Addition permit Date: May 5, 2011 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 336267 | |||||
Sign permit Date: August 23, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 290323 | |||||
New construction permit Date: June 24, 2015 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 615800 | |||||
Zoning/use permit Date: March 14, 2016 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 670485 | |||||
Operations permit Date: May 12, 2014 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 22867 | |||||
Zoning/use permit Date: January 13, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 378017 | |||||
New construction permit Date: July 25, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 88749 | |||||
Sign permit Date: March 7, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 454178 | |||||
Addition permit Date: February 8, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 130388 | |||||
Alteration permit Date: December 29, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 193532 | |||||
Zoning/use permit Date: April 26, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 64431 | |||||
Administrative permit Date: May 23, 2016 Client: Phila Energy Solutions | Permit status: Active | Permit id: 682206 | |||||
Electrical permit Date: July 18, 2014 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 548487 | |||||
Zoning/use permit Date: August 15, 2011 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 354749 | |||||
New construction permit Date: July 24, 2009 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 220289 | |||||
Plumbing permit Date: January 17, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 127198 | |||||
Operations permit Date: September 7, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 20663 | |||||
Zoning/use permit Date: March 4, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 262027 | |||||
Zoning/use permit Date: April 2, 2015 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 591922 | |||||
Plumbing permit Date: July 20, 2009 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 226541 | |||||
Alteration permit Date: April 27, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 263326 | |||||
Electrical permit Date: January 29, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 256475 | |||||
Addition permit Date: November 15, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 115134 | |||||
New construction permit Date: January 13, 2014 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 511508 | |||||
Electrical permit Date: May 30, 2013 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 474400 | |||||
Zoning/use permit Date: June 11, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 154057 | |||||
Zoning/use permit Date: June 8, 2009 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 218599 | |||||
Electrical permit Date: August 6, 2015 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 623031 | |||||
Operations permit Date: August 26, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 22520 | |||||
Alteration permit Date: March 18, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 458246 | |||||
New construction permit Date: July 10, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 161208 | |||||
New construction permit Date: July 25, 2016 Client: Phila Energy Solutions | Permit status: Active | Permit id: 693617 | |||||
Electrical permit Date: May 20, 2016 Client: Phila Energy Solutions | Permit status: Active | Permit id: 689295 | |||||
Zoning permit Date: February 11, 2015 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 576397 | |||||
Alteration permit Date: March 18, 2011 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 325054 | |||||
Plumbing permit Date: February 6, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 54845 | |||||
New construction permit Date: September 5, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 489942 | |||||
New construction permit Date: November 30, 2010 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 311707 | |||||
Zoning/use permit Date: July 30, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 485292 | |||||
Mechanical permit Date: July 27, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 90338 | |||||
Plumbing permit Date: May 22, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 473034 | |||||
Suppression permit Date: July 2, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 158849 | |||||
New construction permit Date: June 13, 2011 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 345662 | |||||
Operations permit Date: October 10, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 21860 | |||||
Addition permit Date: February 10, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 386011 | |||||
Operations permit Date: May 28, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 7611 | |||||
Plumbing permit Date: May 25, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 281167 | |||||
Alteration permit Date: December 29, 2015 Client: Phila Energy Solutions | Permit status: Active | Permit id: 653388 | |||||
Alteration permit Date: February 19, 2016 Client: Phila Energy Solutions | Permit status: Active | Permit id: 663381 | |||||
Electrical permit Date: June 8, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 409932 | |||||
Sign permit Date: April 23, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 398901 | |||||
Operations permit Date: October 8, 2009 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 19864 | |||||
Alteration permit Date: February 29, 2012 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 387750 | |||||
There are alleged violations that are either erroneously stated or overstated or have no factual basis. Some alleged violations should not be the subject of enforcement because they did not occur during normal operations or are in compliance with permit conditons. Date: June 11, 2015 Client: Phila Energy Solutions | Applicant: Paul Amundsen, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 25344 | |||||
Appeal against licenses and inspections for the issuance of zoning/permit #378017 for the subject property. You stated that: the installation of a new digital format sign of this size is inappropriate at the present time because the signage section of the new zoning code has not yet been created. The sign control working group is beginning civic engagement activities this month. Large digital signs invoke unique structural, electrical environmental, safety and aesthetic issues. Best practices on these issues should be determined before this new double faced 96 sign is erected. Date: February 6, 2012 Client: Phila Energy Solutions | Applicant: Stephanie Kindt | Permit type: Appeal | Permit status: Denied | Permit id: 17166 | |||||
There are no penalties stated in the nov; and the alleged violations are either unfounded or do not justify the imposition of penalties; or there are facts and circumstances that mitigate penalty amounts. Date: December 22, 2014 Client: Phila Energy Solutions | Applicant: Paul Amundsen, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 24277 | |||||
This appeal is limited only to certain specific determinations that are erroneous or incorrect. The provisions are noted on the attached copy of the ract plan approval. The provisions on page 4 related to barge loading, which should be applicable only to gasoline or materials with reid vapor pressure of 4 pounds per square inch or greater. Date: February 13, 2015 Client: Phila Energy Solutions | Applicant: Paul Amundsen, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 24632 | |||||
