ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Extend circuits in rooms, total of 962 circuits Date: December 31, 2014Permit type: Intake | Permit status: Closed | Completion date: December 16, 2014 | Permit id: 2014-250045-000 | |||||
Sprinkler-relocate srpinkers to accomodate floor and ceiling changes Date: January 29, 2015Permit type: Intake | Permit status: Approved | Completion date: January 5, 2015 | Permit id: 2015-100432-000 | |||||
Demo work only, infill existing pool and spa for future guest lounge, demo all pool equipment and connections, demo existing locker rooms with restrooms, no occupancy this permits separate building permit required fortenant improvements Date: January 8, 2015Permit type: Application | Permit status: Approved | Completion date: January 8, 2015 | Permit id: 2015-102347-000 | |||||
Converting bathroom to ada. Date: January 13, 2015Permit type: Plumbing inspections | Permit status: Approved | Completion date: January 14, 2015 | Permit id: 2015-104419-000 | |||||
Interior alteration and change of occupancy from from existing a-3 pool/spa area to a-2 guest lounge, (demo work under permit 15-102347co) includes new corridor for access, expand existing exercise room, buffet area with plumbing fixtures and pantry area for use as small kitchen with plumbing fixtures, seating area, new skylight screens. Date: June 25, 2015Permit type: Application | Permit status: Approved | Completion date: January 29, 2015 | Permit id: 2015-111852-000 | |||||
2. 5t heat pump split, 12. 5t packaged heat pump (php), 2,0 cfm exhaust fan interlocked w/php, smoke detector in return, plans w/co Date: June 25, 2015Permit type: Intake | Permit status: Closed | Completion date: January 29, 2015 | Permit id: 2015-111857-000 | |||||
Addition of (4) notification devices in grand ballroom Date: February 3, 2015Permit type: Intake | Permit status: Closed | Completion date: February 3, 2015 | Permit id: 2015-114326-000 | |||||
Alarm-add four notification devices in grand ballroom Date: February 5, 2015Permit type: Intake | Permit status: Approved | Completion date: February 5, 2015 | Permit id: 2015-115523-000 | |||||
Approval of two new rooftop mechanical units and associated screen assemblies to the rooftop of the three-story pool wing of the marriot hotel in the downtown subdistrict of the central city plan district, per the approved site plans, exhibits c-1 through c-9, signed and dated april 10, 2015, subject to the following conditions:a. As part of the building permit application submittal, each of the 4 required site plans and any additional drawings must reflect the information and design approved by this land use review as indicated in exhibits c. 1-c. 9. The sheets on which this information appears must be labeled, proposal and design as approved in case file # lu 15-123242 dz. No field changes allowed. Date: April 16, 2015Permit type: Land use review | Permit status: Completed | Completion date: February 27, 2015 | Permit id: 2015-123242-000 | |||||
Relocate (3) speaker strobes due to room remodel Date: February 23, 2015Permit type: Intake | Permit status: Closed | Completion date: February 23, 2015 | Permit id: 2015-123364-000 | |||||
Alarm-relocate three for remodel on 15th floor Date: February 23, 2015Permit type: Intake | Permit status: Approved | Completion date: February 23, 2015 | Permit id: 2015-123413-000 | |||||
Remodeling for breakfast area Date: April 22, 2015Permit type: Intake | Permit status: Closed | Completion date: April 9, 2015 | Permit id: 2015-147086-000 | |||||
Install manual transfer switch for hvac pumps Date: May 18, 2015Permit type: Electrical inspections | Permit status: Approved | Completion date: June 26, 2015 | Permit id: 2015-172014-000 | |||||
Add lighting and plug circuits for new meeting room areafaxed Date: February 24, 2012Permit type: Intake | Permit status: Closed | Completion date: February 24, 2012 | Permit id: 2012-115771-000 | |||||
Reroof; remove and replace roof Date: September 26, 2014Permit type: Application | Permit status: Approved | Completion date: September 23, 2014 | Permit id: 2014-216570-000 | |||||
Interior renovation of 503 guestrooms with 1 guestrooms receiving a tub-to-shower conversion; one standard guestroom (1641) will be converted to a fully accessible guestroom; guest lounge on the 15th floor will be converted to three standard guestrooms Date: December 15, 2014Permit type: Application | Permit status: Approved | Completion date: September 29, 2014 | Permit id: 2014-218814-000 | |||||
