ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Rough-in and install (2) ada toilets, (2) ada lavatories for new restrooms. Install (1) new sink & icemaker in break room. Date: November 4, 2015Permit type: Plumbing inspections | Permit status: Approved | Completion date: December 1, 2015 | Permit id: 2015-260727-000 | |||||
Voice data Date: November 23, 2015Permit type: Intake | Permit status: Closed | Completion date: November 23, 2015 | Permit id: 2015-268671-000 | |||||
Add two 3t gas packs to serve new office area, gas piping duct work and grilles. Add two exhaust fans. Relocate radiant heater. Structural details attached Date: December 8, 2015Permit type: Intake | Permit status: Closed | Completion date: December 8, 2015 | Permit id: 2015-272588-000 | |||||
Low volt wiring and t-stats Date: December 8, 2015Permit type: Intake | Permit status: Closed | Completion date: December 8, 2015 | Permit id: 2015-274313-000 | |||||
Add roof curb for gravity vent intake for future paint booth (total height = 21) Date: December 22, 2015Permit type: Intake | Permit status: Closed | Completion date: December 22, 2015 | Permit id: 2015-280523-000 | |||||
Fixed system - installation of a pyro chem vehicle paint spray booth fire suppression system Date: December 30, 2015Permit type: Intake | Permit status: Approved | Completion date: December 28, 2015 | Permit id: 2015-281906-000 | |||||
Paint booth - move in existing paint booth from 10 se 11th Date: January 27, 2016Permit type: Intake | Permit status: Approved | Completion date: January 22, 2016 | Permit id: 2016-109127-000 | |||||
Partial change of occupancy for main floor office/storage/warehouse tenant and second floor office tenant. 1st floor: new stair; main floor - light demo (including unpermitted stair); reconfigure existing area separation wall; new kitchen, offices, new restroom, lobby and new storefront/entry, new 3 hr opening between fire areas. 2nd floor - demo and reconfigure space to include large conference room, office, library/work area, kitchenette and restroom. Date: November 4, 2015Permit type: Application | Permit status: Approved | Completion date: July 16, 2015 | Permit id: 2015-202257-000 | |||||
Added value revision to revise entry layout; egress lighting clarifications; add structural beam at lobby area see reference revision 3 on plans Date: November 16, 2015Permit type: Application | Permit status: Approved | Completion date: November 13, 2015 | Permit id: 2015-202257-Rev | |||||
Partial change of occupancy for main floor office storage warehouse tenant and second floor office tenant. 1st floor: new stair; main floor - light demo (including unpermitted stair); reconfigure existing area separation wall; new kitchen, offices, new restroom, lobby and new storefront entry, new 3 hr opening between fire areas. 2nd floor - demo and reconfigure space to include large conference room, office, library work area, kitchenette and restroom. Date: November 4, 2015Permit type: Application | Permit status: Approved | Completion date: July 16, 2015 | Permit id: 2015-202257-000 |