| Content | Date | Cost | Contractor Rank | Address | Contractor |
|---|---|---|---|---|---|
Electrical permit Date: April 21, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 604238 | |||||
Mechanical permit Date: June 18, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 618544 | |||||
Zoning/use permit Date: December 9, 2014Client: Pilgrim Community United | Permit status: Completed | Permit id: 578512 | |||||
Plumbing permit Date: April 30, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 606604 | |||||
Suppression permit Date: June 10, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 608621 | |||||
New construction permit Date: March 9, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 588664 | |||||
Electrical permit Date: April 21, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 604238 | |||||
New construction permit Date: March 9, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 588664 | |||||
Zoning use permit Date: December 9, 2014Client: Pilgrim Community United | Permit status: Completed | Permit id: 578512 | |||||
Plumbing permit Date: May 7, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 608520 | |||||
Mechanical permit Date: June 18, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 618544 | |||||
Suppression permit Date: June 10, 2015Client: Pilgrim Community United | Permit status: Completed | Permit id: 608621 | |||||
SCORE 100 Installation of a fire suppression sprinkler system 13d, 1" combined service for residential bldg Date: June 10, 2015 Contractor: Shannon Fire ProtectionPermit type: Suppression permit | Permit status: Completed | Completion date: February 27, 2016 | Permit id: 608621 | |||||
SCORE 89 Install 4 ton heat pump and all supply and return ductwork thru out in basement Date: June 18, 2015 Contractor: Gray Mechanical IncPermit type: Mechanical permit | Permit status: Completed | Completion date: February 27, 2016 | Permit id: 618544 | |||||
SCORE 100 Install yard drain, main drain & stack & 3-toilets, 2-tubs, 4-lavs, 1-shower, 1-kitchen sink & 1-washer (sfd) Date: May 7, 2015 Contractor: Excel Plumbing Heating Ac IncPermit type: Plumbing permit | Permit status: Completed | Completion date: December 1, 2015 | Permit id: 608520 | |||||
Erection of a new three story sfd with cellar and roof deck with roof access structure. Date: March 9, 2015Permit type: New construction permit | Permit status: Completed | Completion date: November 17, 2015 | Permit id: 588664 | |||||
SCORE 100 Complete wire & install 200amp service & ground as per nec 2008 (sfd) Date: April 21, 2015 Contractor: L Moore Electric IncPermit type: Electrical permit | Permit status: Completed | Completion date: November 14, 2015 | Permit id: 604238 | |||||
SCORE 100 Install 1" water service,5" lateral,curb trap,fai and main drain pa20151041438(sfd)self certifications are no longer permitted","all excavations and plumbing trenches in excess of 5 ft in depth must have approved shoring in place at the time of inspection" Date: April 30, 2015 Contractor: Tommys PlumbingPermit type: Plumbing permit | Permit status: Completed | Completion date: May 19, 2015 | Permit id: 606604 | |||||
For the erection of an attached structure (maximum height nte 38 feet)with a roof deck accessed by a pilot house for use as a single family dwelling.(per proviso plan approved by the zoning board on 10 22 14) Date: December 9, 2014Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 9, 2014 | Permit id: 578512 |