SCORE 100 Demo existing bathroom, add new plaster, electrical, plumbing, tub, sink, toilet, fan/vent exhausted to exterior, tile and paint Permit type: Addition/alteration | Completion date: December 5, 2014 | Current use: One-family | Parcel: 233192 | |||||
SCORE 93 Relocate existing kitchen: demo existing kitchen and current laundry room. Frame new entrance to master bedroom. Cap existing plumbing and rough in new plumbing in new location. Install new amp circuit per ma code. Install new lighting per electrical plan. Insulate and and board new walls and install blocking for cabinets. Plaster paint, finish work upon completion. Install new bath & laundry room in place of old kitchen. Frame in new walls per design plans. Rough in new plumbing for new bath including custom shower unit. Install new outlets and wiring to code and new vent/light ceiling unit. Insulate, board and plaster new walls. Paint and finish work upon completion. Permit type: Addition/alteration | Completion date: January 22, 2016 | Current use: Two-family | Parcel: 2332021 | |||||
SCORE 86 Excavation Date: March 20, 2014 Contractor: Barletta Heavy Division Permit id: Exc19027 | |||||
SCORE 100 Excavation Date: June 4, 2014 Contractor: Nstar Gas Permit id: Exc19272 | |||||
SCORE 100 Excavation Date: July 24, 2009 Contractor: Nstar Gas Permit id: Exc13470 | |||||
SCORE 100 Excavation Date: July 18, 2013 Contractor: Cambridge Water Department Permit id: Exc18333 | |||||
SCORE 100 Excavation Date: April 21, 2009 Contractor: Newport Construction Permit id: Exc13174 | |||||
SCORE 100 Excavation Date: March 29, 2012 Contractor: Nstar Gas Permit id: Exc16776 | |||||
SCORE 100 Excavation Date: February 27, 2015 Contractor: Nstar Gas Permit id: Exc20023 | |||||
SCORE 100 Excavation Date: November 18, 2014 Contractor: K.B. Aruda Construction Inc Permit id: Exc19833 | |||||
SCORE 100 Demo existing bathroom, add new plaster, electrical, plumbing, tub, sink, toilet, fan vent exhausted to exterior, tile and paint Permit type: Addition/alteration | Completion date: December 5, 2014 | Current use: One-family | Permit id: 0 | Parcel: 233192 | |||||
SCORE 93 Relocate existing kitchen: demo existing kitchen and current laundry room. Frame new entrance to master bedroom. Cap existing plumbing and rough in new plumbing in new location. Install new amp circuit per ma code. Install new lighting per electrical plan. Insulate and and board new walls and install blocking for cabinets. Plaster paint, finish work upon completion. Install new bath & laundry room in place of old kitchen. Frame in new walls per design plans. Rough in new plumbing for new bath including custom shower unit. Install new outlets and wiring to code and new vent light ceiling unit. Insulate, board and plaster new walls. Paint and finish work upon completion. Permit type: Addition/alteration | Completion date: January 22, 2016 | Current use: Two-family | Permit id: 0 | Parcel: 2332021 | |||||
SCORE 100 Install solar electric panels on roof of existing home, to be interconnected with the homes electrical system. 14 panels @ 3. 64kw Permit type: Addition/alteration | Completion date: November 28, 2016 | Current use: One-family | Permit id: 0 | Parcel: 233192 | |||||
SCORE 56 Remove all portions of existing roof of entire house. Repair any rotten roof boards. Install 8" aluminum drip edge to all edges. Install ice and water shield for the first 6 of roof in all valleys, around all chimneys and roof protrusions. Install gaf shinglemate to remaining portions of roof. Install gaf architectural shingles to entire roof area. Remove all debris. Permit type: Roof | Completion date: August 21, 2017 | Permit id: 0 | Parcel: 263120 |