Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical permit Date: December 4, 2015 Client: Cathedral Property Holdin | Permit status: Expired | Permit id: 652760 | |||||
Zoning/use permit Date: November 30, 2015 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 648144 | |||||
Sign permit Date: November 30, 2015 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 654903 | |||||
New construction permit Date: September 17, 2013 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 489737 | |||||
Mechanical permit Date: January 23, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 511512 | |||||
Electrical permit Date: December 4, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 565755 | |||||
Use permit Date: September 13, 2012 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 420498 | |||||
Plumbing permit Date: October 28, 2015 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 647885 | |||||
Alteration permit Date: September 17, 2013 Client: Cathedral Property Holdin | Permit status: Expired | Permit id: 493366 | |||||
Suppression permit Date: December 1, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 553556 | |||||
Plumbing permit Date: January 17, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 508684 | |||||
Alteration permit Date: September 22, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 556989 | |||||
Electrical permit Date: December 13, 2013 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 511182 | |||||
Zoning/use permit Date: May 3, 2013 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 426355 | |||||
Administrative permit Date: June 25, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 528107 | |||||
Alteration permit Date: October 20, 2015 Client: Cathedral Property Holdin | Permit status: Expired | Permit id: 637860 | |||||
Suppression permit Date: November 9, 2015 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 650943 | |||||
Permit for the one(1) story addition of an existing elevator penthouse roof from 278 to 284 high , for the reduction of dwelling units from two hundred eighty three (283) to a new total of two hundred seventy six ( 276) dwelling units on 3rd thru 25th floors ( increasing the total sq ft of the building but reducing the total countable gfa from 257, 760sf to 248, 055 sf) , increase in retail spaces on 1st floor thru 2nd floor ( from 3,1 sf to 6,264 sf), the creation of electrical mezzanine ( gsf 1,4 sf) on first floor level, for the amenity services including with personal services (fitness center, yoga room, clubroom with kitchen, offices all accessory to the dwellings) ( not as defined as in 14-603(13) at 2nd floor ( 8,329 sf), for the reduction of off-street parking spaces and one(1) h/c space from 48 spaces including 4 h/c spaces to 42 spaces including 3 h/c space and for the creation of bicycle storage spaces for 67 bicycles below grade ( from 9,4 sf to 8,664 sf) ( bicycle parking Date: July 3, 2013 Client: Cathedral Property Holdin | Applicant: Neil Sklaroff, Esquire | Permit type: Appeal | Permit status: Granted/prov | Completion date: August 13, 2013 | Permit id: 20829 | |||||
On 8/20/13, the department of licenses and inspections issued a notice of refusal for application #483854. Date: August 21, 2013 Client: Cathedral Property Holdin | Applicant: Robert Graves, Aia | Permit type: Appeal | Permit status: Approved | Completion date: July 3, 2014 | Permit id: 21131 | |||||
Electrical permit Date: February 7, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 514980 | |||||
New construction permit Date: November 1, 2013 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 501269 | |||||
Zoning use permit Date: August 5, 2013 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 478226 | |||||
Electrical permit Date: December 4, 2015 Client: Cathedral Property Holdin | Permit status: Expired | Permit id: 652760 | |||||
Suppression permit Date: December 1, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 553556 | |||||
Plumbing permit Date: October 28, 2015 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 647885 | |||||
Plumbing permit Date: January 17, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 508684 | |||||
Use permit Date: September 13, 2012 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 420498 | |||||
Alteration permit Date: September 22, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 556989 | |||||
Mechanical permit Date: January 23, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 511512 | |||||
