Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 99 Sewer connection for new sfd Date: November 18, 2005 Contractor: Trivalley Mechanical Inc Applicant: Tri-Valley Mechanical Inc. | Permit status: Finaled | Completion date: June 20, 2006 | Expiration date: May 17, 2006 | Permit id: 511180012 | |||||
Plum conduit for future bbq Date: January 17, 2007 Applicant: Same As Owner | Permit status: Finaled | Completion date: September 27, 2007 | Expiration date: July 16, 2007 | Permit id: 701170006 | |||||
Elec conduit for future bbq Date: January 17, 2007 Applicant: Same As Owner | Permit status: Finaled | Completion date: September 27, 2007 | Expiration date: July 16, 2007 | Permit id: 701170009 | |||||
SCORE 100 New roof mount solar pv 4. 6 kw, 14 panels, 254 sq ft Engineer: Bassenian Logoni Architects | Applicant: Green Convergence | Permit status: Finaled | Completion date: June 29, 2015 | Expiration date: June 17, 2016 | Permit id: 1506160005 | |||||
New sfd/garage plan 2cr 2725/597 sq ft Date: October 26, 2005 Value: $293,000 Engineer: Bassenian Logoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: June 20, 2006 | Expiration date: April 24, 2006 | Permit id: 510070019 | |||||
New sfd garage plan 2cr 2725 597 sq ft Date: October 26, 2005 Value: $293,000 Engineer: Bassenian Logoni Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: June 20, 2006 | Expiration date: April 24, 2006 | Permit id: 510070019 | |||||
SCORE 99 Sewer connection for new sfd Date: November 18, 2005 Contractor: Trivalley Mechanical, Inc Applicant: Tri-Valley Mechanical Inc. | Permit status: Finaled | Completion date: June 20, 2006 | Expiration date: May 17, 2006 | Permit id: 511180012 |