Kaiser foundation (2nd floor telephone server room) ~ add (4) new l6-30r receptacles & cicuits and (8) new l5-20r receptacles and circuits for equipment room (all circuits from existing electrical panel ups-2 spare spaces) Date: February 2, 2012 Value: $6,500Permit type: Electrical | Permit status: Finaled | Completion date: February 8, 2012 | Permit id: E12-0030 | |||||
T i kaiser permanent ~ remove & replace hvac rooftop system (bldg plbg mech ele) Date: May 20, 2010Permit type: Building | Permit status: Finaled | Completion date: July 22, 2010 | Permit id: Cb10-0383 | |||||
Kaiser permanente ~ replace (2) existing roof-mounted boiler units with (2) new roof-mounted boiler units (mech elec) Date: September 8, 2014 Value: $124,900Permit type: Building | Permit status: Issued | Permit id: Cb14-0679 | |||||
T i kaiser permanente (2nd floor) - replace existing ups (uninterruptible power system) to kva size in 2nd floor equipment room (bldg elec) Date: October 2, 2012 Value: $137,900Permit type: Building | Permit status: Finaled | Completion date: April 9, 2013 | Permit id: Cb12-0709 | |||||
T i kaiser permanente ~ 1st floor (approx. 10,5 sq ft) and accessibility upgrades at exterior parking (ada ramp) and certificate of occupancy (bldg plbg mech elec) Date: September 17, 2012 Value: $117,000Permit type: Building | Permit status: Finaled | Completion date: January 30, 2013 | Permit id: Cb12-0669 | |||||
T i kaiser permanente ~ 1st floor (interior demolition before t i - demo existing ceiling as needed to prepare for construction of partition walls; demo carpet & tile; and remove sheetrock Date: October 11, 2012 Value: $2,000Permit type: Building | Permit status: Finaled | Completion date: November 6, 2012 | Permit id: B12-0990 | |||||
T/i kaiser permanent ~ remove & replace hvac rooftop system (bldg/plbg/mech/ele) Date: May 20, 2010Permit type: Building | Permit status: Permit finaled | Completion date: July 22, 2010 | Expiration date: May 19, 2013 | Current use: Commercial | Permit id: Cb10-0383 | |||||
Kaiser permanente ~ replace (2) existing roof-mounted boiler units with (2) new roof-mounted boiler units (mech/elec) Date: October 2, 2014 Value: $124,900Permit type: Building | Permit status: Permit finaled | Completion date: January 25, 2016 | Expiration date: October 1, 2017 | Current use: Commercial | Permit id: Cb14-0679 | |||||
T/i kaiser permanente (2nd floor) - replace existing ups (uninterruptible power system) to kva size in 2nd floor equipment room (bldg/elec) Date: October 2, 2012 Value: $137,900Permit type: Building | Permit status: Permit finaled | Completion date: April 9, 2013 | Expiration date: October 2, 2015 | Current use: Commercial | Permit id: Cb12-0709 | |||||
T/i kaiser permanente ~ 1st floor (approx. 10,5 sq ft) and accessibility upgrades at exterior parking (ada ramp) and certificate of occupancy (bldg/plbg/mech/elec) Date: November 1, 2012 Value: $117,000Permit type: Building | Permit status: Permit finaled | Completion date: January 30, 2013 | Expiration date: November 1, 2015 | Current use: Commercial | Permit id: Cb12-0669 | |||||
T/i kaiser permanente ~ 1st floor (interior demolition before t/i - demo existing ceiling as needed to prepare for construction of partition walls; demo carpet & tile; and remove sheetrock Date: October 11, 2012 Value: $2,000Permit type: Building | Permit status: Permit finaled | Completion date: November 6, 2012 | Expiration date: October 11, 2015 | Current use: Commercial | Permit id: B12-0990 |