Suppression permit Date: August 22, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 417013 | |||||
Electrical permit Date: August 21, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 423273 | |||||
Plumbing permit Date: August 1, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 419797 | |||||
Zoning/use permit Date: May 7, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 402253 | |||||
New construction permit Date: May 23, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 405275 | |||||
Mechanical permit Date: July 25, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 418070 | |||||
Electrical permit Date: August 21, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 423273 | |||||
New construction permit Date: May 23, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 405275 | |||||
Plumbing permit Date: August 1, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 419797 | |||||
Zoning use permit Date: May 7, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 402253 | |||||
Mechanical permit Date: July 25, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 418070 | |||||
Suppression permit Date: August 22, 2012Client: Sanu Shoba George Sheela Shaji | Permit status: Completed | Permit id: 417013 | |||||
SCORE 79 Installation of fire suppression system in accordance with nfpa 13r and a new 1" connection. Date: August 22, 2012 Contractor: Liberty Fire Protection LlcClient: Sanu Shoba George Sheela Shaji | Permit type: Suppression permit | Permit status: Completed | Completion date: June 12, 2014 | Permit id: 417013 | |||||
SCORE 100 Install two 2-ton heat pump units (two-family dwelling) Date: July 25, 2012 Contractor: Bernard JoergerClient: Sanu Shoba George Sheela Shaji | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 2, 2014 | Permit id: 418070 | |||||
SCORE 100 Replace 5" lateral replace 5x4 curb trap and fresh air inlet install 1" water service Date: August 1, 2012 Contractor: Drain Masters Plumbing LlcClient: Sanu Shoba George Sheela Shaji | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 13, 2013 | Permit id: 419797 | |||||
SCORE 100 All new electric wiring and new 200amp service per 2008 nec (two family) Date: August 21, 2012 Contractor: A One Electric LlcClient: Sanu Shoba George Sheela Shaji | Permit type: Electrical permit | Permit status: Completed | Completion date: January 7, 2016 | Permit id: 423273 | |||||
Erection of a three story attached structure with cellar; 2nd & 3rd floor front bays for use as a duplex. Date: May 7, 2012Client: Sanu Shoba George Sheela Shaji | Permit type: Zoning/use permit | Permit status: Completed | Completion date: May 7, 2012 | Permit id: 402253 | |||||
New construction of a three story attached structure with cellar, 2nd and 3rd floor front bays for use as a duplex. Date: May 23, 2012Client: Sanu Shoba George Sheela Shaji | Permit type: New construction permit | Permit status: Completed | Completion date: August 24, 2012 | Permit id: 405275 | |||||
SCORE 100 Rough in sanitary waste to all fixtures rough in water supply to all fixtures;4wc,4 lavs;4 sh;2 kitchen;2 hwh;2 washing machine (sfd) Date: June 28, 2012 Contractor: Drain Masters Plumbing LlcClient: Sanu Shoba George Sheela Shaji | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 13, 2013 | Permit id: 413843 |