Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical permit Date: December 2, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 485085 | |||||
Plumbing permit Date: July 23, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 475930 | |||||
Zoning/use permit Date: January 17, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 447767 | |||||
Addition permit Date: January 17, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 443586 | |||||
Use permit Date: August 13, 2012 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 421725 | |||||
Mechanical permit Date: May 23, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 473451 | |||||
Electrical permit Date: January 24, 2014 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 515548 | |||||
Demolition permit Date: October 16, 2012 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 432780 | |||||
Suppression permit Date: June 25, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 473243 | |||||
Zoning/use permit Date: September 6, 2012 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 425783 | |||||
Electrical permit Date: December 2, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 485085 | |||||
Mechanical permit Date: May 23, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 473451 | |||||
Addition permit Date: January 17, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 443586 | |||||
Demolition permit Date: October 16, 2012 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 432780 | |||||
Zoning use permit Date: September 6, 2012 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 425783 | |||||
Suppression permit Date: June 25, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 473243 | |||||
Electrical permit Date: January 24, 2014 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 515548 | |||||
Plumbing permit Date: July 23, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 475930 | |||||
Use permit Date: August 13, 2012 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 421725 | |||||
Zoning use permit Date: January 17, 2013 Client: Chesire Equity Llc | Permit status: Completed | Permit id: 447767 | |||||
13 appartments Date: August 13, 2012 Client: Chesire Equity Llc | Permit type: Use permit | Permit status: Completed | Completion date: August 13, 2012 | Permit id: 421725 | |||||
SCORE 100 Extending 3rd and 4th floor to meet 1st and 2nd floor line. Date: September 6, 2012 Contractor: United Maker Client: Chesire Equity Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 6, 2012 | Permit id: 425783 | |||||
Renovation and addition to existing four story structure for 13 residential apartments. Asbestos abatement required prior to the start of work. Date: January 17, 2013 Client: Chesire Equity Llc | Permit type: Addition permit | Permit status: Completed | Completion date: February 21, 2014 | Permit id: 443586 | |||||
SCORE 96 Interior demolition of non load bearing partitions in vacant apartments. Call inspector for an initial inspection prior to the start of work. Date: October 16, 2012 Contractor: Msj Contractors Llc Client: Chesire Equity Llc | Permit type: Demolition permit | Permit status: Completed | Completion date: July 1, 2013 | Permit id: 432780 | |||||
Extending 3rd and 4th floor to meet 1st and 2nd floor line. Date: January 17, 2013 Client: Chesire Equity Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 17, 2013 | Permit id: 447767 | |||||
SCORE 100 Installation of a 2 service line, new automatic wet sprinkler system throughout per nfpa 13r, a new fire pump and a new backflow as per plans. Date: June 25, 2013 Contractor: Oneida Fire Protection Client: Chesire Equity Llc | Permit type: Suppression permit | Permit status: Completed | Completion date: February 27, 2014 | Permit id: 473243 | |||||
SCORE 100 13 apartments with heater and ductwork, 2 tons of ac. All hvac units and duct work installed in separate units. No penetrations through rated assemblies. Date: May 23, 2013 Contractor: Ss Mechanicals Hvac Client: Chesire Equity Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 27, 2014 | Permit id: 473451 | |||||
SCORE 93 Install new waste lines from fixtures, new soil stacks, water to fixtures, 13-toilet, 13-lavs, 13-kitchen sinks, 13-washing machine (multi units) Date: July 23, 2013 Contractor: Oleg Kapkanov Client: Chesire Equity Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 5, 2015 | Permit id: 475930 | |||||
SCORE 100 Install service,install all wiring thoughout 13 apartments and fa done by others per 2008 nec. Installation to comply with articles 210. 8, 210. 12, 210. 52(a)(b)(c) & 406. 11 of the 2008 nec. Smoke co detectors to be on an obvious lighting circuit. Date: December 2, 2013 Contractor: Baldwin Electrical Const Llc Client: Chesire Equity Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: April 28, 2015 | Permit id: 485085 | |||||
SCORE 100 Install addressable fire alarm system as per nfpa72 (cc district) Date: January 24, 2014 Contractor: Baldwin Electrical Const Llc Client: Chesire Equity Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: May 4, 2015 | Permit id: 515548 |