Zoning/use permit Date: September 20, 2012Client: Labrensz Joshua M | Permit status: Completed | Permit id: 424087 | |||||
Plumbing permit Date: February 25, 2013Client: Labrensz Joshua M | Permit status: Completed | Permit id: 455537 | |||||
Mechanical permit Date: February 13, 2013Client: Labrensz Joshua M | Permit status: Completed | Permit id: 453341 | |||||
New construction permit Date: December 6, 2012Client: Labrensz Joshua M | Permit status: Completed | Permit id: 437145 | |||||
Suppression permit Date: February 12, 2013Client: Labrensz Joshua M | Permit status: Completed | Permit id: 451597 | |||||
Electrical permit Date: February 27, 2013Client: Labrensz Joshua M | Permit status: Completed | Permit id: 455861 | |||||
Electrical permit Date: February 27, 2013Client: Labrensz Joshua M | Permit status: Completed | Permit id: 455861 | |||||
Zoning use permit Date: September 20, 2012Client: Labrensz Joshua M | Permit status: Completed | Permit id: 424087 | |||||
Mechanical permit Date: February 13, 2013Client: Labrensz Joshua M | Permit status: Completed | Permit id: 453341 | |||||
New construction permit Date: December 6, 2012Client: Labrensz Joshua M | Permit status: Completed | Permit id: 437145 | |||||
Plumbing permit Date: February 25, 2013Client: Labrensz Joshua M | Permit status: Completed | Permit id: 455537 | |||||
Suppression permit Date: February 12, 2013Client: Labrensz Joshua M | Permit status: Completed | Permit id: 451597 | |||||
Erection of a three over two story attached structure with cellar, 2nd and 3rd floor front bay, roof deck over tow story rear portion and roof deck over three story portion for use as a sfd. Date: September 20, 2012Client: Labrensz Joshua M | Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 20, 2012 | Permit id: 424087 | |||||
SCORE 99 Install (1) hvac unit including ductwork (sfd) Date: February 13, 2013 Contractor: David MercadoClient: Labrensz Joshua M | Permit type: Mechanical permit | Permit status: Completed | Completion date: May 7, 2013 | Permit id: 453341 | |||||
SCORE 100 Wiring & installing outlets, 25 switches, light fixtures, 8 smokes, gfi outlets, 6 phone jacks, 6 tv jacks, a new 200amp service and hook up of all heating and a c units per 2008 nec (sfd) Date: February 27, 2013 Contractor: Harte ElectricsClient: Labrensz Joshua M | Permit type: Electrical permit | Permit status: Completed | Completion date: July 20, 2013 | Permit id: 455861 | |||||
SCORE 100 For the installation of a one (1) inch fire service with one (1) inch water meter for a single family dwelling; installation of fire supression sprinkler system in accordance with nfpa 13d. Date: February 12, 2013 Contractor: Elite Fire ProtectionClient: Labrensz Joshua M | Permit type: Suppression permit | Permit status: Completed | Completion date: May 7, 2013 | Permit id: 451597 | |||||
For the erection of a three story fully sprinkled attached single family dwelling with cellar, roof deck and roof deck access pilot house. Separate permits required for electric; plumbing; mechanical and fire suppression sprinkler system. Date: December 6, 2012Client: Labrensz Joshua M | Permit type: New construction permit | Permit status: Completed | Completion date: May 7, 2013 | Permit id: 437145 | |||||
SCORE 100 Installation of soil and waste pipes, hot and cold water lines to 3 wc, 3 lavs, 1 laundry tray, 1 ks, 1 tub, 1 shower (sfd) pa1 call#20130500365 Date: February 25, 2013 Contractor: Daine BarrettClient: Labrensz Joshua M | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 1, 2013 | Permit id: 455537 |