Install verizon wireless concrete equipment pad and associated stand-by generator on grade. 12 antennaswill be mounted on the proposed 74 monopole tower at rad center of 70-0 Date: July 13, 2015 Value: $80,000Permit type: Commercial building | Permit status: Finaled | Current use: Business building | Permit id: 706521 | |||||
Construct concrete pad on grade for a pre-engineered carport Date: May 23, 2014 Value: $15,000Permit type: Commercial building | Permit status: Stop work | Current use: Commercial miscellaneous struc | Permit id: 669327 | |||||
Electrical permit Date: March 12, 2008Permit status: Finaled | Current use: Business building | Permit id: 479887 | |||||
Verizon southlawn- ap #706521 monopole new site w/ canopy & generator, 2 amp meter & disconnect, feeder & 200amp panel ppi, kw 48 vdc natural gas generator Date: August 12, 2015Permit type: Electrical permit | Permit status: Finaled | Current use: Commercial miscellaneous struc | Permit id: 707078 | |||||
Directional bore under southlawn lane to place conduit for service for 14495 southlawn lane , place, splice and test aerial/buried fiber optic cable facilities in accordance with verizon plan no. 1a1a6yj. Work shall comply with montgomery county specifications for utility construction permit, the direction of the dps inspector and in accordance with the public right-of-way accessibility guidelines (prowag). A mill and overlay shall be required should the patch not meet the specifications as set forth by the current county specifications for utility construction permit and as directed by the dps row inspector. All lane closures/traffic controls shall comply with the mcdot approved traffic control plans, work zone temporary traffic control standards and directions of the dps row inspector. Must check mcdot paving project schedule and have preconstruction meeting with dps row inspector prior to beginning of construction work. Date: November 4, 2015Permit type: Public right of way | Permit status: Finaled | Current use: Public utility | Permit id: 347320 | |||||
On southlawn lane (house #14495) install service drop to 2 amp commercial service in accordance with pepco plan no. 3233208. Complete repair (restoration of right of way) shall be made of any and all damages done to the existing improvements in the public right of way caused by construction operations on this site. Pre-construction meeting requiredcontact mcdps inspector richard long at 301-370-3709 before and after installation. Date: April 3, 2008Permit type: Public right of way | Permit status: Issued | Current use: Public utility | Permit id: 257034 | |||||
Install overhead wire and associated equipment to new 200amp commercial service to cell towerin accordance with pepco plan no. 3475917. Work shall comply with montgomery county specifications for utility construction permit, the direction of the dps inspector and in accordance with the public right-of-way accessibility guidelines (prowag). A mill and overlay shall be required should the patch not meet the specifications as set forth by the current county specifications for utility construction permit and as directed by the dps row inspector. All lane closures/traffic controls shall comply with the mcdot approved traffic control plans, work zone temporary traffic control standards and directions of the dps row inspector. Must check mcdot paving project schedule and have preconstruction meeting with dps row inspector prior to beginning of construction work. Date: November 17, 2015Permit type: Public right of way | Permit status: Finaled | Current use: Public utility | Permit id: 349554 |