ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
New building for switch gear ; berm around new transformer; new stormwater details-no occupancy Permit type: Application | Permit status: Approved | Completion date: March 2, 2015 | Permit id: 2015-127240-000 | |||||
Well field splice Date: August 21, 2015Permit type: Intake | Permit status: Closed | Completion date: August 21, 2015 | Permit id: 2015-222922-000 | |||||
Foundation for new prefab building for switch gear ; berm around new transformer; new stormwater details-no occupancy, prefab building to be deferred submittal, see option 4 from city handout Date: December 4, 2015Permit type: Application | Permit status: Approved | Completion date: July 10, 2015 | Permit id: 2015-127240-000 | |||||
Move electrical substation to new location on same property demolish existing concrete pad see in take process for items Date: April 6, 2000Client: East Portland Neighborhood Office | Permit type: Move | Permit status: Final | Completion date: January 28, 2003 | Current use: Utility | Permit id: 2000-127932-000 | |||||
Wellhead structure for well #36 improvements over a municipal water wel Date: January 31, 2001Client: East Portland Neighborhood Office | Permit type: Addition | Permit status: Under inspection | Current use: Utility | Permit id: 2000-151789-000 | |||||
New chemical bldg, water mains, dechlorination basin, new pavement, landscaping. Seismic stabilizing improvements to existing facilities via embedded stone columns in vicinity of new and existing facilities. Additional water mains. Calcs to follow. Date: June 26, 2002Client: East Portland Neighborhood Office | Permit type: New construction | Permit status: Under inspection | Current use: Hazardous | Permit id: 2000-195516-000 | |||||
Alteration - control bldg - interior only reconfigure lab Date: June 26, 2002Client: East Portland Neighborhood Office | Permit type: Alteration | Permit status: Final | Completion date: February 27, 2004 | Current use: Utility | Permit id: 2001-100544-000 | |||||
Tent permit. Duration 7 10 03 to 8 10 03. Separate tent permit is required from fire marshals office. (1) x and (2) x 15 for uv validation testing - see comments Date: July 7, 2003Client: East Portland Neighborhood Office | Permit type: New construction | Permit status: Issued | Current use: Factory/industrial | Permit id: 2003-144994-000 | |||||
Replace (e) fence with high fence and conc. Footing as well as gate and access road Date: October 21, 2003Client: East Portland Neighborhood Office | Permit type: Alteration | Permit status: Issued | Current use: Factory/industrial | Permit id: 2003-159615-000 | |||||
Build new cmu wall at electrical transformer, add new gates, bases for security camera poles (2 each) Date: June 29, 2005Client: East Portland Neighborhood Office | Permit type: New construction | Permit status: Under inspection | Current use: Factory/industrial | Permit id: 2005-130432-000 | |||||
Solar pv panel - 7 ground mounted solar arrays connected to one inverter within fenced enclosure. Date: August 26, 2009Client: East Portland Neighborhood Office | Permit type: New construction | Permit status: Final | Completion date: December 18, 2009 | Current use: Utility | Permit id: 2009-116897-000 | |||||
Build 14 x 28 cover for existing solar panel equipment. Roof is solid, sides are open. Date: December 2, 2009Client: East Portland Neighborhood Office | Permit type: Alteration | Permit status: Final | Completion date: December 18, 2009 | Current use: Utility | Permit id: 2009-171114-000 | |||||
9. 8 kw solar pv panel solar installation of solar panels Date: January 20, 2012Client: East Portland Neighborhood Office | Permit type: Alteration | Permit status: Final | Completion date: February 22, 2012 | Current use: Hazardous | Permit id: 2012-105625-000 |