Permit for the erection of two (2) double faced outdoor advertising signs (v shaped, 14 x 48) on the same lot with an existing oil refinery. Date: November 4, 2011 Client: Phila Energy Solutions | Applicant: Leslie Gerstein | Permit type: Appeal | Permit status: Denied | Completion date: March 19, 2012 | Permit id: 16537 | |||||
Many of the alleged violations have no factual or legal basis as they did not occur during normal operations or are otherwise consistent with permit conditions. Date: June 10, 2015 Client: Phila Energy Solutions | Applicant: Paul Amundsen, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 25329 | |||||
The alleged facts do not justify punitive measures. Also, there are or may be mitigating circumstances, and/or defenses, to some or all of the facts as stated which would mitigate or eliminate the call for further administrative action. Date: September 5, 2013 Client: Phila Energy Solutions | Applicant: Michael L. Krancer, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 21233 | |||||
Electrical permit Date: July 18, 2014 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 548487 | |||||
New construction permit Date: June 15, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 81001 | |||||
Zoning use permit Date: March 21, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 361999 | |||||
Plumbing permit Date: May 25, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 281167 | |||||
Alteration permit Date: April 5, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 267839 | |||||
Sign permit Date: April 23, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 398901 | |||||
Operations permit Date: October 19, 2016 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 24534 | |||||
New construction permit Date: September 5, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 489942 | |||||
New construction permit Date: June 13, 2011 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 345662 | |||||
Electrical permit Date: August 13, 2013 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 486631 | |||||
Zoning use permit Date: September 27, 2011 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 364546 | |||||
Alteration permit Date: March 11, 2016 Client: Phila Energy Solutions | Permit status: Active | Permit id: 669204 | |||||
Plumbing permit Date: February 19, 2009 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 199337 | |||||
Zoning use permit Date: March 13, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 458239 | |||||
Electrical permit Date: November 8, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 310612 | |||||
Suppression permit Date: July 2, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 158849 | |||||
Alteration permit Date: October 21, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 182589 | |||||
New construction permit Date: January 13, 2014 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 512443 | |||||
Alteration permit Date: May 15, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 470053 | |||||
Administrative permit Date: November 23, 2016 Client: Phila Energy Solutions | Permit status: Active | Permit id: 727478 | |||||
New construction permit Date: August 11, 2015 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 626262 | |||||
Zoning use permit Date: October 12, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 302011 | |||||
Zoning permit Date: February 11, 2015 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 576397 | |||||
Electrical permit Date: May 20, 2016 Client: Phila Energy Solutions | Permit status: Active | Permit id: 689295 | |||||
Zoning use permit Date: May 18, 2015 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 607039 | |||||
Alteration permit Date: February 29, 2012 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 387750 | |||||
Zoning use permit Date: March 11, 2016 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 669203 | |||||
Alteration permit Date: December 29, 2015 Client: Phila Energy Solutions | Permit status: Active | Permit id: 653388 | |||||
New construction permit Date: November 10, 2010 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 309190 | |||||
Operations permit Date: May 28, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 7611 | |||||
Electrical permit Date: April 7, 2015 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 598653 | |||||
Operations permit Date: October 8, 2009 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 19864 | |||||
Zoning use permit Date: June 8, 2009 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 218599 | |||||
Operations permit Date: May 12, 2014 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 22867 | |||||
Operations permit Date: October 10, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 21860 | |||||
New construction permit Date: July 25, 2016 Client: Phila Energy Solutions | Permit status: Active | Permit id: 686069 | |||||
New construction permit Date: April 28, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 143016 | |||||
Zoning use permit Date: June 3, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 154214 | |||||
Addition permit Date: February 8, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 130388 | |||||
Mechanical permit Date: July 27, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 90338 | |||||
Addition permit Date: November 15, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 115134 | |||||
Alteration permit Date: September 2, 2011 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 356660 | |||||
Plumbing permit Date: February 6, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 54845 | |||||
Zoning use permit Date: July 17, 2007 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 87182 | |||||
Addition permit Date: February 10, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 386011 | |||||
Sign permit Date: August 23, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 290323 | |||||
New construction permit Date: July 23, 2009 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 215608 | |||||
Plumbing permit Date: January 17, 2008 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 127198 | |||||
Electrical permit Date: June 8, 2012 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 409932 | |||||
Sign permit Date: March 7, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 454178 | |||||
Addition permit Date: May 5, 2011 Client: Phila Energy Solutions | Permit status: Expired | Permit id: 336267 | |||||
Operations permit Date: August 26, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 22520 | |||||
Operations permit Date: September 7, 2010 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 20663 | |||||
Plumbing permit Date: May 22, 2013 Client: Phila Energy Solutions | Permit status: Completed | Permit id: 473034 | |||||
Appeal against licenses and inspections for the issuance of zoning permit #378017 for the subject property. You stated that: the installation of a new digital format sign of this size is inappropriate at the present time because the signage section of the new zoning code has not yet been created. The sign control working group is beginning civic engagement activities this month. Large digital signs invoke unique structural, electrical environmental, safety and aesthetic issues. Best practices on these issues should be determined before this new double faced 96 sign is erected. Date: February 6, 2012 Client: Phila Energy Solutions | Applicant: Stephanie Kindt | Permit type: Appeal | Permit status: Denied | Permit id: 17166 | |||||
