ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Alteration permit Date: October 14, 2014Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 566255 | |||||
Demolition permit Date: December 2, 2015Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 655448 | |||||
Alteration permit Date: April 20, 2016Client: Exelon Generation Co Llc Richmond Station | Permit status: Active | Permit id: 672915 | |||||
Operations permit Date: May 12, 2016Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 24214 | |||||
Plumbing permit Date: September 24, 2010Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 302974 | |||||
Administrative permit Date: September 13, 2016Client: Exelon Generation Co Llc Richmond Station | Permit status: Active | Permit id: 715748 | |||||
Alteration permit Date: March 1, 2012Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 374005 | |||||
Plumbing permit Date: June 3, 2016Client: Exelon Generation Co Llc Richmond Station | Permit status: Active | Permit id: 686461 | |||||
Operations permit Date: June 13, 2008Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 8771 | |||||
Paragraphs 3. B. And 4. A. Of the approval contain requirements regarding the sulfur content of fuel burned at the facility that are unsupported by law and unrelated to the regulation of nox emissions from the facility that is the purpose of the approval. Date: February 19, 2015Client: Exelon Generation Co Llc Richmond Station | Applicant: Brendan Collins | Permit type: Appeal | Permit status: Withdrawn | Permit id: 24657 | |||||
Operations permit Date: May 12, 2016Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 24214 | |||||
Alteration permit Date: April 15, 2014Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 518674 | |||||
Alteration permit Date: April 20, 2016Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 672915 | |||||
Alteration permit Date: March 1, 2012Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 374005 | |||||
Operations permit Date: June 13, 2008Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 8771 | |||||
Demolition permit Date: December 2, 2015Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 655448 | |||||
Administrative permit Date: August 16, 2016Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 712244 | |||||
Plumbing permit Date: November 10, 2016Client: Exelon Generation Co Llc Richmond Station | Permit status: Active | Permit id: 717348 | |||||
Plumbing permit Date: September 24, 2010Client: Exelon Generation Co Llc Richmond Station | Permit status: Completed | Permit id: 302974 | |||||
Paragraphs 3. B. And 4. A. Of the approval contain requirements regarding the sulfur content of fuel burned at the facility that are unsupported by law and unrelated to the regulation of nox emissions from the facility that is the purpose of the approval. Date: February 19, 2015Client: Exelon Generation Co Llc Richmond Station | Applicant: Brendan Collins | Permit type: Appeal | Permit status: Withdrawn | Permit id: 24657 | |||||
SCORE 95 For alterations to install new elevator shaft to include elevator machine room, proposed fire-rated assemblies, and opening protectives. Separate permits required from pa dept of labor & industry for elevator installation. Separate permits required prior to occupancy. Separate permits required for electrical, mechanical, plumbing, and fire suppression system installations. Asbestos abatement to be completed prior to commencement of work. Date: October 16, 2017 Contractor: Milestone ConstructionClient: Exelon Generation Co Llc Richmond Station | Permit type: Alteration permit | Permit status: Active | Completion date: October 16, 2017 | Permit id: 784238 | |||||
SCORE 95 Amend permit number 672915 for revised civil and structural plans for relocation of sanitary line and removal of styrofoam with concrete slab and addition of structural steel as per approved plans. Date: August 16, 2016 Contractor: Milestone ConstructionClient: Exelon Generation Co Llc Richmond Station | Permit type: Administrative permit | Permit status: Completed | Completion date: October 18, 2016 | Permit id: 712244 | |||||
SCORE 95 Site work to include drilling of well boring holes and installation of geothermal field with supply return piping, accessory mechanical, grouting, for testing and sampling of geothermal properties of site and future conditioning heating of structure(additional permits required for interior mechanical installations and occupancy). Limited civil site work, fencing, paving, back filling at completion of installation. Additional permits req: plumbing. Pwd connections, sewers, utilities work not part of this permit. Date: October 14, 2014 Contractor: Milestone ConstructionClient: Exelon Generation Co Llc Richmond Station | Permit type: Alteration permit | Permit status: Completed | Completion date: August 15, 2015 | Permit id: 566255 | |||||
