New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Application | Permit status: Approved | Completion date: November 21, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Issuance/intake | Permit status: Intake | Completion date: November 21, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Process management | Permit status: Closed | Completion date: November 26, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Process management | Permit status: Closed | Completion date: April 17, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Process management | Permit status: Closed | Completion date: April 23, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Process management | Permit status: Closed | Completion date: June 16, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Process management | Permit status: Closed | Completion date: June 10, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Addressing | Permit status: Approved | Completion date: December 10, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Erosion control | Permit status: Approved | Completion date: December 22, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Site development | Permit status: Required | Completion date: December 22, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Site development | Permit status: Approved | Completion date: December 22, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Life safety | Permit status: Approved | Completion date: June 26, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Life safety | Permit status: Approved | Completion date: June 25, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Structural | Permit status: Required | Completion date: June 26, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Structural | Permit status: Required | Completion date: April 30, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Structural | Permit status: Required | Completion date: December 29, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Commercial plumbing | Permit status: Not reqd | Completion date: December 15, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Fire bureau | Permit status: Approved | Completion date: June 17, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Transportation | Permit status: Approved | Completion date: December 22, 2014 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Water bureau review | Permit status: Approved | Completion date: June 19, 2015 | Permit id: 2014-241075-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Permit type: Parks bureau | Permit status: Approved | Completion date: December 29, 2014 | Permit id: 2014-241075-000 | |||||
Pthps for apartments, ductless split for lobby, tempered supply for corridors, restroom exhaust in wrapped joist bay, plans w/co Permit type: Intake | Permit status: Closed | Completion date: November 21, 2014 | Permit id: 2014-241080-000 | |||||
Pthps for apartments, ductless split for lobby, tempered supply for corridors, restroom exhaust in wrapped joist bay, plans w/co Permit type: Process management | Permit status: Closed | Completion date: June 10, 2015 | Permit id: 2014-241080-000 | |||||
Pthps for apartments, ductless split for lobby, tempered supply for corridors, restroom exhaust in wrapped joist bay, plans w/co Permit type: Mechanical review | Permit status: Approved | Completion date: June 25, 2015 | Permit id: 2014-241080-000 | |||||
Pthps for apartments, ductless split for lobby, tempered supply for corridors, restroom exhaust in wrapped joist bay, plans w/co Permit type: Fire bureau | Permit status: Not reqd | Completion date: December 4, 2014 | Permit id: 2014-241080-000 | |||||
Intake pw Permit status: Assigned | Completion date: June 19, 2015 | Permit id: 2015-188762-000 | |||||
Intake pw Permit status: Assigned | Completion date: June 25, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Not reqd | Completion date: June 25, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Received | Completion date: June 19, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Accepted for review | Completion date: June 23, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Billed | Completion date: June 25, 2015 | Permit id: 2015-188762-000 | |||||
Row pbot note location Date: September 20, 2011Permit type: Intake | Permit status: Closed | Completion date: September 20, 2011 | Permit id: 2011-178157-000 | |||||
Complaint received - illegal dump site. This is stuff that was at one point in the parking lot of the svi. Now dumped in the vacant lot southwest corner of sumner & interstate. Photos in trackit Date: July 25, 2014Permit type: Request | Permit status: Closed | Completion date: July 23, 2014 | Permit id: 2014-184151-000 | |||||