There are alleged violations that are either erroneously stated or overstated or have no factual basis. Some alleged violations should not be the subject of enforcement because they did not occur during normal operations or are in compliance with permit conditons. Date: June 11, 2015 Client: Phila Energy Solutions | Applicant: Paul Amundsen, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 25344 | |||||
Many of the alleged violations have no factual or legal basis as they did not occur during normal operations or are otherwise consistent with permit conditions. Date: June 10, 2015 Client: Phila Energy Solutions | Applicant: Paul Amundsen, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 25329 | |||||
This appeal is limited only to certain specific determinations that are erroneous or incorrect. The provisions are noted on the attached copy of the ract plan approval. The provisions on page 4 related to barge loading, which should be applicable only to gasoline or materials with reid vapor pressure of 4 pounds per square inch or greater. Date: February 13, 2015 Client: Phila Energy Solutions | Applicant: Paul Amundsen, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 24632 | |||||
Permit for the erection of two (2) double faced outdoor advertising signs (v shaped, 14 x 48) on the same lot with an existing oil refinery. Date: November 4, 2011 Client: Phila Energy Solutions | Applicant: Leslie Gerstein | Permit type: Appeal | Permit status: Denied | Completion date: March 19, 2012 | Permit id: 16537 | |||||
There are no penalties stated in the nov; and the alleged violations are either unfounded or do not justify the imposition of penalties; or there are facts and circumstances that mitigate penalty amounts. Date: December 22, 2014 Client: Phila Energy Solutions | Applicant: Paul Amundsen, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 24277 | |||||
The alleged facts do not justify punitive measures. Also, there are or may be mitigating circumstances, and or defenses, to some or all of the facts as stated which would mitigate or eliminate the call for further administrative action. Date: September 5, 2013 Client: Phila Energy Solutions | Applicant: Michael L. Krancer, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 21233 | |||||
Some alleged violations should not be the subject of enforcement because they did not occur during normal operations or are in compliance with permit conditions. Date: December 19, 2016 Client: Phila Energy Solutions | Applicant: Lisa Runyon, Esq. | Permit type: Appeal | Permit status: Withdrawn | Permit id: 29465 | |||||
Erection of 1 double faced digital monopole outdoor advertising sign (non-accessory). Date: March 7, 2013 Client: Phila Energy Solutions | Permit type: Sign permit | Permit status: Completed | Completion date: August 4, 2015 | Permit id: 454178 | |||||
For the construction of foundation for a 4,0 linear above ground crude oil pipeline. No buildings or structures. Date: March 13, 2013 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: March 15, 2013 | Permit id: 458239 | |||||
Install piles and piles caps for compressors,(no structures) Date: February 2, 2007 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: June 18, 2008 | Permit id: 53928 | |||||
SCORE 68 Annual maintenance permit Date: February 6, 2007 Contractor: Richard Mellwig Client: Phila Energy Solutions | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 1, 2008 | Permit id: 54845 | |||||
Construction of foundations and reinstallation of pipe rack for approximately 1o linear feet of aboveground crude oil pipeline from passyunk ave. To gallows rd. In the south yard of philadelphia energy solution property. Pipe elevation must correspond to approved zoning permit #469826. Date: May 15, 2013 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: February 18, 2015 | Permit id: 470053 | |||||
New construction of a blast resistant control room as part of a refinery. Unit # 433 Date: October 12, 2010 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 302011 | |||||
For the erection of a one (1) story addition max height not to exceed 12 ft for use as extension to existing oil refinery, on the same lot with uses as previously approved. Size and location as shown in the application. Existing oil refinery with uses as previously approved. Date: June 8, 2009 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 218599 | |||||
Install new steel framing to the "867 sulfur expansion project" system to include mechanical equipment, piping, machinery equipment supports, etc. As shown in the submitted drawings. New structures: tail gas valve platform, reboiler structure (6e-203a) and steel structure 6e-210. Foundation issued under permit no. 115134. Date: February 8, 2008 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: September 24, 2010 | Permit id: 130076 | |||||
SCORE 93 1" water service pa20131420395 Date: May 22, 2013 Contractor: L M Service Inc Client: Phila Energy Solutions | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 1, 2013 | Permit id: 473034 | |||||
South yard- former tank farm 189 crude oil pump station and pipeline. Construction of foundations and supports for approx 7 linear feet of pipeline in the south yard of the philadelphia energy solutions property. Date: July 30, 2013 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 1, 2013 | Permit id: 485292 | |||||
SCORE 100 Bakken curde unloading facility new 13. 2 volt service with (2) 15kv transformer, (6) 300hp motors,grounding, (74) light poles with feed and base per 2008 nec (oil refinery) Date: August 6, 2013 Contractor: J J White Inc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Expired | Completion date: August 6, 2013 | Permit id: 485313 | |||||
SCORE 89 Install new 480volt power source to relocated scale house trailer. New power supply to new gurard shack. Underground conduit for gate system and card readers per 2008 nec (oil refinery) Date: August 13, 2013 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Expired | Completion date: August 13, 2013 | Permit id: 486631 | |||||
SCORE 89 Install utility poles & 4 15kv cable, new 2. 4kv cables in cable tray & demo exist 2. 4kv aerial wires, replace old feeder cable to substation & install 350mcm copper 15kv cable on exist poles as per nec 2008 Date: August 29, 2013 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: April 23, 2014 | Permit id: 489359 | |||||
For the erection and installation of foundations, vessels, exchangers, pumps, filters and mechanical equipment in unit 859. Size and location as shown in the application. Equipment accessory to existing oil refinery with uses as previously approved. Date: June 3, 2008 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 154214 | |||||
Installing piping system in accordance with zoning use permit no 507662 Date: January 13, 2014 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: December 14, 2015 | Permit id: 512443 | |||||
Structural work to include constructing new concrete slab foundation base for the "cloud point analyzer" project at existing oil refinery complex, and installing prefab equipment shelter; new concrete slab foundation, framing, and appendages as per designers plans. Special inspections by engineer. Low energy,unconditioned exempted building. Date: January 13, 2014 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: February 3, 2017 | Permit id: 511508 | |||||