Administrative permit Date: June 25, 2014 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 528107 | |||||
Zoning use permit Date: November 30, 2015 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 648144 | |||||
Alteration permit Date: October 20, 2015 Client: Cathedral Property Holdin | Permit status: Expired | Permit id: 637860 | |||||
Alteration permit Date: September 17, 2013 Client: Cathedral Property Holdin | Permit status: Expired | Permit id: 493366 | |||||
Electrical permit Date: December 13, 2013 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 511182 | |||||
Sign permit Date: November 30, 2015 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 654903 | |||||
Suppression permit Date: November 9, 2015 Client: Cathedral Property Holdin | Permit status: Completed | Permit id: 650943 | |||||
Permit for the one(1) story addition of an existing elevator penthouse roof from 278 to 284 high , for the reduction of dwelling units from two hundred eighty three (283) to a new total of two hundred seventy six ( 276) dwelling units on 3rd thru 25th floors ( increasing the total sq ft of the building but reducing the total countable gfa from 257, 760sf to 248, 055 sf) , increase in retail spaces on 1st floor thru 2nd floor ( from 3,1 sf to 6,264 sf), the creation of electrical mezzanine ( gsf 1,4 sf) on first floor level, for the amenity services including with personal services (fitness center, yoga room, clubroom with kitchen, offices all accessory to the dwellings) ( not as defined as in 14-603(13) at 2nd floor ( 8,329 sf), for the reduction of off-street parking spaces and one(1) h c space from 48 spaces including 4 h c spaces to 42 spaces including 3 h c space and for the creation of bicycle storage spaces for 67 bicycles below grade ( from 9,4 sf to 8,664 sf) ( bicycle parking Date: July 3, 2013 Client: Cathedral Property Holdin | Applicant: Neil Sklaroff, Esquire | Permit type: Appeal | Permit status: Granted/prov | Completion date: August 13, 2013 | Permit id: 20829 | |||||
On 8 20 13, the department of licenses and inspections issued a notice of refusal for application #483854. Date: August 21, 2013 Client: Cathedral Property Holdin | Applicant: Robert Graves, Aia | Permit type: Appeal | Permit status: Approved | Completion date: July 3, 2014 | Permit id: 21131 | |||||
SCORE 100 Foundation only, as indicated per plans. Special inspections by registered engineer is required for underpinning of adjacent structures. Demolition permits to be issued separately - not part of this permit. Foundation permits only issued prior to demo permits per phc. Additional permit plans & approvals required for future sheeting shoring of structure(s) sidewalk-street. For the establishment of a unity of use to create 1 lot for zoning purposes with restrictive covenants and agreements to be recorded by deed to bind current and future owners of the contiguous 5 parcels to preserve the unity of use and the legality of the entire project that stems from the single zoning lot treatment. Prior to issuance of certificate of occupancy,proof of redecoration of easements,agreements and restrictive covenants must be supplied.[re:3717-19 chestnut;3723 chestnut; 3725 chestnut & 3727-29 chestnut street;13-19 s38th (master permit set is 3727 chestnut)] Date: September 17, 2013 Contractor: Intech Construction Inc Client: Cathedral Property Holdin | Permit type: New construction permit | Permit status: Completed | Completion date: February 17, 2016 | Permit id: 489736 | |||||
SCORE 100 Installing two (2)internally illum wall signs "sprint" 6 1 2"x2-0" (13. 75sqft) as per attached drawings. Date: November 30, 2015 Contractor: Ez Signs Llc Client: Cathedral Property Holdin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: November 30, 2015 | Permit id: 648144 | |||||
SCORE 100 Install 2 signs as per attached ez sign standard. Date: November 30, 2015 Contractor: Ez Signs Llc Client: Cathedral Property Holdin | Permit type: Sign permit | Permit status: Completed | Completion date: January 7, 2016 | Permit id: 654903 | |||||
