ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Replace water main in accordance with wssc plans and specifications. Work shall comply with ada requirements, montgomery county specifications for utility construction permit and the direction of the dps inspector. A mill and overlay shall be required should the patch not meet the specifications as set forth by the current county specifications for utility construction permit and as directed by the dps row inspector. All lane closures and traffic controls shall comply with the mcdot approved traffic control plans, work zone temporary traffic control standards and directions of the dps row inspector. Date: November 22, 2011Permit type: Public right of way | Permit status: Finaled | Current use: Public utility | Permit id: 271983 |