SCORE 86 Installation of various foundations for mechanical equipment and non occupied uses as shown per plans Date: July 25, 2007 Contractor: Tantala Albert M Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: June 18, 2008 | Permit id: 88749 | |||||
SCORE 86 Installation of new compressor system, as per submitted plans with prior fooundation permits. Date: July 27, 2007 Contractor: Tantala Albert M Client: Phila Energy Solutions | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 20, 2008 | Permit id: 90338 | |||||
For the installation of geodesic domes on two existing tanks (no. 841 and no. 847) accessory to existing intensive industrial use on the lot. All work to be done per approved plans. If field condition vary contact design engineer prior to the start of any work. Separate permits required for all other work. Date: February 19, 2016 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: July 31, 2017 | Permit id: 663381 | |||||
Construction of foundations and reinstallation of existing pipe rack for 4,0 linear feet of above ground crude oil pipeline. Date: March 18, 2013 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: July 15, 2015 | Permit id: 458246 | |||||
For the erection of a reinforced concrete drilled shaft footing shallow foundation system to support future above grade steel framing & future above-ground pipeline. Earth disturbance not to exceed 5,0 sqft. Date: April 26, 2013 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: February 19, 2015 | Permit id: 462565 | |||||
Construction of foundations 1,0 linear feet above ground crude oil pipeline. Date: May 15, 2013 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: May 15, 2013 | Permit id: 469826 | |||||
For the erection of pipeline foundations approximately 3,5 linear feet of above ground pipeline with supports for the transportation of crude oil, (size and location as shown in plans). For pipeline accessory to an existing oil refinery with all other uses as previously approved. Date: April 10, 2013 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 19, 2013 | Permit id: 462583 | |||||
Install tail gas unit, structural work, as per submitted plans. Refer to prior fdn. Permit 143020 Date: July 10, 2008 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 161208 | |||||
Relocate an existing trailer bldg onto existing foundations of a for tank, to include the construction of a steel support frame, cast in place concrete step,bollards, etc. Relocation and construction shall be in accordance with the submitted drawings. Date: March 11, 2016 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: March 11, 2016 | Permit id: 669203 | |||||
Relocate an existing trailer building onto existing foundations, work to also include the construction of a steel support frame, cast in place concrete steps,bollards, etc. Relocation and construction shall be in accordance with the submitted drawings. If field conditions vary contact design engineer prior the start of any work. Separate permits required for all other work. Date: March 11, 2016 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: July 31, 2017 | Permit id: 669204 | |||||
Includes a ft diameter heated process tank 1 ft tall stack, a 10ftx20ft coalescer tank sever water pumps and water filter, and various equipment and pipe racks that will stankd about 45- ft off the ground. All work located outside of the fema floodplain and within the existing refinary. Total earth distrubance will be 12,105 sf. No buildings associated with this. Date: March 14, 2016 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 670485 | |||||
Erection of steel poles, steel frame supports & steel cable tray supports Date: September 2, 2011 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 356660 | |||||
SCORE 100 Erect two double static faced outdoor advert signs Date: March 21, 2012 Contractor: H A Steen Industries Inc Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 361999 | |||||
Construct new control building as part of oil refinery. Date: September 27, 2011 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 364546 | |||||
Construct, two faced digital monopole outdoor advertising sign. Date: January 13, 2012 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 13, 2012 | Permit id: 378017 | |||||
Install foundations for the common bioplant -oil refinery Date: February 10, 2012 Client: Phila Energy Solutions | Permit type: Addition permit | Permit status: Completed | Completion date: October 17, 2013 | Permit id: 386011 | |||||
Install metal building modular type for office breakroom on prior constructed foundation as aprt of common bioplant 2 brm project in existing refinery area. Addl permits req: electrical, plumbing ,hvac Date: February 29, 2012 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 387750 | |||||
SCORE 100 Erect 2 static double faced non accessory outdoor free-standing advertising signs(v-shapes) Date: April 23, 2012 Contractor: H A Steen Industries Inc Client: Phila Energy Solutions | Permit type: Sign permit | Permit status: Completed | Completion date: July 30, 2012 | Permit id: 398901 | |||||
SCORE 99 Wiring 2 double sided v shaped billboards each with: 8-400watt lights, 1 time clock, 1- amp service and 1-6 circuit panel as per 2008 nec (commercial- sign) Date: June 8, 2012 Contractor: Ciarlante Electric Inc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: July 9, 2012 | Permit id: 409932 | |||||
Install "867 sulfur expansion project" system to include mechanical equipment, piping, machinery equipment supports, etc. As shown in the submitted drawings numbered. New steel framing structures. Date: February 8, 2008 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 130408 | |||||
Install foundations for the unit 433 revamp project,in accordance with submitted drawings. Not approved for any structure above ground. Date: April 28, 2008 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: December 10, 2009 | Permit id: 143016 | |||||
SCORE 89 Fire alarm is being added to a new remote instrument building. Install new fire alarm panel,smoke detectors,pull station and strobes per nfpa 72(oil refinery) Date: March 26, 2015 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: November 6, 2015 | Permit id: 587169 | |||||
Install a pre manufactured preengineered one story shelter building approx 8 x ft for ambient air monitoring purposes. Installation includes construction of perimeter concrete pad and bollards. No change in any existing guildings height, bulk or use. No change in accessory parking or signage. Date: April 2, 2015 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 2, 2015 | Permit id: 591922 | |||||
SCORE 89 2-ambient air fenceline monitoring analyzer shelters, provide 480vac power via aerial distribution to the shelters & install mount analyzer & weather monitoring equipment as per nec 2008 comm Date: April 7, 2015 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: October 28, 2015 | Permit id: 598653 | |||||
SCORE 89 Install 480v & 2. 4kv aerial cable, grounding for concrete pad & to pole & bldg, install xfmr & new conduit on primary & 2nd of xfmr, to pole top & bldg pnl & fire alarm pnls, strobes, horns & pull station as per nec 2008 & nfpa 72(oil refinery) Date: April 28, 2015 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: October 28, 2015 | Permit id: 600905 | |||||