San/st conn: 217 lf of 10ncp combo main, approx d=10, in n sumner st. Contractor connect to existing branch per std p-262 (approx l=18 and d=10) 44 from ds smh (aaq179) sewer & install 6x6 wye at curb line for separated sanitary & storm lines to property. Contractor to verify all depths and locations in field. Contact x37869 Date: December 10, 2015Permit type: Intake | Permit status: Closed | Completion date: December 10, 2015 | Permit id: 2015-275463-000 | |||||
Install sanitary and storm sewer on property Date: December 10, 2015Permit type: Intake | Permit status: Closed | Completion date: December 10, 2015 | Permit id: 2015-275468-000 | |||||
Install complete plumbing to 25 guests units and retail space Date: February 17, 2016Permit type: Intake | Permit status: Closed | Completion date: February 17, 2016 | Permit id: 2016-122415-000 | |||||
Sprinkler-automatic sprinkler fire protection system for new apartment buiilding. Permit type: Intake | Permit status: Approved | Completion date: April 11, 2016 | Permit id: 2016-149258-000 | |||||
Sprinkler-automatic sprinkler fire protection system for new apartment buiilding. Permit type: Intake | Permit status: Closed | Completion date: April 11, 2016 | Permit id: 2016-149258-000 | |||||
New construction of 25-unit apartment building with partial ground floor retail; interior bike parking; attached trash enclosure with eco roof above, no onsite parking Date: December 10, 2015Permit type: Application | Permit status: Approved | Completion date: November 21, 2014 | Permit id: 2014-241075-000 | |||||
Dfs for anchor tiedown system Date: February 26, 2016Permit type: Application | Permit status: Approved | Completion date: January 27, 2016 | Permit id: 2014-241075-Dfs | |||||
Revision-replacement of street tree at n sumner st. With (2) new street trees, relocation of (2) bike parking spaces, change in elevator type, addition of mailboxes at lobby, addition of recessed smoke curtains at elevator doors, revised exterior materials, elimination of upper facade element Permit type: Application | Permit status: Approved | Completion date: April 19, 2016 | Permit id: 2014-241075-Rev | |||||
Revision-replacement of street tree at n sumner st. With (2) new street trees, relocation of (2) bike parking spaces, change in elevator type, addition of mailboxes at lobby, addition of recessed smoke curtains at elevator doors, revised exterior materials, elimination of upper facade element Permit type: Issuance/intake | Permit status: Intake | Completion date: April 19, 2016 | Permit id: 2014-241075-Rev | |||||
Revision-replacement of street tree at n sumner st. With (2) new street trees, relocation of (2) bike parking spaces, change in elevator type, addition of mailboxes at lobby, addition of recessed smoke curtains at elevator doors, revised exterior materials, elimination of upper facade element Permit type: Process management | Permit status: Closed | Completion date: April 24, 2016 | Permit id: 2014-241075-Rev | |||||
Revision-replacement of street tree at n sumner st. With (2) new street trees, relocation of (2) bike parking spaces, change in elevator type, addition of mailboxes at lobby, addition of recessed smoke curtains at elevator doors, revised exterior materials, elimination of upper facade element Permit type: Life safety | Permit status: Approved | Completion date: April 21, 2016 | Permit id: 2014-241075-Rev | |||||
Pthps for apartments, ductless split for lobby, tempered supply for corridors, restroom exhaust in wrapped joist bay, plans w/co Date: December 10, 2015Permit type: Intake | Permit status: Closed | Completion date: November 21, 2014 | Permit id: 2014-241080-000 | |||||
Intake pw Permit status: Assigned | Completion date: June 19, 2015 | Permit id: 2015-188762-000 | |||||
Intake pw Permit status: Assigned | Completion date: June 25, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Not reqd | Completion date: June 25, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Received | Completion date: June 19, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Accepted for review | Completion date: June 23, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Completed | Completion date: October 26, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Billed | Completion date: November 23, 2015 | Permit id: 2015-188762-000 | |||||
Utility review - all Permit status: No additional review | Completion date: August 18, 2015 | Permit id: 2015-188762-000 | |||||
Plan review pw Permit status: Appr w/corr | Completion date: October 15, 2015 | Permit id: 2015-188762-000 | |||||
Bond/insurance pw Permit status: Approved | Completion date: November 13, 2015 | Permit id: 2015-188762-000 | |||||
Pre-issuance pw Permit status: Completed | Completion date: November 6, 2015 | Permit id: 2015-188762-000 | |||||