New construction of high rise building and penthouse, associate site and civil work. Foundation and underpinning approvals under ap489737, separate demolition permits under prior individual permits. Included interior exterior alteraions to existing church at 13-19 s38th with interior modifications to existing cathedral undercroft exterior modifications for weathertight connection to adjacent new construction , modifications to existing cathedral for ne doorways and corridor to allow direct access between existing cathedral and adjacent new construction. High rise provisions apply section 403 with reduction.. Additonal permits req: electrical, plumbing, hvac, sprinklers, signs, co and use permit for vacant retail space, and lobby area - amenity fit outs. See cathedral alteraions permit ap501920. For the documentation of a 25 story high rise structure extending into 13-19 s38th street and 3717-19 chestnut. 5 parcels 3717-19, 3723, 3725 and 3727-29 chestnut steet, 13-19 s38th are joined b Date: November 18, 2013 Client: Cathedral Property Holdin | Permit type: New construction permit | Permit status: Completed | Completion date: October 26, 2015 | Permit id: 501263 | |||||
For the partial demo of (3) existing four story structures; for the erection of a twenty six (26) story addition including penthouse 278 feet high (size and location as shown in the application). For vacant commercial space (use registration permit required prior to occupancy), daycare, house of worship, office accessory to the house of worship on 1st floor, two hundred eighty three (283) dwelling units, forty eight (48) accessory below grade parking spaces including (3) handicap spaces without any ticket issuing mechanism, two (2) enclosed loading spaces. No sign on this permit. Date: May 3, 2013 Client: Cathedral Property Holdin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: February 7, 2014 | Permit id: 426355 | |||||
SCORE 99 Installation of hvac system, duct work, roof top mechanicals, accessory mechanicals, mechanical piping, vav boxes, heat pumps, for parking level office building portion at 3717-19 space as per plans and specs. For the documentation of a 3 story structure with vacant retail space, offices and parking garage level extending into 3727 chestnut and 13-19 s38th streets. See ap#501269 (3727 chestnut) for certificate of occupancy and plans. 5 parcels 3717-19, 3723, 3725 and 3727-29 chestnut street, 13-19 s38th are joined by unity of use and known as 3727 chestnut street for zoning purposes only (see zoning permit #420498 for unity of use). Separate parcels retained for all other purposes. Date: January 23, 2014 Contractor: Air Distribution Systems Inc Client: Cathedral Property Holdin | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 13, 2014 | Permit id: 511512 | |||||
SCORE 100 Install sanitary and domestic water supply piping for 1 water closet and 1 lavatory (tie into existing) all work to comply with the 2004 ppc Date: October 28, 2015 Contractor: E J Raith Mechanical Inc Client: Cathedral Property Holdin | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 12, 2015 | Permit id: 647885 | |||||
SCORE 100 Misc. Disconnect,temp. Light and pwr,connect to ex. Panel,breach panel,feeders,light fixtures,switches,recepts,empty box and stubup for comm. Hvac,security as per 2008 nec(west district) Date: December 4, 2014 Contractor: Anmar Electrical Contractor In Client: Cathedral Property Holdin | Permit type: Electrical permit | Permit status: Completed | Completion date: January 6, 2015 | Permit id: 565755 | |||||
SCORE 100 Install one spreaker strobe and one strobe and associated cabling on existing building system per nfpa 72 (retail)west district Date: December 4, 2015 Contractor: Adams Electrical Const Inc Client: Cathedral Property Holdin | Permit type: Electrical permit | Permit status: Expired | Completion date: December 4, 2015 | Permit id: 652760 | |||||
SCORE 77 To amend permit number 489736 to assemble and disassemble a tower crane at 38th street and chestnut street. Street closure permit attached. Date: June 25, 2014 Contractor: Ajs Cranes Llc Client: Cathedral Property Holdin | Permit type: Administrative permit | Permit status: Completed | Completion date: May 9, 2015 | Permit id: 528107 | |||||
SCORE 100 Install panels transformer, recepticle, lighting and equipment, including feeders, branch circuits and devices per plans and the 2008 nec Date: November 27, 2015 Contractor: Adams Electrical Const Inc Client: Cathedral Property Holdin | Permit type: Electrical permit | Permit status: Completed | Completion date: January 25, 2016 | Permit id: 647790 | |||||
SCORE 100 (on chestnut st) 15" rcp wye storm, 15" clp wye sanitary, 12" clp storm, (on ludlow st) 6" clp wye storm, 10" clp wye sanitary Date: January 17, 2014 Contractor: J S Plumbing Company Llc Client: Cathedral Property Holdin | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 6, 2015 | Permit id: 508684 | |||||
