Mechanical permit Date: January 11, 2011 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 320174 | |||||
Electrical permit Date: November 10, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 310970 | |||||
Suppression permit Date: November 4, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 308988 | |||||
Plumbing permit Date: September 30, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 303854 | |||||
Zoning/use permit Date: April 30, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 269349 | |||||
New construction permit Date: July 23, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 283531 | |||||
Mechanical permit Date: January 11, 2011 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 320174 | |||||
Suppression permit Date: November 4, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 308988 | |||||
New construction permit Date: July 23, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 283531 | |||||
Zoning use permit Date: April 30, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 269349 | |||||
Plumbing permit Date: September 30, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 303854 | |||||
Electrical permit Date: November 10, 2010 Client: Vahedi Golnaz Faryabi Robert | Permit status: Completed | Permit id: 310970 | |||||
SCORE 100 Comfortmaker warm air 120,0 btu 90% with related duct work. Date: January 11, 2011 Contractor: Rosenberg Neil Client: Ahedi Golnaz Faryabi Robert | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 2, 2011 | Permit id: 320174 | |||||
SCORE 89 25 duplex receptacles, 15 single pole switches, lighting fixtures, 2 amp service, 6 smoke detectors, all as per 2008 nec (south dist) Date: November 10, 2010 Contractor: Tartaglio And Son Elec Cont Client: Ahedi Golnaz Faryabi Robert | Permit type: Electrical permit | Permit status: Completed | Completion date: October 3, 2011 | Permit id: 310970 | |||||
SCORE 96 Install (1) wet fire suppression sprinkler system for new sfd per hyd. Cals & plan. Date: November 4, 2010 Contractor: S S Sprinkler Company Inc Client: Ahedi Golnaz Faryabi Robert | Permit type: Suppression permit | Permit status: Completed | Completion date: September 2, 2011 | Permit id: 308988 | |||||
SCORE 100 Install stack and waste line for 1 kitchen sink, 4 lav sink,3 water closets,2bath tubs 1 stand pipe 1 shower Date: September 30, 2010 Contractor: Norman Cole Sr, Client: Ahedi Golnaz Faryabi Robert | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 2, 2011 | Permit id: 303854 | |||||
SCORE 100 Instll new complete 3 4" k copper water service, install new curb trap and main house drain into building Date: August 10, 2010 Contractor: Mark Hughes Client: Ahedi Golnaz Faryabi Robert | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 295552 | |||||
New construction of a new 3 story sfd. Date: July 23, 2010 Client: Ahedi Golnaz Faryabi Robert | Permit type: New construction permit | Permit status: Completed | Completion date: August 24, 2011 | Permit id: 283531 |