SCORE 100 Commercial shell building and mezzanine bldg 6 51,052 sq ft Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: July 20, 2006 | Permit id: 0501100039 | |||||
SCORE 80 New retaining wall 0. 5-7h x 211l Applicant: Bb&g Consulting Alisa | Permit status: Finaled | Completion date: July 20, 2006 | Permit id: 0502100047 | |||||
SCORE 80 New retaining wall 1-6h x 60l Applicant: Bb&g Consulting Alisa | Permit status: Finaled | Completion date: July 20, 2006 | Permit id: 0502100048 | |||||
SCORE 100 Ti to add offices on 1st fl/mezz/warehouse/restrms/shipping/ service area/elect. Rm 20,751 sq ft Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0510210022 | |||||
SCORE 80 New retaining wall 2-10h x 409l Applicant: Bb&g Consulting Alisa | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0512160029 | |||||
SCORE 99 Fire sprinklers for comm shell 533 heads 46,474 sq ft Applicant: Guardian Fire Protection,Inc | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0601260025 | |||||
SCORE 100 Ti to add foundation for future exterior nitrogen tank Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0603280032 | |||||
SCORE 95 Ti add freestanding ceiling in the warehouse 5,3 sq ft Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: August 24, 2006 | Permit id: 0605170002 | |||||
SCORE 100 Ti install storage racks 29 sq ft Applicant: Advanced Industrial Solutions | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0606010013 | |||||
T. I. To add non-bearing walls for clean rooms 2,0 sq ft Date: May 8, 2007 Value: $30,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 22, 2007 | Permit id: 0609280070 | |||||
SCORE 99 Fire sprinklers for t. I. In mezzanine area 5,6 sq ft Applicant: Guardian Fire Protection,Inc. | Permit status: Finaled | Completion date: May 22, 2007 | Permit id: 0611300012 | |||||
SCORE 98 Temporary power pole 200amp w/4 sub poles Date: July 8, 2005 Contractor: S And S Construction Applicant: S & S Construction Services | Permit status: Permisud | Permit id: 0507080024 | |||||
SCORE 98 Electrical for comm. Shell building and mezzanine bldg 6 Date: August 25, 2005 Contractor: Southern Power Inc Applicant: Southern Power Inc | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0508040028 | |||||
SCORE 98 Elect. For t. I. To add offices-1st fl/mezz/warehouse/ restrms/shipping/service area/elect. Rm Date: February 22, 2006 Contractor: Southern Power Inc Applicant: Southern Power Inc | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0602210052 | |||||
SCORE 98 Additional elect. For t. I. Date: June 14, 2006 Contractor: Southern Power Inc Applicant: Southern Power Inc | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0606140021 | |||||
SCORE 100 Temp. Power pole for const. Of new comm shell bldg and mezz Date: June 19, 2006 Contractor: Andy Gump Inc Applicant: Garcia Randy | Permit status: Permisud | Permit id: 0606190036 | |||||
SCORE 99 Elec for t. I. Date: May 10, 2007 Contractor: G R C Electric Applicant: Grc | Permit status: Finaled | Completion date: May 22, 2007 | Permit id: 0705100034 | |||||
SCORE 95 Landscaping for lots,1 thru 5 and 7 thru 11. 15 acres Date: July 19, 2006 Contractor: Owner Applicant: Bb&g Consulting Alisa | Permit status: Finaled | Completion date: July 20, 2006 | Permit id: 0506010001 | |||||
SCORE 99 Mech for t. I. 20,751 sq ft Date: March 22, 2006 Contractor: Wittler Young Co. Inc Applicant: Wither Young Co Inc | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0603220030 | |||||
SCORE 65 Mechanical for t. I. To add non-bearing walls for clean rooms Date: May 9, 2007 Contractor: Canoga Park Hvac Applicant: Canoga Park Ac - Wade Keith | Permit status: Finaled | Completion date: May 22, 2007 | Permit id: 0705090018 | |||||
Lot line adjustment for lots 1,2,3 Date: September 28, 2005 Value: $10,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: October 6, 2005 | Permit id: 0509190002 | |||||
SCORE 98 Plumbing for comm. Shell building and mezzanine bldg 6 Date: August 16, 2005 Contractor: Andersen Commercial Plumbing Applicant: Bb&g Consulting | Permit status: Finaled | Completion date: July 20, 2006 | Permit id: 0508040011 | |||||
SCORE 98 Plumbing for t. I. To add offices-1st fl/mezz/warehouse/ restrms/shipping/service area/elect. Rm Date: February 22, 2006 Contractor: Andersen Commercial Plumbing Applicant: Benitez Jose | Permit status: Finaled | Completion date: July 18, 2006 | Permit id: 0602210028 |