Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning permit Date: March 21, 2016 Client: Sd Development Llc | Permit status: Completed | Permit id: 677146 | |||||
Plumbing permit Date: May 27, 2016 Client: Sd Development Llc | Permit status: Active | Permit id: 695720 | |||||
Plumbing permit Date: June 19, 2015 Client: Zion Land Lp | Permit status: Completed | Permit id: 619067 | |||||
Demolition permit Date: July 15, 2016 Client: Sd Development Llc | Permit status: Active | Permit id: 695773 | |||||
New construction permit Date: August 26, 2014 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 553829 | |||||
Mechanical permit Date: August 26, 2015 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 634754 | |||||
Suppression permit Date: July 3, 2015 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 621885 | |||||
Electrical permit Date: August 3, 2015 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 629178 | |||||
Zoning/use permit Date: July 22, 2014 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 549537 | |||||
Zoning permit Date: September 5, 2012 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 422808 | |||||
Zoning permit Date: June 30, 2014 Client: Zion Land Lp | Permit status: Completed | Permit id: 545646 | |||||
Zoning/use permit Date: February 20, 2013 Client: Zion Land Lp | Permit status: Completed | Permit id: 450268 | |||||
Demolition permit Date: May 12, 2014 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 535797 | |||||
Permit for the lot adjustment to create five(5) lots ( lot# 1, lot# 2, lot# 3, lot# 4 and lot# 5) from six(6) opa accounts ( 11 e hewson st, 1122 e hewson st, 1124 e hewson st, 1126 e hewson st and 1128 e hewson st and 11 e hewson st) as follows: for the erection of an attached structure ( nte 38 high); bay windows from second (2nd) through third ( 3rd ) floors; deck at 2nd floor rear; pilot house access to roof deck above the third floor and for the creation of one(1) accessory parking space for one(1) car ( access from front street) for a single family household living on each lot. Size and location as shown in the application. Date: April 16, 2015 Client: Gap Group Llc | Applicant: Joseph Beller, Esq. | Permit type: Appeal | Permit status: Granted | Completion date: July 7, 2015 | Permit id: 24998 | |||||
Permit for relocation of lot lines to create twelve lots from eleven lots, for the erection of twelve (12) three story attached structures (maximum height nte 35 feet) with cellar, with a roof deck above accessed by a pilot house, each for use as a single family dwelling, lots 1 thru 11 with interior parking for one automobile each. Date: June 7, 2012 Client: Zion Land Lp | Applicant: Ronald Patterson, Esq | Permit type: Appeal | Permit status: Granted/prov | Permit id: 18172 | |||||
New construction permit Date: August 26, 2014 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 553829 | |||||
Zoning permit Date: September 5, 2012 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 422808 | |||||
Zoning use permit Date: July 22, 2014 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 549537 | |||||
Demolition permit Date: May 12, 2014 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 535797 | |||||
Plumbing permit Date: August 6, 2015 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 630311 | |||||
Zoning permit Date: March 21, 2016 Client: Sd Development Llc | Permit status: Completed | Permit id: 677146 | |||||
Zoning permit Date: June 30, 2014 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 545650 | |||||
Electrical permit Date: August 3, 2015 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 629178 | |||||
Zoning use permit Date: February 20, 2013 Client: Mccann Brian | Permit status: Completed | Permit id: 450268 | |||||
Suppression permit Date: July 3, 2015 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 621885 | |||||
Zoning use permit Date: December 5, 2016 Client: Sd Development Llc | Permit status: Completed | Permit id: 740572 | |||||
Demolition permit Date: July 15, 2016 Client: Sd Development Llc | Permit status: Completed | Permit id: 695773 | |||||
Mechanical permit Date: August 26, 2015 Client: Brinton Joanna Galego Brad | Permit status: Completed | Permit id: 634754 | |||||
Plumbing permit Date: May 27, 2016 Client: Sd Development Llc | Permit status: Active | Permit id: 695720 | |||||