Add new 14 walls and doorway for new parking attendants office Permit type: Application | Permit status: Approved | Completion date: January 12, 2004 | Permit id: 2004-000750-000 | |||||
Add new 14 walls and doorway for new parking attendants office Permit type: Life safety | Permit status: Approved | Completion date: January 12, 2004 | Permit id: 2004-000750-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Intake | Permit status: Closed | Completion date: July 28, 2015 | Permit id: 2015-208234-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Planning and zoning | Permit status: Approved | Completion date: July 28, 2015 | Permit id: 2015-208234-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Life safety | Permit status: Not reqd | Completion date: July 28, 2015 | Permit id: 2015-208234-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Mechanical review | Permit status: Approved | Completion date: August 25, 2015 | Permit id: 2015-208234-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Fire bureau | Permit status: Approved | Completion date: November 16, 2015 | Permit id: 2015-208234-000 | |||||
Adding distributed audio to m-club 3rd floor Date: August 7, 2015Permit type: Intake | Permit status: Closed | Completion date: August 7, 2015 | Permit id: 2015-214376-000 | |||||
Install (1) new non-illuminated wall sign, 13. 12 sq ft, sign awest elevation Date: September 25, 2015Permit type: Intake | Permit status: Closed | Completion date: August 27, 2015 | Permit id: 2015-218877-000 | |||||
Install (1) illuminated projecting wall sign, 18. 29 sq ft, sign bsouth elevation Date: September 25, 2015Permit type: Intake | Permit status: Closed | Completion date: August 27, 2015 | Permit id: 2015-218907-000 | |||||
Install (1) non-illuminated wall sign, 3. 88 sq ft sign c northwest elevation Date: September 25, 2015Permit type: Intake | Permit status: Approved | Completion date: September 4, 2015 | Permit id: 2015-218911-000 | |||||
Install (1) non-illuminated wall sign, 9. 6 sq ft sign deast elevation Date: September 25, 2015Permit type: Intake | Permit status: Approved | Completion date: September 4, 2015 | Permit id: 2015-218917-000 | |||||
Install (1) non-illuminated wall sign, 15. 6 sq ft sign h Date: September 25, 2015Permit type: Intake | Permit status: Approved | Completion date: September 4, 2015 | Permit id: 2015-218918-000 | |||||
Install (1) sign circuit Date: September 25, 2015Permit type: Intake | Permit status: Closed | Completion date: September 4, 2015 | Permit id: 2015-218919-000 | |||||
Alarm-converting the pool/spa area into a lounge area and remodleing the exercise room. Date: September 10, 2015Permit type: Intake | Permit status: Approved | Completion date: September 2, 2015 | Permit id: 2015-230473-000 | |||||
Demo locker rooms, convert pool area into server station/food prep Date: September 10, 2015Permit type: Environmental services | Permit status: Approved | Completion date: September 15, 2015 | Permit id: 2015-234506-000 | |||||
Sprinkler - add/relocate sprinklers per nfpa 13 to accommodate ti changes Date: October 14, 2015Permit type: Intake | Permit status: Approved | Completion date: September 21, 2015 | Permit id: 2015-239600-000 | |||||
Install electrical for 2. 5t heat pump split, 12. 5t packaged heat pump (php), 2,0 cfm exhaust fan interlocked w/php, smoke detector in return Date: October 5, 2015Permit type: Intake | Permit status: Closed | Completion date: October 5, 2015 | Permit id: 2015-246246-000 | |||||
Cat6 cabling down hallways into guest roomsfaxed Date: November 20, 2014Permit type: Electrical inspections | Permit status: Approved | Completion date: November 3, 2015 | Permit id: 2014-238738-000 | |||||
Replace shower valves and drains Date: December 15, 2014Permit type: Plumbing inspections | Permit status: Approved | Completion date: December 11, 2015 | Permit id: 2014-249397-000 | |||||
Add new 14 walls and doorway for new parking attendants office Permit type: Application | Permit status: Approved | Completion date: January 12, 2004 | Permit id: 2004-000750-000 | |||||