SCORE 100 Foundation only - as indicated per plans. Special inspections by registered engineer is required for underpinning of adjacent structures. Demolition permits to be issued separately - not part of this permit. Foundation permits only issued prior to demo permits per phc. Additional permit plans & approvals required for future sheeting shoring of structure(s) sidewalk-street. For the establishment of a unity of use to create 1 lot for zoning purposes with restrictive covenants and agreements to be recorded by deed to bind current and future owners of the contiguous 5 parcels to preserve the unity of use and the legality of the entire project that stems from the single zoning lot treatment. Prior to issuance of certificate of occupancy,proof of redecoration of easements,agreements and restrictive covenants must be supplied.[re:3717-19 chestnut;3723 chestnut; 3725 chestnut & 3727-29 chestnut street;13-19 s38th (master permit set is 3727 chestnut)] Date: September 17, 2013 Contractor: Intech Construction Inc Client: Cathedral Property Holdin | Permit type: New construction permit | Permit status: Completed | Completion date: November 13, 2014 | Permit id: 489737 | |||||
SCORE 96 Interior alterations to create a vacant tenant space #1 with an ada restroom. Separate permit required for fit-out and certificate of occupancy. Date: October 20, 2015 Contractor: Intech Construction Llc Client: Cathedral Property Holdin | Permit type: Alteration permit | Permit status: Expired | Completion date: December 8, 2015 | Permit id: 637860 | |||||
SCORE 100 Install new fire suppression system in accordance with nfpa 13 throughout the entire building. Work to include two (2) new 8" main feeds with sectional valve, two (2) fire pumps installation, two (2) standpipe risers and all branch lines and sprinklers as per approved plans. All work shall comply with the approved plans. All work shall be performed by a fire suppression contractor licensed by the city of philadelphia. Date: December 1, 2014 Contractor: Majek Fire Protection, Inc Client: Cathedral Property Holdin | Permit type: Suppression permit | Permit status: Completed | Completion date: November 13, 2015 | Permit id: 553556 | |||||
SCORE 100 Electrical fire alarm alterations throughout - provide temporary electrical for the jobsite - install electrical fire alarm alterations per the approved plans, the nec 2008 and the nfpa 72 Date: February 7, 2014 Contractor: Anmar Electrical Contractor In Client: Cathedral Property Holdin | Permit type: Electrical permit | Permit status: Completed | Completion date: December 4, 2015 | Permit id: 514980 | |||||
SCORE 99 For installation of a new mechanical hvac system to include ductwork, fire smoke dampers, horizontal shaft enclosures, refrigerant pumps and piping, exhaust fans, water source heat pumps, air conditioning unit, roof top cooling tower, roof top air handling unit, boilers, unit heaters, condensing units, and registers diffusers grilles. Date: September 2, 2014 Contractor: Air Distribution Systems Inc Client: Cathedral Property Holdin | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 13, 2015 | Permit id: 511497 | |||||
SCORE 100 Provide 320ampo single phase 120 208v service to feed 2 (200amp slingle phase panels for construction trailers as per 2008 nec (west district) Date: December 13, 2013 Contractor: Anmar Electrical Contractor In Client: Cathedral Property Holdin | Permit type: Electrical permit | Permit status: Completed | Completion date: April 23, 2014 | Permit id: 511182 | |||||
SCORE 100 Exterior alterations - interior as shown, repairs for masonry restoration, structural and facade remediation. Bell tower repairs and star bolt reinforcements, remove and rebuild top portion of historic chimney, parging, crack repairs, infills, special inspections required as noted. Any sidewalk shelter platform installation requires additional engineer plans and streets department approval. Any sidewalk barriers closures requires streets department permit. Must protect adjacent structures and public way from debris. For the establishment of a unity of use to create 1 lot for zoning purposes with restrictive covenants and agreements to be recorded by deed to bind current and future owners of the contiguous 5 parcels to preserve the unity of use and the legality of the entire project that stems from the single zoning lot treatment. Prior to issuance of certificate of occupancy,proof of redecoration of easements,agreements and restrictive covenants must be supplied.[re:3717-19 chestnut;37 Date: September 17, 2013 Contractor: Intech Construction Inc Client: Cathedral Property Holdin | Permit type: Alteration permit | Permit status: Expired | Completion date: October 20, 2015 | Permit id: 493366 | |||||