Permit for the lot adjustment to create five(5) lots ( lot# 1, lot# 2, lot# 3, lot# 4 and lot# 5) from six(6) opa accounts ( 11 e hewson st, 1122 e hewson st, 1124 e hewson st, 1126 e hewson st and 1128 e hewson st and 11 e hewson st) as follows: for the erection of an attached structure ( nte 38 high); bay windows from second (2nd) through third ( 3rd ) floors; deck at 2nd floor rear; pilot house access to roof deck above the third floor and for the creation of one(1) accessory parking space for one(1) car ( access from front street) for a single family household living on each lot. Size and location as shown in the application. Date: April 16, 2015 Client: Gap Group Llc | Applicant: Joseph Beller, Esq. | Permit type: Appeal | Permit status: Granted | Completion date: July 7, 2015 | Permit id: 24998 | |||||
Permit for relocation of lot lines to create twelve lots from eleven lots, for the erection of twelve (12) three story attached structures (maximum height nte 35 feet) with cellar, with a roof deck above accessed by a pilot house, each for use as a single family dwelling, lots 1 thru 11 with interior parking for one automobile each. Date: June 7, 2012 Client: Mccann Brian | Applicant: Ronald Patterson, Esq | Permit type: Appeal | Permit status: Granted/prov | Permit id: 18172 | |||||
SCORE 100 Sealing 5"sewer lateral-pa1#20161481025-"self-certifications are no longer permitted" - "all excavations and plumbing trenches in excess of 5 feet in depth must have approved shoring in place at the time of inspection" Date: May 27, 2016 Contractor: Tommys Plumbing Client: Gap Group Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 6, 2017 | Permit id: 695720 | |||||
For the lot adjustment to create five(5) lots ( lot# 1, lot# 2, lot# 3, lot# 4 and lot# 5) from six(6) opa accounts ( 11 e hewson st, 1122 e hewson st, 1124 e hewson st, 1126 e hewson st and 1128 e hewson st and 11 e hewson st) . Size and location as shown in the application. Date: March 21, 2016 Client: Gap Group Llc | Permit type: Zoning permit | Permit status: Completed | Completion date: March 21, 2016 | Permit id: 593283 | |||||
Construction of a three story attached structure, with cellar, roof deck, and access pilot house (stairs and landing only). All work shall conform to the plans approved under permit ap# 742470. Date: February 9, 2017 Client: Gap Group Llc | Permit type: New construction permit | Permit status: Active | Completion date: October 13, 2017 | Permit id: 753367 | |||||
SCORE 100 For the installation of a one (1) inch fire service line and an automatic fire suppression system as per nfpa 13d. All work shall be done in accordance with approved plans hydraulic calculations. For plans and hydraulic calculation refer to ap# 805220 Date: October 19, 2017 Contractor: B. M. Consulting Services Inc Client: Gap Group Llc | Permit type: Suppression permit | Permit status: Active | Completion date: November 9, 2017 | Permit id: 824998 | |||||
For the complete demolition of one attached two story structure for use as a single-family dwelling. All permitted demolition activity to be in accordance with approved site safety demolition plan & such plan to be maintained on site at all times in accordance with code bulletin b-1302r. Alleyway protection and full sidewalk closure required as reflected on engineers statement details, approved site plan and in accordance with section 3306 of the ibc (safety zone is 12. 5 feet). Separate street sidewalk closure permit to be obtained from streets deparement prior to the start of any work. Separate permits required for all other work. Any deviation will require an amended building permit. Date: July 15, 2016 Client: Gap Group Llc | Permit type: Demolition permit | Permit status: Completed | Completion date: November 14, 2016 | Permit id: 695773 | |||||
SCORE 100 Trap, fai, lateral, rfss & ws - pa1# 2015-2011635"self-certifications are no longer permitted" - "all excavations and plumbing trenches in excess of 5 feet in depth must have approved shoring in place at the time of inspection" Date: August 6, 2015 Contractor: Glenn H Wood Plumbing Llc Client: Brinton Joanna Galego Brad | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 28, 2015 | Permit id: 630311 | |||||
SCORE 100 For the installation of an automatic sprinkler system w. One (1) inch combined domestic & fire service line to serve previously approved three (3) story above grade plane, w. Basement & rooftop structure, residential building. Automatic sprinkler system installation in accordance with nfpa 13d. Date: July 3, 2015 Contractor: B. M. Consulting Services Inc Client: Mccann Brian | Permit type: Suppression permit | Permit status: Completed | Completion date: April 12, 2016 | Permit id: 618873 | |||||
Permit for foundation work only. All other work requires additional permits. No stairs or egress well permitted until streets department approval for a building permit is obtained. Call the inspector prior to starting work. Date: August 26, 2014 Client: Mccann Brian | Permit type: New construction permit | Permit status: Completed | Completion date: December 2, 2015 | Permit id: 544161 | |||||