Add new 14 walls and doorway for new parking attendants office Permit type: Life safety | Permit status: Approved | Completion date: January 12, 2004 | Permit id: 2004-000750-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Intake | Permit status: Closed | Completion date: July 28, 2015 | Permit id: 2015-208234-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Planning and zoning | Permit status: Approved | Completion date: July 28, 2015 | Permit id: 2015-208234-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Life safety | Permit status: Not reqd | Completion date: July 28, 2015 | Permit id: 2015-208234-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Mechanical review | Permit status: Approved | Completion date: August 25, 2015 | Permit id: 2015-208234-000 | |||||
2. 5 ton split on 3rd floor and 12. 5 ton roof top packaged heat pump, duct work and grilles, structural details attached Permit type: Fire bureau | Permit status: Approved | Completion date: November 16, 2015 | Permit id: 2015-208234-000 | |||||
Alarm-converting the pool spa area into a lounge area and remodleing the exercise room. Date: September 10, 2015Permit type: Intake | Permit status: Approved | Completion date: September 2, 2015 | Permit id: 2015-230473-000 | |||||
Demo locker rooms, convert pool area into server station food prep Date: September 10, 2015Permit type: Environmental services | Permit status: Approved | Completion date: September 15, 2015 | Permit id: 2015-234506-000 | |||||
Sprinkler - add relocate sprinklers per nfpa 13 to accommodate ti changes Date: October 14, 2015Permit type: Intake | Permit status: Approved | Completion date: September 21, 2015 | Permit id: 2015-239600-000 | |||||
Install electrical for 2. 5t heat pump split, 12. 5t packaged heat pump (php), 2,0 cfm exhaust fan interlocked w php, smoke detector in return Date: October 5, 2015Permit type: Intake | Permit status: Closed | Completion date: October 5, 2015 | Permit id: 2015-246246-000 | |||||
Interior alteration and change of occupancy from from existing a-3 pool spa area to a-2 guest lounge, (demo work under permit 15-102347co) includes new corridor for access, expand existing exercise room, buffet area with plumbing fixtures and pantry area for use as small kitchen with plumbing fixtures, seating area, new skylight screens. Date: June 25, 2015Permit type: Application | Permit status: Approved | Completion date: January 29, 2015 | Permit id: 2015-111852-000 | |||||
2. 5t heat pump split, 12. 5t packaged heat pump (php), 2,0 cfm exhaust fan interlocked w php, smoke detector in return, plans w co Date: June 25, 2015Permit type: Intake | Permit status: Closed | Completion date: January 29, 2015 | Permit id: 2015-111857-000 | |||||
Change walls to relocate restrooms, excerise near swimming pool area. Date: April 5, 2005Client: Neighbors West Northwest | Permit type: Alteration | Permit status: Final | Completion date: January 12, 2006 | Current use: Business | Permit id: 2005-113393-000 | |||||
Remove one toilet in mens restroom to create ada stall and add one at lounge to womens Date: April 17, 2006Client: Neighbors West Northwest | Permit type: Alteration | Permit status: Final | Completion date: April 4, 2007 | Current use: Hotel/motel | Permit id: 2006-123170-000 | |||||
Interior renovation of accessible guestrooms. Date: November 14, 2006Client: Neighbors West Northwest | Permit type: Alteration | Permit status: Final | Completion date: April 4, 2007 | Current use: Hotel/motel | Permit id: 2006-160383-000 | |||||
Complete renovation of the ballroom lower level 1, meeting rooms on public level, bathrooms on third and lower level 1 Date: May 1, 2007Client: Neighbors West Northwest | Permit type: Alteration | Permit status: Under inspection | Current use: Assembly | Permit id: 2007-105819-000 | |||||
Renovate existing bar and restaurant; renovate lobby; reconstruct exterior ramp; re-route exhaust hood at omelette station Date: November 1, 2011Client: Neighbors West Northwest | Permit type: Alteration | Permit status: Final | Completion date: June 11, 2012 | Current use: Hotel/motel | Permit id: 2011-166180-000 | |||||
Change occupancy of existing restaurant (a2) to conference rooms (a3), adding 39 total occupants; expand and reconfigure existing restrooms adding 2 wcs, 2 lavs @women, adding 2 lavs @men. Date: November 22, 2011Client: Neighbors West Northwest | Permit type: Alteration | Permit status: Final | Completion date: June 11, 2012 | Current use: Assembly | Permit id: 2011-184424-000 | |||||
Convert existing space to gift shop Date: February 2, 2012Client: Neighbors West Northwest | Permit type: Alteration | Permit status: Final | Completion date: February 29, 2012 | Current use: Mercantile | Permit id: 2012-103410-000 |