SCORE 70 Hotworks: welding cutting soldering torch work - permit expires: 10 19 16 Date: October 19, 2016 Contractor: Philadelphia Energy Solutions Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 24536 | |||||
SCORE 70 Hotworks: welding cutting soldering torch work - permit expires: 8 29 18 Date: August 29, 2017 Contractor: Philadelphia Energy Solutions Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 25116 | |||||
SCORE 70 Hotworks: welding cutting soldering torch work - permit expires: 8 29 17 Date: August 29, 2017 Contractor: Philadelphia Energy Solutions Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 25117 | |||||
SCORE 60 Install 400a feeder to main distribution panel 480v 3-phase. Power & control for 2 rack pumps, 2 offload pumps, bio blend fuel skid. All work is in non-classified areas. Date: January 29, 2010 Contractor: Devanney Electric Inc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: July 30, 2010 | Permit id: 256475 | |||||
Construct unit 137 rmo rp-752 as shoen in the submitted drawing. No change in existing bldgs hgt, area, floor area, bulk or use. No change in acc parking or acc signage. Date: February 16, 2010 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 257497 | |||||
Installation of six(6) tanks (12 x 40) 33,8 gal for storage of bio-diesel fuel class iiib (above ground) as per plan. Date: February 22, 2010 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: February 22, 2010 | Permit id: 258869 | |||||
Erection compressor structure for an oil refinery Date: February 24, 2010 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: February 24, 2010 | Permit id: 260712 | |||||
Construct unit 1332 h -400 401 scr project Date: March 4, 2010 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: March 4, 2010 | Permit id: 262027 | |||||
"install six (6) 338 gallon tanks for storage of biodiesel fuel, blending system including heated equipment enclosure for blending biodiesel into ultra low sulfur diesel" fuel is class iiib combustible and the installation must comply with section 3404 of the 2007 philadelphia fire code and nfpa 30. Date: March 1, 2010 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 262051 | |||||
For the amendement of previously approved permit #663381 for the removal of the geodesic dome cover on top of existing tank #841. Original permit approved for the installation of geodesic domes on two existing tanks (no. 841 and no. 847) accessory to existing intensive industrial use on the lot. All work to be done per approved plans. If field condition vary contact design engineer prior to the start of any work. Separate permits required for all other work. Date: November 23, 2016 Client: Phila Energy Solutions | Permit type: Administrative permit | Permit status: Completed | Completion date: June 19, 2017 | Permit id: 727478 | |||||
For the lot adjustment to create eight (8) lots (lots 1 through 8) from five (5) deeded lots (36 lanier avenue, 30 penrose ferry road, 3002 penrose ferry road, 3404 penrose avenue, 3144 passyunk avenue)with five opa accounts. Size and location as shown per application plan. Date: February 11, 2015 Client: Phila Energy Solutions | Permit type: Zoning permit | Permit status: Completed | Completion date: February 11, 2015 | Permit id: 576397 | |||||
SCORE 89 Install new 400amp panel,install new lights,receptacles,emergency lights,light switches,connect up heaters and exhaust fans. Fire alarm is being added to a new panel in an adjacent bldg per 2008 nec & nfpa72 (oil refinery) Date: December 12, 2014 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: May 8, 2015 | Permit id: 577651 | |||||
SCORE 86 Install the 1332 unit c3 c4 compressor system Date: July 17, 2007 Contractor: Tantala Albert M Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 87182 | |||||
SCORE 96 Rework 7 125volt 20amp receptacles and 7 2x4 layins in fixtures as per 2008 nec Date: November 8, 2010 Contractor: Briegels Service And Installati Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: January 19, 2011 | Permit id: 310612 | |||||
Construction of a one-story building for use as a control room with employee break room as part of an existing oil refinery Date: November 30, 2010 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 311689 | |||||
Install construct new prefab control room superstructure for unit 8 rmo project, prior foundation permit and approvals ap305628. Date: November 30, 2010 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 311707 | |||||
Work to include foundation and equipment rack for pes 8 cooling water pump project. All work to be done per approved plans. If field conditions vary contact structural engineer prior to the start of any work. Work involves less than 5,0 square feet so it is exempt from pwd stormwater review. Special inspector referenced on submitted forms is yong li p. E; and robert yagle. Separate permits required for all other work. Date: August 11, 2016 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: January 19, 2017 | Permit id: 709930 | |||||
Work to include foundation and equipment rack for pes 864 unifer-coalescer foundation reconfiguration project. All work to be done per approved plans. If field conditions vary contact structural engineer prior to the start of any work. Work involves less than 5,0 square feet so it is exempt from pwd stormwater review. Special inspector referenced on submitted forms is yong li p. E; and robert yagle. Date: August 11, 2016 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: November 10, 2017 | Permit id: 709950 | |||||
Install foundation and superstructure for the ubit 1232 rmo project per plan. Special inspection required for the proposed foundation system. Date: March 18, 2011 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 325054 | |||||
SCORE 89 Install new 400amp panel, install new lights, receptacles & kitchen, emergency lights light switches as per nec 2008 (oil refinery) Date: October 9, 2014 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Expired | Completion date: November 28, 2014 | Permit id: 565193 | |||||
For the installation of structures with associated equipment on the same lot as existing structures and crude oil pipeline. Size and location as shown on application plans. Structures and equipment accessory to an existing intensive industrial use. Date: December 29, 2015 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 29, 2015 | Permit id: 653386 | |||||
Construct foundation, install utilities unit #3 boiler prefab type structure control area for existing oil refinery site. Date: March 18, 2011 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 325844 | |||||
Construct control room addition around existing bldg 59 as per plans Date: April 18, 2011 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 332863 | |||||
Install foundatations only as per plans for oil refinery. Date: May 5, 2011 Client: Phila Energy Solutions | Permit type: Addition permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 336267 | |||||
Construct the superstructure for the "common bioplant 2 control room" per plan. Previous foundation permit 336267. Date: June 13, 2011 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 345662 | |||||
SCORE 87 5 20 08 - hotwork: welding cutting soldering torch work @ sunoco philadelphia refinery - permit expires 5 20 09. Date: May 28, 2008 Contractor: Sunoco Inc Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 7611 | |||||
