roofed trash enclosure in the same location as the existing trash enclosure; new area of p1 interior parking lot landscaping along the new ada parking space; new 5 feet of l2 landscaping between the trash enclosure and the sidewalk on se pine. Infilling arched openings on rear building additions east and south facades with dark bronze anodized aluminum framed storefront glazing and doors (option a) or dark bronze anodized aluminum framed storefront glazing and doors with one area of open metal mesh (option b); installing one new dark bronze anodized aluminum framed slider window in the south faade, in an existin Date: July 28, 2014Permit type: Land use review | Permit status: Completed | Completion date: March 11, 2014 | Permit id: 2014-124124-000 | |||||
Revise ash st. Exit stair & gate; addition to enlarge (e) office space from 715 sf to 14 sf, create opening between (e) boiler room an (e) office, raise floor in boiler room to match office, remove (e) boiler room ramp. New window opening in south wall of boiler room, new storefront and window openings for office. Demolish ramp in boiler room & (e) exterior office walls. Add accessible parking, route from sidewalk. No occupancy this permit. Comcheck for interior lighting and toilet rooms required with separate tenant improvement permit. Date: April 16, 2015Permit type: Application | Permit status: Approved | Completion date: August 27, 2014 | Permit id: 2014-204687-000 | |||||
Value added revision to create larger opening between boiler room and office, change to structural design, create chase opening for future ductwork Date: June 23, 2015Permit type: Application | Permit status: Approved | Completion date: June 23, 2015 | Permit id: 2014-204687-Rev | |||||
Build new detached covered trash enclosure, 288 sf Date: April 16, 2015Permit type: Application | Permit status: Approved | Completion date: August 27, 2014 | Permit id: 2014-204692-000 | |||||
Ti for existing tenant; new door between units 104 and 106; relocating existing sinks for handwash area Date: August 26, 2015Permit type: Application | Permit status: Approved | Completion date: August 26, 2015 | Permit id: 2015-226046-000 | |||||
Sprinklers-add two new dry sidewalls, remove three dry sidewalls, add one upright head in kitchen Date: September 14, 2015Permit type: Intake | Permit status: Approved | Completion date: September 14, 2015 | Permit id: 2015-235756-000 | |||||
Wire a rooftop hvac unit Date: April 4, 2016Permit type: Intake | Permit status: Closed | Completion date: April 4, 2016 | Permit id: 2016-144770-000 | |||||
New walls, bar, and seating area to convert office space to new restaurant. Exterior walls, doors, and windows are existing and not altered. Walk-in cooler under separate permit. Date: April 5, 2016Permit type: Application | Permit status: Approved | Completion date: April 5, 2016 | Permit id: 2016-145488-000 | |||||
Plumbing for commercial ti of existing space. Date: April 18, 2016Permit type: Intake | Permit status: Closed | Completion date: April 18, 2016 | Permit id: 2016-154636-000 | |||||
Create opening between tenant spaces, remove interior ramp and raise floor; at service entry replace interior stairs with ramp - no occupancy this permit Permit type: Application | Permit status: Approved | Completion date: December 11, 2013 | Permit id: 2013-236874-000 | |||||
Create opening between tenant spaces, remove interior ramp and raise floor; at service entry replace interior stairs with ramp - no occupancy this permit Permit type: Application | Permit status: Closed | Completion date: December 11, 2013 | Permit id: 2013-236874-000 | |||||
Create opening between tenant spaces, remove interior ramp and raise floor; at service entry replace interior stairs with ramp - no occupancy this permit Permit type: Planning and zoning | Permit status: Not reqd | Completion date: December 11, 2013 | Permit id: 2013-236874-000 | |||||
Install 1 1/2 double check on building water main Date: July 14, 2015Permit type: Plumbing inspections | Permit status: Approved | Completion date: July 15, 2015 | Permit id: 2015-201293-000 | |||||
Sight lighting Date: July 16, 2015Permit type: Intake | Permit status: Closed | Completion date: July 16, 2015 | Permit id: 2015-202420-000 | |||||
