Temp sales trailer for tract Date: December 12, 2001 Value: $5,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: December 6, 2002 | Permit id: 0112120044 | |||||
SCORE 90 Ret wall 2x68long Applicant: G O Construction | Permit status: Finaled | Completion date: March 25, 2008 | Permit id: 0302250016 | |||||
SCORE 90 New shade bar patio 5 sq ft Applicant: G O Construction | Permit status: Finaled | Completion date: July 10, 2003 | Permit id: 0302250018 | |||||
SCORE 95 New roof mount solar pv 422 sq ft,24 panels,6. 1 kw Applicant: Verengo Inc | Permit status: Finaled | Completion date: June 6, 2012 | Permit id: 1205100026 | |||||
New sfd/garage plan 5 bx 3752/669 sq ft bedroom 6/bath on 2nd floor Date: June 12, 2002 Value: $416,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: December 6, 2002 | Permit id: 0206050012 | |||||
SCORE 100 Tpp for construction trailer 2 amp Date: December 4, 2001 Contractor: Andy Gump Inc Applicant: Andy Gump | Permit status: Finaled | Completion date: December 5, 2001 | Permit id: 0112040028 | |||||
SCORE 100 5 sub poles for tract construction Date: April 9, 2002 Contractor: Andy Gump Inc Applicant: Andy Gump | Permit status: Finaled | Completion date: April 10, 2002 | Permit id: 0204090019 | |||||
SCORE 100 Tpp for tract Date: May 15, 2002 Contractor: Andy Gump Inc Applicant: Andy Gump | Permit status: Finaled | Completion date: December 6, 2002 | Permit id: 0205150044 | |||||
SCORE 95 Electrical for roof mount solar pv 24 panels,6. 1 kw add 125 a sub panel Date: May 22, 2012 Contractor: Verengo Inc Applicant: Verengo Inc | Permit status: Finaled | Completion date: June 6, 2012 | Permit id: 1205100019 | |||||
SCORE 100 Mechanical to replace (2) ac units - same location Date: July 17, 2009 Contractor: Pacific Aire Applicant: Pacific Aire | Permit status: Finaled | Completion date: December 12, 2011 | Permit id: 0907170010 | |||||
SCORE 90 Gas line for future use Date: February 25, 2003 Contractor: G O Construction Applicant: G O Construction | Permit status: Finaled | Completion date: July 10, 2003 | Permit id: 0302250011 |