Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 96 Phase 1 - replace 22 of primary wire along rhode island ave ne various locations (large feeder reliability project) as indicated on attached prints. Wr# 3524228 (ltadmasu@pepco. Com) admasu/mason Date: October 19, 2016 Contractor: Potomac Electric Power Company Permit type: Over head work; string electrical wire | Permit status: Assigned | Expiration date: May 19, 2017 | |||||
SCORE 96 Phase 1 - replace 2200' of primary wire along rhode island ave ne various locations (large feeder reliability project) as indicated on attached prints. Wr# 3524228 (ltadmasu@pepco. Com) admasu mason Date: October 19, 2016 Contractor: Potomac Electric Power Company Permit type: Over head work; string electrical wire | Permit status: Resubmitted | Expiration date: May 19, 2017 | |||||
SCORE 89 Construction staging area Date: July 9, 2014 Permit status: Expired | Expiration date: August 14, 2014 | Permit id: Pa10139363-R2 | |||||
SCORE 89 Construction staging area Date: June 13, 2014 Permit status: Expired | Expiration date: July 14, 2014 | Permit id: Pa10139363-R1 | |||||
SCORE 89 Construction staging area Date: May 14, 2014 Permit status: Permit expired | Expiration date: June 15, 2014 | Permit id: Pa10139363 | |||||
SCORE 96 Phase 1 - replace 2200' of primary wire along rhode island ave ne various locations (large feeder reliability project) as indicated on attached prints. Wr# 3524228 (ltadmasu@pepco. Com) admasu mason Date: February 1, 2017 Contractor: Potomac Electric Power Company Permit status: Issued | Expiration date: July 28, 2017 | Permit id: Pa185375 | |||||
SCORE 95 Per emergency permit e78963, excavate to replace frame and cover for mh #798 in the roadway of rhode island avenue ne and 17th street ne as shown on job 1a2hr7c. Date: August 28, 2017 Contractor: Verizon Permit type: Excavation; manhole frame and cover (adjust) | Permit status: Issued | Expiration date: October 26, 2017 | Permit id: Pa221054 |