Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Ret wall 5hx70l Applicant: Davidon Homes | Permit status: Finaled | Completion date: March 1, 2001 | Permit id: 0006200035 | |||||
SCORE 100 New sfd plan 1br 3015/692 sq ft Applicant: Davidon Homes | Permit status: Finaled | Completion date: March 1, 2001 | Permit id: 0007250058 | |||||
New shade bar patio 4 sq ft Date: August 16, 2001 Value: $8,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: April 30, 2002 | Permit id: 0108160013 | |||||
SCORE 100 Gunite spa 68 sq ft standard plan 26072 Applicant: Bouquet Construction | Permit status: Finaled | Completion date: December 12, 2001 | Permit id: 0107270001 | |||||
SCORE 100 Electric 3015/692 sq ft Date: September 29, 2000 Contractor: Davidon Homes Applicant: Davidon Homes | Permit status: Finaled | Completion date: March 1, 2001 | Permit id: 0009290004 | |||||
SCORE 100 Elec for bbq Date: July 27, 2001 Contractor: Bouquet Construction Applicant: Bouquet Construction | Permit status: Finaled | Completion date: April 30, 2002 | Permit id: 0107270005 | |||||
SCORE 100 Mechanical Date: September 29, 2000 Contractor: Davidon Homes Applicant: Davidon Homes | Permit status: Finaled | Completion date: March 1, 2001 | Permit id: 0009290014 | |||||
SCORE 100 Plumbing Date: September 29, 2000 Contractor: Davidon Homes Applicant: Davidon Homes | Permit status: Finaled | Completion date: March 1, 2001 | Permit id: 0009290021 | |||||
SCORE 100 Gas line for bbq Date: July 27, 2001 Contractor: Bouquet Construction Applicant: Bouquet Construction | Permit status: Finaled | Completion date: April 30, 2002 | Permit id: 0107270004 | |||||
SCORE 100 Sewer Date: October 3, 2000 Contractor: Davidon Homes Applicant: Davidon Homes | Permit status: Finaled | Completion date: March 1, 2001 | Permit id: 0010030002 |