Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Lot 6 friendship corners, sfd w/scrn prch & deck Date: April 10, 2012 Value: $132,175 Client: D R Horton Inc | Client Address: 20 Aerial Center Parkway Suite 1 Cary Nc 27560 | Permit type: Single family new | Permit status: Certificate issued | Completion date: April 10, 2012 | Current use: Residential | Permit id: 12-00001407 | |||||
Footing excavation Date: October 28, 2011 Permit type: Building | Permit status: Approved | Permit id: 12-00001407 | |||||
Electrical temporary bd Date: November 1, 2011 Permit type: Electrical | Permit status: Approved | Permit id: 12-00001407 | |||||
Mechanical rough-in Date: December 21, 2011 Permit type: Mechanical | Permit status: Approved | Permit id: 12-00001407 | |||||
Plumbing rough-in Date: December 21, 2011 Permit type: Plumbing | Permit status: Disapproved with penalty | Permit id: 12-00001407 | |||||
Mech c. O. C. Per gs160a423 Date: February 15, 2012 Permit type: Mechanical | Permit status: Disapproved with penalty | Permit id: 12-00001407 | |||||
Deck framing Date: March 15, 2012 Permit type: Building | Permit status: Approved | Permit id: 12-00001407 | |||||
Site inspection Date: March 28, 2012 Permit type: Planning | Permit status: Approved | Permit id: 12-00001407 | |||||
Gas piping test Date: December 21, 2011 Permit type: Mechanical | Permit status: Approved | Permit id: 12-00001407 | |||||
Water service Date: December 29, 2011 Permit type: Plumbing | Permit status: Approved | Permit id: 12-00001407 | |||||
Sewer service Date: December 29, 2011 Permit type: Plumbing | Permit status: Approved | Permit id: 12-00001407 | |||||
Framing rough-in Date: January 12, 2012 Permit type: Building | Permit status: Disapproved with penalty | Permit id: 12-00001407 | |||||
Wall insulation Date: January 19, 2012 Permit type: Building | Permit status: Approved | Permit id: 12-00001407 | |||||
Gas piping test Date: February 27, 2012 Permit type: Mechanical | Permit status: Disapproved | Permit id: 12-00001407 | |||||
Bldg c. O. C. Per gs160a423 Date: March 28, 2012 Permit type: Building | Permit status: Disapproved | Permit id: 12-00001407 | |||||
Foundation inspection Permit type: Building | Permit status: Cancelled | Permit id: 12-00001407 | |||||
Foundation inspection Date: November 9, 2011 Permit type: Building | Permit status: Disapproved with penalty | Permit id: 12-00001407 | |||||
Open floor framing inspt. Date: December 1, 2011 Permit type: Building | Permit status: Approved | Permit id: 12-00001407 | |||||
Electrical rough-in Date: December 30, 2011 Permit type: Electrical | Permit status: Disapproved | Permit id: 12-00001407 | |||||
Electrical rough-in Date: January 5, 2012 Permit type: Electrical | Permit status: Approved | Permit id: 12-00001407 | |||||
Plbg c. O. C. Per gs160a423 Date: February 16, 2012 Permit type: Plumbing | Permit status: Approved | Permit id: 12-00001407 | |||||
Engineering Date: March 28, 2012 Permit type: Water reso | Permit status: Approved | Permit id: 12-00001407 | |||||
Res. Erosion sign off Date: October 25, 2011 Permit type: Water reso | Permit status: Approved | Permit id: 12-00001407 | |||||
Exterior/moist/protect/barrier Date: December 21, 2011 Permit type: Building | Permit status: Approved | Permit id: 12-00001407 | |||||
Deck footing Date: January 9, 2012 Permit type: Building | Permit status: Approved | Permit id: 12-00001407 | |||||
Framing rough-in Permit type: Building | Permit status: Cancelled | Permit id: 12-00001407 | |||||
Garage slab Date: November 18, 2011 Permit type: Building | Permit status: Approved | Permit id: 12-00001407 | |||||
Fireplace inspection Date: December 21, 2011 Permit type: Mechanical | Permit status: Approved | Permit id: 12-00001407 | |||||
Footing excavation Date: January 9, 2012 Permit type: Building | Permit status: Approved | Permit id: 12-00001407 | |||||
Elec c. O. C. Per gs160a423 Date: February 15, 2012 Permit type: Electrical | Permit status: Approved | Permit id: 12-00001407 | |||||
Foundation inspection Permit type: Building | Permit status: Cancelled | Permit id: 12-00001407 | |||||
SCORE 95 Single family new Client: D R Horton Inc | Client Address: 20 Aerial Center Parkway Suite 1 Cary Nc 27560 | Permit status: Certificate issued | Completion date: April 10, 2012 | Current use: Residential | Permit id: 12-00001407 | |||||
Framing rough-in Permit type: Building | Permit status: Cancelled | Permit id: 12-00001407 | |||||
Building Date: December 21, 2011 Permit status: Approved | Permit id: 12-00001407 | |||||
SCORE 99 New sngl fam detached Contractor: Yellow Dot Heating And Air Cond Permit id: 12-00001407 | |||||
SCORE 93 New sngl fam detached Contractor: Carnells Plumbing Permit id: 12-00001407 | |||||
SCORE 95 New sngl fam detached Contractor: D R Horton Inc Permit id: 12-00001407 | |||||
SCORE 100 New sngl fam detached Contractor: Imperial Electric Permit id: 12-00001407 | |||||
SCORE 100 Single family new Client: D R Horton Inc | Client Address: 20 Aerial Center Parkway Suite 1 Cary Nc 27560 | Permit status: Certificate issued | Completion date: April 10, 2012 | Current use: Residential | Permit id: 12-00001407 | |||||
Framing rough-in Permit type: Building | Permit status: Cancelled | Permit id: 12-00001407 | |||||
Foundation inspection Permit type: Building | Permit status: Cancelled | Permit id: 12-00001407 | |||||
SCORE 100 New sngl fam detached Contractor: D R Horton, Inc Permit id: 12-00001407 | |||||
Infrastructure Date: March 28, 2012 Permit type: Water resources | Permit status: Approved | Permit id: 12-00001407 | |||||
Foundation inspection Permit type: Building | Permit status: Cancelled | Permit id: 12-00001407 | |||||
Framing rough-in Permit type: Building | Permit status: Cancelled | Permit id: 12-00001407 |