Equipment foundations unit 137 - compressor skids - sunoco refinery Date: April 9, 2010 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 266151 | |||||
Oil refinery facility: construct new foundation, pile and caps, install prefab building system superstructure blast control room, as per submitted plans. Date: April 7, 2010 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 267221 | |||||
Install foundations and superstructure for the "unit 1332 h-400 401 scr project " no change in ht area floor-area bulk or use. All work shall comply with the approved plans. The contractor of record shall be listed by the district inspector prior to the commencement of work. Date: April 5, 2010 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: June 18, 2012 | Permit id: 267839 | |||||
SCORE 99 Annual plumbing permit for maintenance Date: May 25, 2010 Contractor: Riggs Distler And Co Inc Client: Phila Energy Solutions | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 1, 2011 | Permit id: 281167 | |||||
SCORE 86 Construct additional pile caps and foundations for the 1332 unit, c3 c4 compressor system, in accordance with submitted drawings. Previous piling foundation constructed under permit #53928 Date: June 15, 2007 Contractor: Tantala Albert M Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: June 18, 2008 | Permit id: 81001 | |||||
Level ii exterior alterations to replace portions of an existing, elevated, piping-support structure as per approved plans. Work to include additional concrete foundations, steel column supports, reinforcement of steel pipe racks and installation of concrete pads for pump equipment. Date: June 27, 2017 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Active | Completion date: July 14, 2017 | Permit id: 787731 | |||||
SCORE 99 For the modification of an existing entrance within an existing credit union. All work shall comply with the approved plans. Date: April 27, 2010 Contractor: Blackman And Company Inc Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 263326 | |||||
Erection of a concrete foundation (for the "cloud point analyzer") and erection of a detached equipment shelter maximum height ne 7 ft. Equipment shelter accessory to an existing oil refinery with all other uses as previously approved (no change in existing building height, use. No change in accessory parking or accessory signage). Date: December 26, 2013 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 26, 2013 | Permit id: 511501 | |||||
For the erection of a foundation consisting of 86 steel h piles and related site work for future installation of processing equipment and racks for lsg tier iii project, within "zone 1" (see ap#788260) of intensive industrial site, as per plans and supplemental documents; no other work on this permit; contact structural engineer prior to start of work if there is any variation in field conditions; earth disturbance to be less than 5,0 square feet; area of work is outside the 100-year zone ae flood plain. Date: August 29, 2017 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Active | Completion date: September 19, 2017 | Permit id: 803724 | |||||
For phase i of foundation work for 864 unifer reconfiguration project. First phase to consist of reinforced concrete auger piles. All work to be done per approved plans. If field conditions vary contact structural engineer prior to the start of any work. Work involves less than 5,0 square feet so it is exempt from pwd stormwater review. Special inspector referenced on submitted forms is neil scafonas, p. E. Date: July 25, 2016 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: August 14, 2017 | Permit id: 686069 | |||||
For the erection of a one story building for ambient air monitoring purposes accessory to intensive industial use on the lot. Work to include the construction of a concrete pad, and bollards. All work to be done per approved plans. If field conditions vary contact structural engineer prior to the start of any work. Separate permits required for all other work. Date: May 4, 2015 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: November 7, 2017 | Permit id: 600929 | |||||
SCORE 89 Install new ground grid for rail car unloading facility and install area task lighting,mast lighting and lighting contactor per 2008 nec (oil refinery) Date: September 11, 2014 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: May 8, 2015 | Permit id: 557895 | |||||
SCORE 89 Install new ground grid, new lights, recptacles, cable tray instrumentation, 2. 4kv aerial feeder, mcc, xfmr, rie bldg & cems bldg as per nec 2008 (oil refinery) Date: October 30, 2014 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: November 6, 2015 | Permit id: 567033 | |||||
SCORE 89 Install new fire alarm panel and smoke detectors per 2008 nec & nfpa 72(oil refinery) Date: October 30, 2014 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: December 1, 2014 | Permit id: 569238 | |||||
SCORE 89 Provide power to 4-new cems analyzer shelters for the refinery flares, provide install grounding system at each shelter install aerial conduit powerdist to each per plans as per nec 2008 oil refinery south district Date: August 6, 2015 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: December 30, 2015 | Permit id: 623031 | |||||
For the addition od 22,0 sf area of the existing refinery including with two(2) process towers ( reboiler and splitter tower) with associated equipment on the same lot as existing structures and crude oil pipeline structures and equipment accessory to an existing intensive industrial use. Size and location as shown on application plans. Date: July 14, 2017 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 788260 | |||||
SCORE 89 Install 15kv service to 15kv to 480v xfmr &install pdc bldg. Install ground grid for rail care unloading facility. Install lights,power & instrumentation,cable tray,conduit,aerial cable & bldg wire to facilitate the sow (oil refinery) Date: September 11, 2014 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: May 8, 2015 | Permit id: 557894 | |||||
SCORE 89 Pre fab building will be provided & set by others, provide dual power feeds to new rie bldg, ea ckt is 150amps, 480v installed by using clx cable in cable tray system new ground grid & connect to existing grounding as per 2008 nec (south district) connect up 120v to fire alarm panel as per nfpa72 Date: May 20, 2016 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: August 24, 2017 | Permit id: 689295 | |||||
For phase ii of foundation work for 864 unifer reconfiguration project. Second phase to consist of reinforced concrete pile cap pad and heater support pedestals. All work to be done per approved plans. If field conditions vary contact structural engineer prior to the start of any work. Work involves less than 5,0 square feet so it is exempt from pwd stormwater review. Special inspector referenced on submitted forms is neil scafonas, p. E. Date: July 25, 2016 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: July 31, 2017 | Permit id: 693617 | |||||
SCORE 99 Due to a truck crashing into building rebuild exterior cmu walland 3 interior offices Date: September 22, 2010 Contractor: Blackman And Company Inc Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: December 7, 2012 | Permit id: 296684 | |||||
New construction of a blast resistant control room as part of a refinery unit # 870. Date: September 30, 2010 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 1, 2010 | Permit id: 302012 | |||||
