ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
New 12 unit townhouses with above subterranean parking Date: November 9, 2000 Value: $1,831,000Applicant: Same As Owner | Permit status: Finaled | Completion date: February 1, 2002 | Permit id: 0003220045 | |||||
Demolish duplex Date: August 18, 2000 Value: $3,000Applicant: Same As Owner | Permit status: Finaled | Completion date: November 13, 2000 | Permit id: 0008180028 | |||||
Retaining wall for 12 unit townhouses Date: August 29, 2000 Value: $12,000Applicant: Same As Owner | Permit status: Finaled | Completion date: February 1, 2002 | Permit id: 0008290040 | |||||
SCORE 61 Fire sprinkler for 12 unit townhouses Applicant: Y-Z Plumbing,Inc. | Permit status: Finaled | Completion date: February 1, 2002 | Permit id: 0104160012 | |||||
SCORE 89 Roof mounted photovoltaic system Applicant: Webb Wade | Permit status: Finaled | Completion date: February 11, 2004 | Permit id: 0401130060 | |||||
SCORE 83 Add new bathroom in garage and non-bearing wall. Applicant: Gagossian Raffi | Permit status: Finaled | Completion date: November 13, 2009 | Permit id: 0908050027 | |||||
SCORE 61 Apply 4 ply built up roof over 1 existing layer of built up Applicant: Hwang Ha Joo | Permit status: Finaled | Completion date: January 31, 2012 | Permit id: 1110310072 | |||||
Temporary power pole Date: August 29, 2000Applicant: Same As Owner | Permit status: Finaled | Completion date: November 3, 2000 | Permit id: 0008290038 | |||||
SCORE 91 Electrical for 12-unit townhouses Date: December 20, 2000 Contractor: 3 Phase ElectricApplicant: 3 Phase Electric | Permit status: Finaled | Completion date: February 1, 2002 | Permit id: 0012200004 | |||||
SCORE 89 Electrical for roof mounted photo-voltaic system. Date: February 2, 2004 Contractor: Solar Webb IncApplicant: Webb Wade | Permit status: Finaled | Completion date: February 11, 2004 | Permit id: 0402020035 | |||||
SCORE 83 Electrical for new bathroom in garage and non-bearing wall Date: September 30, 2009 Contractor: Gartal ConstructionsApplicant: Gagossian Raffi | Permit status: Finaled | Completion date: January 31, 2012 | Permit id: 0909300029 | |||||
Site preparation Date: August 29, 2000Applicant: Same As Owner | Permit status: Finaled | Completion date: February 1, 2002 | Permit id: 0006060002 | |||||
SCORE 56 12 package units installed on apartment roof. Date: March 19, 2001 Contractor: D And A AirApplicant: Markosain Khachatur | Permit status: Finaled | Completion date: February 1, 2002 | Permit id: 0103190005 | |||||
SCORE 82 New plumbing fixtures for the 12 unit apartments Date: November 9, 2000 Contractor: Sergios PlumbingApplicant: Sergios Plumbing Co | Permit status: Finaled | Completion date: February 1, 2002 | Permit id: 0011090016 | |||||
SCORE 83 Plumbing for new bathroom in garage Date: August 5, 2009 Contractor: Gartal ConstructionsApplicant: Gagossian Raffi | Permit status: Finaled | Completion date: November 13, 2009 | Permit id: 0908050036 | |||||
SCORE 82 Connect 12-unit tounhouses to public sewer Date: September 28, 2001 Contractor: Sergios PlumbingApplicant: Sergios Plumbing Co | Permit status: Finaled | Completion date: February 1, 2002 | Permit id: 0109280009 |