ACTIVITY
PERMITS VALUATION
Get several free quotes from best contractors in your area.
| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Permit for Date: January 12, 2017Client: Redden-Ricketts Linda Tr Flozell Love Living Trust | Applicant: Henry M. Clinton, Esq | Permit type: Appeal | Permit id: 29722 | |||||
SCORE 93 Install 200amp main service 2 gang meter, 100amp panel in units no common area, install 45 recessed outlets 25 switches 7 smoke and 2 carbon detectors, phone & cable lines as per nec 2008 (south district) Date: October 10, 2017 Contractor: Kieran HughesPermit type: Electrical permit | Permit status: Active | Completion date: October 10, 2017 | Permit id: 822708 | |||||
SCORE 79 Install (2) hvac systems with ductwork. (two-family) Date: September 25, 2017 Contractor: Jesse Fritz Airtight HeatingPermit type: Mechanical permit | Permit status: Active | Completion date: October 16, 2017 | Permit id: 818775 | |||||
SCORE 100 For the installation of a two (2) inch fire service line with backflow preventer and automatic fire suppression system as per nfpa 13r. All work shall be done in accordance with approved plans. Date: August 15, 2017 Contractor: Elite Fire ProtectionPermit type: Suppression permit | Permit status: Active | Completion date: October 31, 2017 | Permit id: 800898 | |||||
For the erection of a four (4) story structure with roof deck and roof deck access structure; for use as two family dwelling. Entire building to be sprinkler per nfpa 13r @ min. Foundation shall be designed in accordance with the geotechnical report. Underpinning shall be inspected continuously. Separate permit required for any mep and fire suppression work. Date: June 8, 2017Permit type: New construction permit | Permit status: Active | Completion date: November 8, 2017 | Permit id: 784119 | |||||
SCORE 100 For the complete demolition of an existing, attached, three (3) story structure. Structure to be demolished by hand and with hand held tools only. Pedestrian protection to be in place prior to start of work and to be maintained during all demolition activities. A covered walkway or sidewalk closure shall be required within 8 feet of building facade in accordance with section 3306 of the ibc. Separate building and or streets department permits are required. 21 day posting and notice required per a-303. 2 newly exposed walls to be treated. Date: April 28, 2017 Contractor: Gama Wrecking IncPermit type: Demolition permit | Permit status: Completed | Completion date: June 9, 2017 | Permit id: 776185 | |||||
SCORE 100 Remove house trap and seal lateral at curb line pa2017100697 (sfd)self certifications are no longer permitted","all excavations and plumbing trenches in excess of 5 ft in depth must have approved shoring in place at the time of inspection" Date: April 10, 2017 Contractor: Daine BarrettPermit type: Plumbing permit | Permit status: Completed | Completion date: November 8, 2017 | Permit id: 773928 | |||||
SCORE 89 1"water serv, lateral, fai, ct, hd, pa20172361138 self certification no longer accepted all trenches in excess of 5 ft must have approved shoring at the time of inspection. And 2-hwh, area drain, and 26-fixtures the installation will comply with the philadelphia plumbing code 2004 Date: August 30, 2017 Contractor: Pipeline Plumbing LlcPermit type: Plumbing permit | Permit status: Active | Completion date: October 31, 2017 | Permit id: 812550 | |||||
For complete demolition of (2) existing structures and for the construction of an attached (4) stone structure (38- h) to include a rear open deck at the 2nd floor level with vertical supports, a roof-top deck with enclosed stair access tower. Date: April 4, 2017Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 4, 2017 | Permit id: 771260 |