Adding glass resistant control room to a oil refinery. Date: October 12, 2010 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 4, 2011 | Permit id: 304281 | |||||
Foundation work for unit 869 8 rmo project. Operator shelter. Site work. Additional approvals and soils under ap267221 Date: October 26, 2010 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 305628 | |||||
SCORE 99 Legalize new ground sign 5 x as per drawing. Date: June 29, 2010 Contractor: Tupp Signs Incorporated Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 29, 2010 | Permit id: 288320 | |||||
SCORE 96 Installation of an approved fire alarm system according to nfpa-72 and local fire alarm codes (south dist) Date: July 16, 2010 Contractor: Adt Security Svcs Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: March 25, 2011 | Permit id: 290062 | |||||
SCORE 99 Install 5x ground sign as per drawings for a bank. Date: August 23, 2010 Contractor: Tupp Signs Incorporated Client: Phila Energy Solutions | Permit type: Sign permit | Permit status: Completed | Completion date: June 9, 2014 | Permit id: 290323 | |||||
For the erection of a concrete pad ( 35x60)and the equipment rack (extend 20above grade)(cooling water pumps on concrete slab) structures and equipment accessory to an existing intensive industrial use. Size and location as shown on the application plans. Date: August 5, 2016 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 5, 2016 | Permit id: 708214 | |||||
Install unit 867 tail gas project systems to include vessels, exchanges, pumps, tanks filters Date: May 8, 2008 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 143348 | |||||
1-install unit 867 amine modifications system as shown on drawings;2-no change n existing bldgs ht area floor area bukl or use;no change in accessory parking or signs Date: June 11, 2008 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 11, 2008 | Permit id: 154057 | |||||
Install unit 867 sulfur storage system as shown on submitted drawings; 2-no change in existing bldgs ht area floorarea bulk or use;no change in accessory parking or signage Date: June 11, 2008 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 11, 2008 | Permit id: 154059 | |||||
Install foundation for the 867 tail gas unit #2 Date: May 8, 2008 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: December 10, 2009 | Permit id: 143020 | |||||
Install steel framing addition to the "867 sulfur expansion project" system to include mechanical equipment, piping, machinery equipment supports, etc. As shown in the submitted drawings. Steel frame additions: acid gas valve platform, steel structures (6e-209) and (6e-501). See ap#130076 for drawings. Date: February 8, 2008 Client: Phila Energy Solutions | Permit type: Addition permit | Permit status: Completed | Completion date: October 24, 2008 | Permit id: 130388 | |||||
SCORE 89 Install new 480volt power source to relocated analyzer building install new 120 2 panel inside shelter fed from new xfmr install lights and power inside shed per 2008 nec (oil refinery) Date: December 30, 2013 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: June 20, 2014 | Permit id: 511314 | |||||
1. Install a geodesic dome cover (approximately 23- 6" high) atop existing tank no 841. (exisitng tank is apporximately 50-0" high, and has a diameter of approximately 1 feet. 2. Install another geodesic dome cover (apporximately 26-9" high) atop exisitng tank no 847. (existing tank is approximately 48-9" highm and has a diameter of apporximately 1 feet). 3. Tank locations are shown on the submitted drawing no. 9-0-3d 25006d dated nov 15 (rev 0) by pes. [note that similar geodesic dome covers were approved for nos. 885 & 886 by zoning permit no. 653386 dated 29 dec15]for the installation of structures with associated equipment on the same lot as existing structures and crude oil pipeline. Size and location as shown on application plans. Structures and equipment accessory to an existing intensive industrial use. Date: February 19, 2016 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 663379 | |||||
SCORE 87 Hotworks: welding cutting soldering torch work - permit expires 95 12 2014 girard point Date: May 12, 2014 Contractor: Sunoco Inc Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 22876 | |||||
SCORE 70 Hotworks: welding cutting soldering torch work - permit expires: Date: October 19, 2016 Contractor: Philadelphia Energy Solutions Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 24534 | |||||
SCORE 87 Hotworks: welding cutting soldering torch work - permit expires point breeze 05 12 2015 srtf location Date: May 12, 2014 Contractor: Sunoco Inc Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 22875 | |||||
SCORE 100 Sunoco refinery Date: October 10, 2012 Contractor: Taylor Rental 1309 Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 21860 | |||||
Install foundations for the unit 859 rmo project. Date: July 23, 2009 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: February 2, 2010 | Permit id: 215608 | |||||
Upgrade existing bulkhead foundation Date: November 3, 2008 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: February 26, 2009 | Permit id: 184533 | |||||
Install revamp system superstructure for oil refinery Date: October 27, 2008 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 27, 2008 | Permit id: 180063 | |||||
Isntall 433 pip revamp system superstructure in oil refinery per submitted sealed plans. Date: October 27, 2008 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 180064 | |||||
Install foundations for the "867 amine system modifications projects" as per plans Date: October 21, 2008 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 182589 | |||||
Install the 867 amine system modifications project super structure as per plans Date: December 29, 2008 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 193532 | |||||
SCORE 89 Fire alarm is being added to a new deluge building in the south yard. Install new fire alarm panel,low flow switches,smoke detectors,pull station and strobes per nfpa 72 (oil refinery) Date: March 26, 2015 Contractor: Matrix North American Construc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: November 6, 2015 | Permit id: 587163 | |||||
For the erection of one (1) detached structure on the same lot as existing structures and crude oil pipeline. Size and location as shown on plans application. Structures accessory to an existing intensive industrial use. Date: July 6, 2015 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 6, 2015 | Permit id: 618923 | |||||
For the erection of a one story building for flare monitoring purposes accessory to intensive industrial use on the lot and for modification to existing flare stack structure. All work to be done per approved plans, construction to include concrete foundations, bollards and structural steel reinforcement. If field conditions vary contact structural engineer prior to the start of any work. Separate permits required for all other work. Date: June 24, 2015 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: May 31, 2017 | Permit id: 615800 | |||||
Install a pre manufactured one story building. Modify the lower portions of an existing flare stack structure. Construct a proposed structural steel stair tower providing access to a proposed structural steel platform. Per plans Date: May 18, 2015 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 607039 | |||||
