New cross dock warehouse and office building Date: July 24, 2013Permit type: Application | Permit status: Approved | Completion date: January 24, 2013 | Permit id: 2013-108530-000 | |||||
Dfs 01- stairs and handrails for cross dock building Date: November 24, 2014Permit type: Application | Permit status: Approved | Completion date: November 10, 2014 | Permit id: 2013-108530-Dfs | |||||
Dfs 02 - girders for cross dock building Date: December 8, 2014Permit type: Application | Permit status: Approved | Completion date: November 10, 2014 | Permit id: 2013-108530-Dfs | |||||
Attach sanitary sewer to existing line and add row of trees to screen along canal Date: August 16, 2013Permit type: Application | Permit status: Approved | Completion date: August 12, 2013 | Permit id: 2013-108530-Rev | |||||
Rev 2 - addition of stormdrain manhole to accomodate a storm drain line placed in the field Date: September 19, 2013Permit type: Application | Permit status: Approved | Completion date: September 13, 2013 | Permit id: 2013-108530-Rev | |||||
Revision of dock drain system, revision to inlet catch basin Date: May 21, 2014Permit type: Application | Permit status: Approved | Completion date: April 15, 2014 | Permit id: 2013-108530-Rev | |||||
New shop and maintenance bldg Date: July 24, 2013Permit type: Application | Permit status: Approved | Completion date: January 24, 2013 | Permit id: 2013-108534-000 | |||||
Shop bldg: steel stairs Date: November 24, 2014Permit type: Application | Permit status: Approved | Completion date: November 7, 2014 | Permit id: 2013-108534-Dfs | |||||
Dfs 2 -shop building - steel joists and girders Date: December 8, 2014Permit type: Application | Permit status: Approved | Completion date: November 7, 2014 | Permit id: 2013-108534-Dfs | |||||
Radiant heat in shop, misc exhausts, 2. 5-ton gas split, three unit heaters, plans w/co Date: July 24, 2013Permit type: Intake | Permit status: Closed | Completion date: January 24, 2013 | Permit id: 2013-108553-000 | |||||
Two 7. 5-ton, one 5-ton and three 3-ton gas packs, one 4-ton gas split, 14 misc exhausts, ductwork, gas piping, plans w/co Date: July 24, 2013Permit type: Intake | Permit status: Closed | Completion date: January 24, 2013 | Permit id: 2013-108554-000 | |||||
New shop, cross dock and site lighting Date: August 23, 2013Permit type: Intake | Permit status: Closed | Completion date: July 18, 2013 | Permit id: 2013-181825-000 | |||||
Trucking terminal with 19 acres of site improvements/ added 35 catch basins per correction notice Date: July 24, 2013Permit type: Intake | Permit status: Closed | Completion date: July 24, 2013 | Permit id: 2013-184274-000 | |||||
Sprinkler-new wet fire sprinkler system with a dry extension for the old dominion freight line shop building. Date: November 5, 2013Permit type: Intake | Permit status: Approved | Completion date: July 30, 2013 | Permit id: 2013-185593-000 | |||||
Sprinkler-new wet and dry fire sprinkler systems with a fire pump for the old dominion freight line terminal bldg see underground permit 13-195804fs Date: November 5, 2013Permit type: Intake | Permit status: Approved | Completion date: July 29, 2013 | Permit id: 2013-185603-000 | |||||
Hazardous/tanks -piping and installation of fuel site, including (2) 20k tanks9/16/13 description changed per revisions (per beutler): installation of (1) 20,000gal diesel tank and (2) 1,0 gal single wall def tanks and piping associated with the install. Date: September 16, 2013Permit type: Intake | Permit status: Approved | Completion date: August 8, 2013 | Permit id: 2013-190216-000 | |||||
Underground - install 8 underground fire line and 4 fire hydrants see sprinkler permit 13-185603fs 9/13/13 recd revised plans and calcs Date: September 19, 2013Permit type: Intake | Permit status: Approved | Completion date: August 21, 2013 | Permit id: 2013-195804-000 | |||||
Interior plumbing as per plan Date: September 16, 2013Permit type: Plumbing inspections | Permit status: Approved | Completion date: November 14, 2013 | Permit id: 2013-205287-000 | |||||
Fire alarm-installation of a new fire alarm system Date: October 18, 2013Permit type: Intake | Permit status: Approved | Completion date: October 4, 2013 | Permit id: 2013-213216-000 | |||||
Install diesel dispenser and def dispenser Date: December 18, 2013Permit type: Intake | Permit status: Closed | Completion date: December 18, 2013 | Permit id: 2013-239698-000 | |||||
Approval of an adjustment to zoning code section 33. 140. 245. C and table 140-6 to reduce the amount of landscaping for exterior storage from 25 feet of l3 to feet, per the approved site plans, exhibits c. 1 through c. 4, signed and dated september 23, 2014, subject to the following conditions:a. As part of the building permit application submittal, the following development-related conditions (b) must be noted on each of the 4 required site plans or included as a sheet in the numbered set of plans. The sheet on which this information appears must be labeled zoning compliance page - case file lu 14-164952 ad. All requirements must be graphically represented on the site plan, landscape, or other required plan and must be labeled required. B. The applicant will remove weeds and hydro-seed the area of the 30-foot odot easement on the property with grass as per odot specifications, to be completed by the time of final inspection. Date: September 24, 2014Permit type: Land use review | Permit status: Completed | Completion date: June 5, 2014 | Permit id: 2014-164952-000 | |||||
Old dominion-(2) low voltage energy circuits for security and access control Date: August 26, 2014Permit type: Electrical inspections | Permit status: Approved | Completion date: November 20, 2014 | Permit id: 2014-203856-000 | |||||
Installation of a low voltage security system fence Date: October 1, 2014Permit type: Electrical inspections | Permit status: Approved | Completion date: December 12, 2014 | Permit id: 2014-219732-000 | |||||
Access control system. Site:old dominion freight line. Tyco job 83-28336-1 Date: October 15, 2014Permit type: Electrical inspections | Permit status: Approved | Completion date: November 20, 2014 | Permit id: 2014-226173-000 | |||||
Hazardous material - tank - installed two storage tanks and plumbed oil to reel banks Date: October 16, 2014Permit type: Intake | Permit status: Approved | Completion date: October 16, 2014 | Permit id: 2014-226581-000 | |||||
Backflow device for irrigation Date: October 28, 2014Permit type: Intake | Permit status: Closed | Completion date: October 28, 2014 | Permit id: 2014-231364-000 | |||||
Connecting irrigation controller to existing electrical Date: October 28, 2014Permit type: Intake | Permit status: Closed | Completion date: October 28, 2014 | Permit id: 2014-231368-000 | |||||
Old dominion freight temporary service faxed Date: June 28, 2013Permit type: Electrical inspections | Permit status: Approved | Completion date: July 2, 2013 | Permit id: 2013-173663-000 | |||||
New shop, cross dock and site lightingfaxed Date: August 23, 2013Permit type: Intake | Permit status: Closed | Completion date: July 18, 2013 | Permit id: 2013-181825-000 | |||||
Access control system. Site:old dominion freight line. Tyco job 83-28336-1faxed Date: October 15, 2014Permit type: Electrical inspections | Permit status: Approved | Completion date: November 20, 2014 | Permit id: 2014-226173-000 | |||||