Installation of wine grape extraction unit, heat exchanger, boiler, pumps, (3) tanks, and piping equipment anchoring and electrical wring conduct and panel. Date: June 20, 2016Client: Panziera Ranch Llc | Permit type: Combination | Permit status: Open | Permit id: 16cp01742 | |||||
Installation of (1) amp 480v panel with (1) 3kva transformer for 120/2 v power to new water system. Date: September 30, 2015Client: Panziera Ranch Llc | Permit type: Electrical | Permit status: Applied | Permit id: 15cp02466 | |||||
Residential roof-mounted photovoltaic system. 7. 28 kw 28 panels. Existing electrical panel will be used. 1 amps Date: August 4, 2016Permit type: Solar | Permit status: Applied | Permit id: 16cp02239 | |||||
Removal of existing poly water storage tank and slab, replace with new slab, water treatment equipment and 258 sq ft mechanical cover. Construction of new allan block retaining walls ranging from 28"-510", 72 liner feet. Date: June 9, 2015Client: Panziera Ranch Llc | Permit type: Combination | Permit status: Applied | Permit id: 15cp01463 | |||||
Add new metal panels to an existing metal framed shed to protect existing equipment. Date: October 5, 2016Client: Panziera Conundrum Winery | Permit type: Building | Permit status: Issued | Permit id: 16cp02863 | |||||
Installation of (1) amp 480v panel with (1) 3kva transformer for 120 2 v power to new water system. Date: September 30, 2015Client: Panziera Ranch Llc | Permit type: Electrical | Permit status: Applied | Permit id: 15cp02466 | |||||
Addition of a new wine juice press equipment for an existing winery. Date: March 30, 2017Client: Panziera Ranch Llc | Permit status: Open | Permit id: 17cp00823 | |||||
Construction permit to allow the installation of three water tanks, 2,500, 6,0 and 10,5 gallons for reverse osmosis and nanofiltration water system for an existing winery. Including, foundation, piping electrical and installation of filtration equipment. Date: April 3, 2017Client: Panziera Ranch | Permit status: Open | Permit id: 17cp00860 | |||||
Installation of a x1 temporary tent structures for wine gala event at mer soleil winery installation will begin 05 17 2017, event date 05 17 2017 , and to be removed by 05 22 2017 tent engineering approved under master plan 17mp00004 Date: April 19, 2017Client: Mission Ranch | Permit status: Open | Permit id: 17cp01027 | |||||
Installation of a new 6 amps main service panel to serve the crush equipment for an existing winery. Date: May 8, 2017Client: Panziera Ranch Llc | Permit status: Issued | Permit id: 17cp01213 |