Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 New sfd, 4031 sf (3341 finished sf, 6 sf attached garage, 554 sf of decks & covered porches) 5 bedrooms, 3. 5 bathrooms. New 3 amp service. Steep slope, mass movement area Client: Stewart Cohune, Cohune | Applicant: Ellsworth Builders, Inc. | Permit type: Building, electrical | Permit status: Co | Current use: Single family d | |||||
SCORE 99 Electrical permit only for temporary construction power. Date: September 12, 2007 Contractor: Heres Howe Inc Client: Stewart Cohune, Cohune | Applicant: Heres Howe, Inc. | Permit type: Electrical | Permit status: Cmp | Completion date: August 18, 2008 | Current use: Single family d | |||||
SCORE 100 Full structure demolition of an existing sfd, see his2007-00245 for landmarks approval. Date: September 19, 2007 Contractor: Ellsworth Builders Inc Client: Stewart Cohune, Cohune | Applicant: Ellsworth Builders, Inc. | Permit type: Demolition | Permit status: Cmp | Completion date: December 31, 2007 | Current use: Single family d | |||||
SCORE 100 Install new gas service Date: November 13, 2007 Contractor: Xcel Energy Client: Stewart Cohune, Cohune | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Upgrade meter pit Date: November 14, 2007 Contractor: Eba Inc Client: Stewart Cohune, Cohune | Applicant: Eba Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 81 Remove replace existing concrete curbwalk in front of residence Date: May 19, 2008 Contractor: Lawson Construction Co Client: Stewart Cohune, Cohune | Applicant: Lawson Construction Co | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Installation of a flush mount grid-tie 6. 12 kw photovoltaic system array to remain below ridge, inside below hips and rake edges, and above eave. See engineerfoots letter and drawing for specific information. Date: January 30, 2012 Contractor: Lighthouse Solar Client: Bulend Corbacioglu,Sonja Corbacioglu | Applicant: Lighthouse Solar | Permit type: Photovoltaic | Permit status: Cmp | Completion date: February 13, 2012 | Current use: Single family d | |||||
SCORE 100 Installation of a flush mount grid-tie 6. 12 kw photovoltaic system array to remain below ridge, inside below hips and rake edges, and above eave. See engineerfoots letter and drawing for specific information. Client: Bulend Corbacioglu | Permit type: Photovoltaic | Permit status: Cmp | Completion date: February 13, 2012 | Current use: Single family detached dwelling, existin | Permit id: Pmt2012-00387 | |||||
SCORE 99 Electrical permit only for temporary construction power. Date: September 12, 2007 Contractor: Heres Howe, Inc Client: Stewart Cohune | Permit type: Electrical | Permit status: Cmp | Completion date: August 18, 2008 | Current use: Single family detached dwelling, existin | Permit id: Pmt2007-03956 | |||||
SCORE 99 Full structure demolition of an existing sfd, see his2007-00245 for landmarks approval. Date: September 19, 2007 Contractor: Ellsworth Builders, Inc Client: Stewart Cohune | Permit type: Demolition | Permit status: Cmp | Completion date: December 31, 2007 | Current use: Single family detached dwelling, existin | Permit id: Pmt2007-04099 | |||||
Install new gas service Date: November 13, 2007 Client: Stewart Cohune | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-05061 | |||||
SCORE 99 New sfd, 4031 sf (3341 finished sf, 6 sf attached garage, 554 sf of decks & covered porches) 5 bedrooms, 3. 5 bathrooms. New 3 amp service. Steep slope, mass movement area Client: Stewart Cohune | Permit type: Building, electrical, mechanical, plumbing, water, wastewater, right-of-way | Permit status: Co | Current use: Single family detached dwelling, new, ga | Permit id: Pmt2007-03095 |