ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Restoration and erosion of man made drainage gully to control drainage with a series of check dams to direct storm flows and limit lateral scour, slow water velocity, trap sediment, and stabilize the bottom and bank of the lower section (+100) of the gully. (135 cubic yards cut and 135 cubic yards fill) Date: August 26, 2015Client: Del Monte Foundation Inc (del Monte Forest Conservancy) | Permit type: Grading | Permit status: Open | Permit id: 15cp02159 | |||||
Grading of approximately 395 cubic yards of cut and cubic yards of fill for a temporary parking lot. Date: June 16, 2017Client: Pebble Beach Company | Permit status: Incomplete | Permit id: 17cp01665 |