Installation of reinforced concrete foundations for structures and various process equipment, and equipment pipe racks for the lsf tier iii project. Application to also include the foundation system of two unoccupied equipment sheds (cems and pdc) that are being relocated from other areas. The sheds have been granted an ada compliance waiver (ab#2017-137 file #528985 dated 0725 2017). Separate permits required for relocation and erection of structures. All work to be done per approved plans. If field conditions vary contact structural engineer prior to the start of any work. Pwd storm water review has been approved for the entire project site. Special inspector referenced on submitted forms is occie a norton, p. E. Date: October 10, 2017 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Active | Completion date: October 31, 2017 | Permit id: 817911 | |||||
Construct utilities unit #3 boiler as shown on drawings. Date: February 1, 2011 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 4, 2011 | Permit id: 320361 | |||||
Construct a substation feeder project.-oil refinery Date: August 15, 2011 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 15, 2011 | Permit id: 354749 | |||||
SCORE 100 Extending extg deluge system, installation new heads, lines as per plans. Date: July 2, 2008 Contractor: Simplexgrinnell Client: Phila Energy Solutions | Permit type: Suppression permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 158849 | |||||
Installation of new foundations for the "867 sulfur project" sulfur wall pit, as per submitted drawings; no change in existing building Date: June 11, 2008 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: December 10, 2009 | Permit id: 156775 | |||||
SCORE 100 Furnish and install 61 wood poles,94 pole mounted flood lights,(2)125amp services and (1)75kva transformer per 2008 nec (oil refinery) Date: July 18, 2014 Contractor: Carr And Duff Co Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: January 12, 2015 | Permit id: 548487 | |||||
SCORE 70 Hotworks: welding cutting soldering torch work - permit expires:10 19 17 Date: October 19, 2016 Contractor: Philadelphia Energy Solutions Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 24535 | |||||
For the installation of geodesic domes on two existing tanks (no. 885 and no. 886) accessory to existing intensive industrial use on the lot. All work to be done per approved plans. If field condition vary contact design engineer prior to the start of any work. Separate permits required for all other work. Date: December 29, 2015 Client: Phila Energy Solutions | Permit type: Alteration permit | Permit status: Completed | Completion date: July 31, 2017 | Permit id: 653388 | |||||
SCORE 99 Provide conduit, fittings, wire cable at exist refinery, consists of 15kv & 480v, utility poles, aerial cable, valve connections instrumentation devices & control some work in classified area as per nec 2008 (refinery) Date: August 27, 2013 Contractor: Riggs Distler And Co Inc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Completed | Completion date: January 3, 2014 | Permit id: 489657 | |||||
SCORE 86 Install and modify above-grade items of the "unit 1232 expansion an dfgt project" system, to include all necessary equipment, piping, supports, ect. Date: April 26, 2007 Contractor: Tantala Albert M Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: May 9, 2007 | Permit id: 64431 | |||||
For the amendment of building permit no. 653388 by changing the contractor for the installation of tank no. 885 to j. J. White, inc. Original permit approved for the for the installation of geodesic domes on two existing tanks (no. 885 and no. 886) accessory to existing intensive industrial use on the lot. All work to be done per approved plans. If field condition vary contact design engineer prior to the start of any work. Separate permits required for all other work. Date: May 23, 2016 Client: Phila Energy Solutions | Permit type: Administrative permit | Permit status: Completed | Completion date: June 15, 2017 | Permit id: 682206 | |||||
Install the 859 rmo project superstructure as per plans. Foundations previously permitted under ap #215608. Date: July 24, 2009 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: October 12, 2011 | Permit id: 220289 | |||||
Install piping at gas station Date: December 23, 2013 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 23, 2013 | Permit id: 507662 | |||||
Construction of foundations and supports for approximately 7 linear feet of pipeline in the south yard of the philadelphia energy solutions property. Project includes pump pad, transformer pad and a pre-fabricated electrical shed. All work to be done per approved plans, pipe line to be located 4 to 24 feet above existing grade depending on location, existing disturbance to be 31,5 sqft. Date: September 5, 2013 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Completed | Completion date: February 18, 2015 | Permit id: 489942 | |||||
SCORE 68 Install house drain,trap and fixtures in blast proof building Date: July 20, 2009 Contractor: Richard Mellwig Client: Phila Energy Solutions | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 10, 2009 | Permit id: 226541 | |||||
SCORE 100 09 27 2013 erect assembly tent for philadelphia energy solutions Date: August 26, 2013 Contractor: Taylor Rental 1309 Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 22520 | |||||
SCORE 87 Hotworks: welding cutting soldering torch work - permit expires 05 12 2015 point breeze location Date: May 12, 2014 Contractor: Sunoco Inc Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 22867 | |||||
SCORE 99 Installing a new 3 amp service and wiring two digital billboards as per 2008 nec. Date: May 30, 2013 Contractor: Ciarlante Electric Inc Client: Phila Energy Solutions | Permit type: Electrical permit | Permit status: Expired | Completion date: May 30, 2013 | Permit id: 474400 | |||||
Install foundation at oil refinery Date: November 10, 2010 Client: Phila Energy Solutions | Permit type: New construction permit | Permit status: Expired | Completion date: May 7, 2013 | Permit id: 309190 | |||||
SCORE 68 Annual plumbing permit for maintenance Date: January 17, 2008 Contractor: Richard Mellwig Client: Phila Energy Solutions | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 8, 2008 | Permit id: 127198 | |||||
Install "867 sulfur expansion project" system to include mechanical equipment, piping, machinery equipment supports, etc. As shown in the submitted drawings numbered. New steel frame additions extending existing steel frame structures. Date: February 8, 2008 Client: Phila Energy Solutions | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 10, 2017 | Permit id: 128348 | |||||
SCORE 86 Construct new foundation system only, as per plans, for oil refinery equipment machinery. Date: November 15, 2007 Contractor: Tantala Albert M Client: Phila Energy Solutions | Permit type: Addition permit | Permit status: Completed | Completion date: October 24, 2008 | Permit id: 115134 | |||||
SCORE 99 Annual plumbing permit for maintenance Date: February 19, 2009 Contractor: Riggs Distler And Co Inc Client: Phila Energy Solutions | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 29, 2009 | Permit id: 199337 | |||||
SCORE 87 Hotworks: welding cutting soldering torch work - permit expires 01 25 2013 Date: January 25, 2012 Contractor: Sunoco Inc Client: Phila Energy Solutions | Permit type: Operations permit | Permit status: Completed | Permit id: 21399 |