ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
The soil borings will be advanced, as close as possible to the location on figure two, using a geoprobe soilboring will be advanced to 15 below the ground surface bg or to refusal if encountered above 15 feet. All downhole equipment will be decontaminated prior to utilization, and between borings. The soil borings diameter will be about two inch, also dome borings will be converted to monitoring point. Installation of eight temporary soil borings, as per site plas, work plan report, dc well construction form and dc well schematic form, for the jemaiz buzzard point, llc Date: August 15, 2012Client: Jemalz Buzzard Point | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Sb1200309 |