Interior alterations to include tenant fit-out as per approved plan to the 3rd floor. Separate permit required for mechanical, electrical, plumbing, and fire suppression work. See ap#501269 for certificate of occupancy. Date: September 22, 2014 Client: Cathedral Property Holdin | Permit type: Alteration permit | Permit status: Completed | Completion date: December 24, 2014 | Permit id: 556989 | |||||
SCORE 100 Relocate heads to fit new wall ceiling layout-3rd floor Date: October 23, 2014 Contractor: Majek Fire Protection, Inc Client: Cathedral Property Holdin | Permit type: Suppression permit | Permit status: Completed | Completion date: December 30, 2014 | Permit id: 569608 | |||||
For the installation of a new hvac system to include ductwork, registers diffusers, ductless split unit, and all other work as per approved plans. Date: October 16, 2014 Client: Cathedral Property Holdin | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 30, 2014 | Permit id: 560091 | |||||
SCORE 100 Relocate 6 sprinkler heads in retail space Date: November 9, 2015 Contractor: Fields Fire Protection Client: Cathedral Property Holdin | Permit type: Suppression permit | Permit status: Completed | Completion date: January 7, 2016 | Permit id: 650943 | |||||
For the one(1) story addition of an existing elevator penthouse roof from 278 to 284 high , the creation of electrical mezzanine ( gsf 1,4 sf) on first floor level, for the creation of bicycle storage spaces for 92 bicycles below grade (bicycle parking along an accessible route). Size and location as shon in the application. For the reduction of dwelling units from two hundred eighty three (283) to a new total of two hundred seventy six ( 276) dwelling units on 3rd thru 25th floors ( increasing the total sq ft of the building but reducing the total countable gfa from 257, 760sf to 248, 055 sf) , increase in retail spaces on 1st floor thru 2nd floor ( from 3,1 sf to 6,264 sf), for the amenity services including with personal services (fitness center, yoga room, clubroom with kitchen, offices all accessory to the dwellings) ( not as defined as in 14-603(13) at 2nd floor (8,329 sf), for the reduction of off-street parking spaces and one(1) h c space from 48 spaces including 4 h c spaces t Date: August 5, 2013 Client: Cathedral Property Holdin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 8, 2014 | Permit id: 478226 | |||||
Application for unity of use agreement as follows demo of (3) existing four story structure; construction of a (25) story structure not inclluding elevator penthouse roof for mixed use including (238) residential dwelling units, retail on ground floor, daycare, office accessory to church, (48) below grade parking spaces including (3) handicap, loading, green roof and playground. Date: September 13, 2012 Client: Cathedral Property Holdin | Permit type: Use permit | Permit status: Completed | Completion date: September 13, 2012 | Permit id: 420498 | |||||
New construction of 3 story building with underground parking level. Included interior exterior alterations to existing church at 13-19 s38th with interior modifications to existing cathedral undercroft exterior modifications for weathertight connection to adjacent new construction , modifications to existing cathedral for ne doorways and corridor to allow direct access between existing cathedral and adjacent new construction. See prior foundation and underpinning approvals ap489737. Demolition of structures on site issued prior under individual permits. Additional permits req: electrical, plumbing, hvac, sprinklers, signs, co and use permit for vacant retail space. See cathedral alterations permit ap501920. Also in relation with high rise permit ap501263. For the documentation of a 3 story structure with vacant retail space, offices and parking garage level extending into 3727-29 chestnut and 13-19 s38th streets. 5 parcels : 3717-19, 3723, 3725 and 3727-29 chestnut street, 13-19 s38t Date: November 1, 2013 Client: Cathedral Property Holdin | Permit type: New construction permit | Permit status: Completed | Completion date: November 12, 2014 | Permit id: 501269 |