Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical permit Date: October 14, 2016 Client: Ii Omega Corporation | Permit status: Active | Permit id: 729358 | |||||
Zoning permit Date: February 2, 2016 Client: Ii Omega Corporation | Permit status: Completed | Permit id: 666195 | |||||
Plumbing permit Date: October 20, 2016 Client: Ii Omega Corporation | Permit status: Completed | Permit id: 730619 | |||||
Zoning use permit Date: January 17, 2017 Client: Ii Omega Corporation | Permit status: Completed | Permit id: 731323 | |||||
Demolition permit Date: January 17, 2017 Client: Ii Omega Corporation | Permit status: Active | Permit id: 731324 | |||||
Permit for the erection of an attached structure with a roof deck accessed by roof deck access structure. For use as multi-family household living (four (4) dwelling) with four (4) interior accessory off-street parking spaces, including one (1) ada (van accessible) parking space, accessed from the front street. All existing structure on lot to be completely demolished. Size and location s shown in the plans application. Date: December 21, 2016 Client: Ii Omega Corporation | Applicant: William Obrien | Permit type: Appeal | Permit id: 29478 | |||||
Relocation of lot line shared with 124 levering street. No construction or alteration Date: February 2, 2016 Client: Mega Corporation | Permit type: Zoning permit | Permit status: Completed | Completion date: February 2, 2016 | Permit id: 666195 | |||||
SCORE 84 Complete demolition of existing building by hand and mechanical equipment. All permitted demolition activity to be in accordance with approved site safety demolition plan & such plan to be maintained on site at all times. Special inspections shall be performed on a continuous basis until the structure is demolished to a height of ft. Full sidewalk closure required as reflected on approved site plan and in accordance with section 3306 of the ibc. Separate street closure permit required prior to start of work. Date: January 17, 2017 Contractor: Omega Corporation Client: Mega Corporation | Permit type: Demolition permit | Permit status: Completed | Completion date: July 28, 2017 | Permit id: 731324 | |||||
SCORE 100 Sealing 5"lateral-pa1#20162913059-seal 5" lateral at the curb line by removing the house trap and hermetically sealing the lateral by a cap or plug per section p-606. 1 of the philadelphia plumbing code 2004 - "self-certifications are no longer permitted" - "all excavations and plumbing trenches in excess of 5 feet in depth must have approved shoring in place at the time of inspection" Date: October 20, 2016 Contractor: Glenn H Wood Plumbing Llc Client: Mega Corporation | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 27, 2017 | Permit id: 730619 | |||||
For the complete demolition of an existing structure on lot; for the erection of an attached structure with a roof deck accessed by roof deck access structure. For use as multi-family household living (four (4) dwelling) with four (4) interior accessory off-street parking spaces, including one (1) ada (van accessible) parking space, accessed from the front street; size and location as shown in the plans application. Date: March 6, 2017 Client: Mega Corporation | Permit type: Zoning/use permit | Permit status: Completed | Completion date: March 6, 2017 | Permit id: 739142 | |||||
SCORE 84 Temporary 100amp service on pole for demolition only as per 2008 nec (north district) additional permit required for construction when building permit has been issued Date: October 14, 2016 Contractor: Omega Corporation Client: Mega Corporation | Permit type: Electrical permit | Permit status: Expired | Completion date: October 14, 2016 | Permit id: 729358 | |||||
SCORE 84 Demo building Date: January 17, 2017 Contractor: Omega Corporation Client: Mega Corporation | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 17, 2017 | Permit id: 731323 |