| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Remove and replace 9-doors & 25-windows Date: November 13, 2015Permit type: Commercial building trade permit | Permit status: Issued | Expiration date: January 3, 2017 | Current use: Commercial | Permit id: Btr-16-0448661 | |||||
Install a building wall sign Date: January 6, 2016Permit type: Commercial miscellaneous permit | Permit status: Complete | Completion date: March 29, 2016 | Expiration date: October 2, 2016 | Current use: Commercial | Permit id: Bld-16-0442909 | |||||
Early start issued for interior only - contractor understands plans may not be approved for change of occupancy. Change of use renovate existing second floor from hotel rooms into vanilla shell office space. Includes demolition, new partitions, new finishes, and upgrades to mechanical, electrical and plumbing systems. To include modifications to existing fire sprinkler and alarm system. This project consists of the renovation of an existing hotel floor into new office space. The new areas being built out will be new vanilla shell office areas for future open office areas or tenant spaces, and two office areas being partitioned out with private offices, one on the 2nd floor north east tenant space and a new tenant space in the 1st floor northeast tenant space to include a new restroom. The project will also consist of work in the common corridors lobby on the 2nd floor and the construction of new common restrooms on the 2nd floor. The work will also consist of upgrades to the structure Date: January 9, 2017Permit type: Commercial building alterations (renovations) | Permit status: In process | Expiration date: July 23, 2017 | Current use: Commercial | Permit id: Bld-17-0449704 | |||||
Installation of new fire alarm system. Attach to gc permit #bld-16-0447483 Date: November 14, 2016Permit type: Commercial miscellaneous permit | Permit status: Complete | Completion date: December 7, 2016 | Expiration date: June 10, 2017 | Current use: Commercial | Permit id: Bld-17-0448363 | |||||
Hvac: attached are the revised installation modifications you requested during your field inspection. Fire dampers were added to outdoor air ducts entering the l-3 suite from the second floor above. Also, a fire damper detail has been added. In regards to the energy calculation submission, we have attached the exemption status paragraph waiving the requirement for this calculation. Due to the historic nature of the facility, an energy calculation is not required per florida building code: energy conservation-2014, 5th edition. We have highlighted this paragraph for your convenience. Also, the pvc condensate lines located in any air plenum will be totally wrapped with a fire retardant insulation similar to armaflex fr or approved equal. Plumbing: mr. Frank paleveda the use of cpvc pipe with solvent fittings for domestic cold and water lines are approved by engineer of record. Date: October 18, 2016Permit type: Building plan revision | Permit status: Complete | Completion date: October 27, 2016 | Current use: Revision | Permit id: Bld-16-0447483- | |||||
Interior renovation of the 1st floor of an existing historic building to create new office space. The work will include new 1-hour walls to create tenant corridor, new offices, and new bathrooms consisting of new interior partitions, glass partitions, finishes, and mechanical, electrical, plumbing. Relocation modification of existing fire sprinkler and alarm as required for new layout and space. Date: September 2, 2016Permit type: Commercial utility application | Permit status: Complete | Completion date: October 13, 2016 | Current use: Commercial | Permit id: Utl-16-0001775 | |||||
Existing conditions field coordination changes to hvac condenser unit locations on roof and associated chase work. Please note this project is under expedited review - thank you! Date: November 8, 2016Permit type: Building plan revision | Permit status: Complete | Completion date: November 22, 2016 | Current use: Revision | Permit id: Bld-16-0447483- | |||||
Interior renovation of the 1st floor of an existing historic building to create new office space. The work will include new 1-hour walls to create tenant corridor, new offices, and new bathrooms consisting of new interior partitions, glass partitions, finishes, and mechanical, electrical, plumbing. Relocation modification of existing fire sprinkler and alarm as required for new layout and space. Date: October 13, 2016Permit type: Commercial building alterations (renovations) | Permit status: Complete | Completion date: December 29, 2016 | Expiration date: July 2, 2017 | Current use: Commercial | Permit id: Bld-16-0447483 | |||||
Tco request for use of areas completed and final inspected, the areas completed are entire 1st floor with exception of se space which is to remain vacant until tenant is acquired. Entire 2nd floor execpt ne space with some work to remain. The areas to remain vacant or require work are se space on 1st floor (vacant until future tenant), 2nd floor ne office area (2000sf)-millwork, flooring, plumbing and electrical trim out still be completed in 2nd fl ne. Basement to remain vacant and still needs mechanical closet and soffit to be completed. All areas have active sprinkler and fire alarm. Date: June 6, 2017Permit type: Commercial temp certificate of occupancy | Permit status: In process | Expiration date: June 6, 2017 | Current use: Commercial | Permit id: Bld-17-0449704- | |||||
Early start issued for interior only - contractor understands plans may not be approved for change of occupancy. Change of use renovate existing second floor from hotel rooms into vanilla shell office space. Includes demolition, new partitions, new finishes, and upgrades to mechanical, electrical and plumbing systems. To include modifications to existing fire sprinkler and alarm system. This project consists of the renovation of an existing hotel floor into new office space. The new areas being built out will be new vanilla shell office areas for future open office areas or tenant spaces, and two office areas being partitioned out with private offices, one on the 2nd floor north east tenant space and a new tenant space in the 1st floor northeast tenant space to include a new restroom. The project will also consist of work in the common corridors lobby on the 2nd floor and the construction of new common restrooms on the 2nd floor. The work will also consist of upgrades to the structure Date: February 20, 2017Permit type: Commercial building alterations (renovations) | Permit status: Issued | Expiration date: December 12, 2017 | Current use: Commercial | Permit id: Bld-17-0449704 | |||||
Temporary certificate of occupancy for the added use of the area completed for the tenant on the 2nd floor, the 2nd floor northeast space. (shown on shaded drawing) Date: July 20, 2017Permit type: Commercial temp certificate of occupancy | Permit status: Complete | Completion date: July 24, 2017 | Expiration date: July 20, 2017 | Current use: Commercial | Permit id: Bld-17-0449704- |