Replace 70ft of on property sanitary sewer Date: August 3, 2015Permit type: Intake | Permit status: Closed | Completion date: August 3, 2015 | Permit id: 2015-203173-000 | |||||
Create opening between tenant spaces, remove interior ramp and raise floor; at service entry replace interior stairs with ramp - no occupancy this permit Permit type: Application | Permit status: Approved | Completion date: December 11, 2013 | Permit id: 2013-236874-000 | |||||
Create opening between tenant spaces, remove interior ramp and raise floor; at service entry replace interior stairs with ramp - no occupancy this permit Permit type: Application | Permit status: Closed | Completion date: December 11, 2013 | Permit id: 2013-236874-000 | |||||
Create opening between tenant spaces, remove interior ramp and raise floor; at service entry replace interior stairs with ramp - no occupancy this permit Permit type: Planning and zoning | Permit status: Not reqd | Completion date: December 11, 2013 | Permit id: 2013-236874-000 | |||||
Install 1 1 2 double check on building water main Date: July 14, 2015Permit type: Plumbing inspections | Permit status: Approved | Completion date: July 15, 2015 | Permit id: 2015-201293-000 | |||||
Construct three walls to create a new room in an existing assembly room. No change of occupancy this permit. Maintain 100% sprinkler and alarm coverage under separate permit from fire marshals office. See folder comments Date: September 4, 2001Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: March 6, 2002 | Current use: Assembly | Permit id: 2001-156481-000 | |||||
Adding two interior partion walls and change of occ. From a to e. - see comments Date: April 8, 2002Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: June 7, 2006 | Current use: Educational | Permit id: 2001-155106-000 | |||||
Replace min fire rated door in to rated corridor. Original use has been maintained, no change of occupancy. Date: March 17, 2004Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: March 22, 2004 | Current use: Business | Permit id: 2004-010245-000 | |||||
Ti - first floor renovation of (e) build change of occupancy from a to b : mezzanine addition (3 separate in areas 4, 5, 6). Total increase in occupancy is negative. Square footage of addition is approximately 1067 square feet. No seismic upgrade at this time. Date: April 1, 2005Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: March 17, 2006 | Current use: Business | Permit id: 2005-118184-000 | |||||
Remodel existing commercial kitchen, add sink, grease trap, etc. Date: July 12, 2005Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: February 5, 2009 | Current use: Business | Permit id: 2005-143435-000 | |||||
New tenant, interior vestibule, exit door Date: December 16, 2005Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: March 17, 2006 | Current use: Assembly | Permit id: 2005-180667-000 | |||||
Interior ti for new tenant, bakery(vegan), three compartment sinks, etc. Change of occupancy from b to f1 Date: March 3, 2006Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: July 7, 2006 | Current use: Business | Permit id: 2006-113275-000 | |||||
Convert portion of exisitng building to restaurant--maintain b occupancy, reconfigure stairs. Date: November 20, 2006Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: March 8, 2007 | Current use: Business | Permit id: 2006-170840-000 | |||||
Ti- change health clinic to fitness center--retrofit beams and columns to support added gymnasium equipment Date: August 6, 2010Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: September 14, 2012 | Current use: Assembly | Permit id: 2010-163526-000 | |||||
Retrofit beams and columns to support added gymnasium equipment in second studio space Date: August 23, 2012Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: March 20, 2013 | Current use: Assembly | Permit id: 2012-169833-000 | |||||
Install walk in cooler Date: July 21, 2016Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: September 16, 2016 | Current use: Business | Permit id: 2016-209067-000 | |||||
Ti for existing tenant; change of use from office to prep kitchen; install new plumbing fixtures and work table Date: August 19, 2016Client: Southeast Uplift Neighborhood Program | Permit type: Alteration | Permit status: Final | Completion date: September 13, 2016 | Current use: Business | Permit id: 2016-227187-000 |