San st conn: 217 lf of 10ncp combo main, approx d=10, in n sumner st. Contractor connect to existing branch per std p-262 (approx l=18 and d=10) 44 from ds smh (aaq179) sewer & install 6x6 wye at curb line for separated sanitary & storm lines to property. Contractor to verify all depths and locations in field. Contact x37869 Date: December 10, 2015Permit type: Intake | Permit status: Closed | Completion date: December 10, 2015 | Permit id: 2015-275463-000 | |||||
Sprinkler-automatic sprinkler fire protection system for new apartment buiilding. Permit type: Intake | Permit status: Approved | Completion date: April 11, 2016 | Permit id: 2016-149258-000 | |||||
Sprinkler-automatic sprinkler fire protection system for new apartment buiilding. Permit type: Intake | Permit status: Closed | Completion date: April 11, 2016 | Permit id: 2016-149258-000 | |||||
Revision-replacement of street tree at n sumner st. With (2) new street trees, relocation of (2) bike parking spaces, change in elevator type, addition of mailboxes at lobby, addition of recessed smoke curtains at elevator doors, revised exterior materials, elimination of upper facade element Permit type: Application | Permit status: Approved | Completion date: April 19, 2016 | Permit id: 2014-241075-Rev | |||||
Revision-replacement of street tree at n sumner st. With (2) new street trees, relocation of (2) bike parking spaces, change in elevator type, addition of mailboxes at lobby, addition of recessed smoke curtains at elevator doors, revised exterior materials, elimination of upper facade element Permit type: Issuance/intake | Permit status: Intake | Completion date: April 19, 2016 | Permit id: 2014-241075-Rev | |||||
Revision-replacement of street tree at n sumner st. With (2) new street trees, relocation of (2) bike parking spaces, change in elevator type, addition of mailboxes at lobby, addition of recessed smoke curtains at elevator doors, revised exterior materials, elimination of upper facade element Permit type: Process management | Permit status: Closed | Completion date: April 24, 2016 | Permit id: 2014-241075-Rev | |||||
Revision-replacement of street tree at n sumner st. With (2) new street trees, relocation of (2) bike parking spaces, change in elevator type, addition of mailboxes at lobby, addition of recessed smoke curtains at elevator doors, revised exterior materials, elimination of upper facade element Permit type: Life safety | Permit status: Approved | Completion date: April 21, 2016 | Permit id: 2014-241075-Rev | |||||
Pthps for apartments, ductless split for lobby, tempered supply for corridors, restroom exhaust in wrapped joist bay, plans w co Date: December 10, 2015Permit type: Intake | Permit status: Closed | Completion date: November 21, 2014 | Permit id: 2014-241080-000 | |||||
Intake pw Permit status: Assigned | Completion date: June 19, 2015 | Permit id: 2015-188762-000 | |||||
Intake pw Permit status: Assigned | Completion date: June 25, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Not reqd | Completion date: June 25, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Received | Completion date: June 19, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Accepted for review | Completion date: June 23, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Completed | Completion date: October 26, 2015 | Permit id: 2015-188762-000 | |||||
Pre-design pw Permit status: Billed | Completion date: November 23, 2015 | Permit id: 2015-188762-000 | |||||
Utility review - all Permit status: No additional review | Completion date: August 18, 2015 | Permit id: 2015-188762-000 | |||||
Plan review pw Permit status: Appr w/corr | Completion date: October 15, 2015 | Permit id: 2015-188762-000 | |||||
Bond/insurance pw Permit status: Approved | Completion date: November 13, 2015 | Permit id: 2015-188762-000 | |||||
Pre-issuance pw Permit status: Completed | Completion date: November 6, 2015 | Permit id: 2015-188762-000 | |||||
Demo existing commercial bldg Date: May 9, 2008Client: North Portland Neighborhood Services | Permit type: Demolition | Permit status: Final | Completion date: February 15, 2012 | Current use: Business | Permit id: 2008-124948-000 | |||||
Basement conversion to family room, new egress window, fur out falls Date: August 23, 2011Client: North Portland Neighborhood Services | Permit type: Alteration | Permit status: Final | Completion date: December 12, 2011 | Current use: Single family dwelling | Permit id: 2011-169905-000 | |||||
Remove door at hallway on main floor; and on second floor closet in master bedrom remove closet doors and replace with glulam beam at roof Date: October 12, 2011Client: North Portland Neighborhood Services | Permit type: Alteration | Permit status: Final | Completion date: December 12, 2011 | Current use: Single family dwelling | Permit id: 2011-184682-000 |