SCORE 91 Abandon(e) 1000gal septic tank and install new microseptec es-6 system per approved plan only. Date: August 7, 2012 Contractor: Ely Jrs Pumping And Septic System Applicant: Ely Jrs Plumbing | Permit status: Finaled | Completion date: September 13, 2012 | Expiration date: August 7, 2013 | Permit id: 1208070001 | |||||
Detached deck 327 sq ft Date: April 24, 2000 Value: $28,000 Engineer: Laima Reeder | Applicant: Same As Owner | Permit status: Finaled | Completion date: September 1, 2000 | Expiration date: October 21, 2000 | Permit id: 2280027 | |||||
SCORE 100 Geo review for existing septic tank replacement Date: March 19, 2012 Contractor: Tbd Engineer: Mountain Geology | Applicant: Coulson Shelley | Permit status: Permisud | Expiration date: September 15, 2012 | Permit id: 1203190001 | |||||
Adding (n) future seepage pit only Date: September 10, 2012 Applicant: Same As Owner | Permit status: Finaled | Completion date: September 13, 2012 | Expiration date: September 10, 2013 | Permit id: 1209100004 | |||||
SCORE 99 Replace furnace & a/c, (7) ducts, add (2) new heat pumps w/ electrical hook up and (2) air handlers Date: January 6, 2011 Contractor: J W Heating And Air Inc Applicant: Ian Jacoby | Permit status: Finaled | Completion date: January 24, 2011 | Expiration date: January 6, 2012 | Permit id: 1101060023 | |||||
SCORE 99 (2) 220v circuits for heat pumps Date: January 6, 2011 Contractor: J W Heating And Air Inc Applicant: Ian Jacoby | Permit status: Finaled | Completion date: January 24, 2011 | Expiration date: January 6, 2012 | Permit id: 1101060031 | |||||
SCORE 100 Upgrade panel to 2 amp. Date: March 7, 2012 Contractor: G B C Electrical Services Applicant: Gary Carter | Permit status: Finaled | Completion date: March 13, 2012 | Expiration date: March 7, 2013 | Permit id: 1203070002 | |||||
34x4 ret wall with 4 piles (master permit for 620&6 taba rd) Date: April 3, 2008 Value: $22,180 Engineer: Leonard Liston | Applicant: Same As Owner | Permit status: Finaled | Completion date: November 4, 2008 | Expiration date: September 30, 2008 | Permit id: 804030089 | |||||
SCORE 99 Replace furnace & a/c, (7) ducts, add (2) new heat pumps w/ electrical hook up and (2) air handlers Date: January 6, 2011 Contractor: J W Heating And Air Inc Applicant: Ian Jacoby | Permit status: Finaled | Completion date: January 24, 2011 | Expiration date: January 6, 2012 | Permit id: 1101060023 | |||||
SCORE 99 (2) 220v circuits for heat pumps Date: January 6, 2011 Contractor: J W Heating And Air Inc Applicant: Ian Jacoby | Permit status: Finaled | Completion date: January 24, 2011 | Expiration date: January 6, 2012 | Permit id: 1101060031 | |||||
SCORE 99 (2) 220v circuits for heat pumps Date: January 6, 2011 Contractor: J W Heating And Air, Inc Applicant: Ian Jacoby | Permit status: Finaled | Completion date: January 24, 2011 | Expiration date: January 6, 2012 | Permit id: 1101060031 | |||||
SCORE 99 Replace furnace & a c, (7) ducts, add (2) new heat pumps w electrical hook up and (2) air handlers Date: January 6, 2011 Contractor: J W Heating And Air, Inc Applicant: Ian Jacoby | Permit status: Finaled | Completion date: January 24, 2011 | Expiration date: January 6, 2012 | Permit id: 1101060023 | |||||
SCORE 100 New 7. 9 kw roof pv solar system - panels Engineer: James Adams | Applicant: Torres Andres | Permit status: Permisud | Completion date: October 13, 2016 | Expiration date: October 13, 2017 | Permit id: 1608150027 |