SCORE 62 Selective demolition and construction placement of concrete topping, structural steel fabrication and erection, steel joists, steel decking, steel stairways, and other improvements and incidental work. Date: April 15, 2014 Contractor: Thomas P Carney IncClient: Exelon Generation Co Llc Richmond Station | Permit type: Alteration permit | Permit status: Completed | Completion date: January 14, 2017 | Permit id: 518674 | |||||
SCORE 100 Alteration: interior plumbing for a 1st floor office space.(commercial). This building is unoccupied. The installation will comply with the philadelphia plumbing code, 2004. Separate permits are required for the 2nd, 3rd and 4th floors; plumbing sitework; 8" sanitary lateral and 4" domestic water distribution service. Date: June 3, 2016 Contractor: Dolan Mechanical IncClient: Exelon Generation Co Llc Richmond Station | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 25, 2017 | Permit id: 686461 | |||||
SCORE 95 Level ii interior alterations (no occupancy at this time) for reconditioning of the 1st floor area to include site work (water and sanitary and storm sewer), concrete, framing, masonry, misc steel, drywall and insulation as per approved plans. No occupancy of building at this time, separate permits required for use registration and fit-out prior to occupancy of building separate permits required for any mep or fire suppression work at this time Date: April 20, 2016 Contractor: Milestone ConstructionClient: Exelon Generation Co Llc Richmond Station | Permit type: Alteration permit | Permit status: Completed | Completion date: February 10, 2017 | Permit id: 672915 | |||||
SCORE 65 Ust removals. 1 1,5 gallon motor oil. 1-6 gallon transmission oil, 1-1,5 gallon hydraulic oil Date: December 2, 2015 Contractor: Rj Walsh AssociatesClient: Exelon Generation Co Llc Richmond Station | Permit type: Demolition permit | Permit status: Completed | Completion date: July 5, 2016 | Permit id: 655448 | |||||
SCORE 100 Alterations:interior plumbing; rough-in domestic piping only; rehab reconditioning of existing vacant incinerator building. Stubbing up to 34 fixtures and adding a 119 gallon water heater-the installation will comply with the philadephia plubming code 2004 Date: November 1, 2017 Contractor: Dolan Mechanical IncClient: Exelon Generation Co Llc Richmond Station | Permit type: Plumbing permit | Permit status: Active | Completion date: November 1, 2017 | Permit id: 816509 | |||||
SCORE 100 Alterations:interior plumbing; rough-in sanitary piping only; rehab reconditioning of existing vacant incinerator building - the installation will comply with the philadephia plubming code 2004 Date: November 10, 2016 Contractor: Dolan Mechanical IncClient: Exelon Generation Co Llc Richmond Station | Permit type: Plumbing permit | Permit status: Active | Completion date: June 27, 2017 | Permit id: 717348 | |||||
SCORE 100 5 20 16 erect assembly tent 30x60, 20x40 Date: May 12, 2016 Contractor: Anthony Rental And Sales IncClient: Exelon Generation Co Llc Richmond Station | Permit type: Operations permit | Permit status: Completed | Permit id: 24214 | |||||
SCORE 100 Repair 15"private water main Date: September 24, 2010 Contractor: Fluidics IncClient: Exelon Generation Co Llc Richmond Station | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 30, 2010 | Permit id: 302974 | |||||
SCORE 95 Phased rehab reconditioning of existing vacant incinerator building: no occupancy. Exterior alteration for weatherization sealing and protection of structure for future proposed occupancy, remove and replace roof and parapet with reuse of existing materials and installation of new roof membrane, structural rehab reconditioning, new windows and doors. Partial interior alterations, demo, clean up, make safe. Prior asbestos removal phase per designer. Future permits required : zoning use, fit out certificate of occupancy, electrical, plumbing,hvac, sprinklers. Date: March 1, 2012 Contractor: Milestone ConstructionClient: Exelon Generation Co Llc Richmond Station | Permit type: Alteration permit | Permit status: Completed | Completion date: April 12, 2013 | Permit id: 374005 | |||||
SCORE 95 Amend permit #672915 to include additional metal wall framing (no insulation, gwb or interior doors) throughout the building as per approved plans. Separate permits required for c. O. Prior to occupancy Date: March 17, 2017 Contractor: Milestone ConstructionClient: Exelon Generation Co Llc Richmond Station | Permit type: Administrative permit | Permit status: Active | Completion date: June 9, 2017 | Permit id: 763292 | |||||
SCORE 95 Amend permit number 672915 to include wall rough in and wall changes, changes to the layout of the bathrooms, wall types, and the door schedule as per approved plans. Date: September 13, 2016 Contractor: Milestone ConstructionClient: Exelon Generation Co Llc Richmond Station | Permit type: Administrative permit | Permit status: Completed | Completion date: January 25, 2017 | Permit id: 715748 |