For the lot adjustment to create thirteen lots (lot 1-13) and one (1) shared driveway easement from eight (8) existing opa accounts (1101-03 e berks, 1105-09 e berks st, 1111-15 e berks st, 11 e hewson st. 1102 e hewson st, 1104 e hewson st, 1106-08 e hewson st & 11 e hewson st) and twelve (12) deeded lots (1101-03 e berks st, 1105 e berks, 1107 e berks, 1109 e berks, 1111 e berks, 1113 e berks, 1115 e berks, 11 e hewson st, 1102 e hewson st, 1104 e hewson st, 1106-08 e hewson st, 11 e hewson st). Size and location as shown on plans application. Date: June 30, 2014 Client: Mccann Brian | Permit type: Zoning permit | Permit status: Completed | Completion date: June 30, 2014 | Permit id: 545646 | |||||
Permit for foundation work only. All other work requires additional permits. No stairs or egress well permitted until streets department approval for a building permit is obtained. See a p # 544161 for the approved plans. Call the inspector prior to starting work. Date: August 26, 2014 Client: Brinton Joanna Galego Brad | Permit type: New construction permit | Permit status: Completed | Completion date: December 2, 2015 | Permit id: 553829 | |||||
SCORE 100 For the installation of an automatic sprinkler system w. One (1) inch combined domestic & fire service line to serve previously approved three (3) story above grade plane, w. Basement & rooftop structure, residential building. Automatic sprinkler system installation in accordance with nfpa 13d. See fire suppression permit# 618873 for approved construction documents. Date: July 3, 2015 Contractor: B. M. Consulting Services Inc Client: Brinton Joanna Galego Brad | Permit type: Suppression permit | Permit status: Completed | Completion date: January 6, 2016 | Permit id: 621885 | |||||
SCORE 100 Install a 200amp service,38 lights,25 switches, outlets,5 gfi outlets,7 arc fault breakers and 6 smoke alarms as per 2008 nec (east district) Date: August 3, 2015 Contractor: Karalis Electric Co Inc Client: Mccann Brian | Permit type: Electrical permit | Permit status: Completed | Completion date: March 30, 2016 | Permit id: 629063 | |||||
SCORE 89 Install 1 hvac unit with ductwork(sfd) Date: August 26, 2015 Contractor: Alkaun Co Client: Mccann Brian | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 12, 2016 | Permit id: 634749 | |||||
For the erection of an attached structure ( nte 38 high); bay windows from second ( 2nd ) through third ( 3rd ) floors; deck at 2nd floor rear; pilot house access to roof deck above the third floor for a single family household living with one(1) accessory parking space for one(1) car ( access from front street)size and location as shown in the application. Date: December 5, 2016 Client: Gap Group Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 5, 2016 | Permit id: 740572 | |||||
SCORE 100 Trap, fai, lateral & ws - pa1# 2015-2011635"self-certifications are no longer permitted" - "all excavations and plumbing trenches in excess of 5 feet in depth must have approved shoring in place at the time of inspection" Date: July 29, 2015 Contractor: Glenn H Wood Plumbing Llc Client: Mccann Brian | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 19, 2015 | Permit id: 628152 | |||||
For the erection of an attached structure, with a roof deck accessed by a pilot house; size and location as shown on plans application. For use as single family household living, to include one (1) accessory, surface parking space accessed by the rear shared driveway. See a p no 527268 Date: July 22, 2014 Client: Mccann Brian | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 22, 2014 | Permit id: 549532 | |||||
New construction of a (3) story wood framed sfd, with full cellar and upper level roof deck from pilot house. See ap 561633 for approved plans Date: October 22, 2014 Client: Brinton Joanna Galego Brad | Permit type: New construction permit | Permit status: Completed | Completion date: December 31, 2015 | Permit id: 567141 | |||||
SCORE 100 3-water closet, 3-lav, 2-tub shower, 1-kit sink & 1-washing machine the installation will comply with the philadelphia plumbing code 2004 Date: June 19, 2015 Contractor: Glenn H Wood Plumbing Llc Client: Brinton Joanna Galego Brad | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 30, 2015 | Permit id: 619083 | |||||
SCORE 100 For the complete demolition of an existing one (1) story structure. Size and location as shown on application plan. For use as a vacant lot. See ap 450272 for new construction permit Date: March 31, 2014 Contractor: Gama Wrecking Inc Client: Brinton Joanna Galego Brad | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 7, 2015 | Permit id: 527018 | |||||
SCORE 100 For complete demolition of site to remove exist. One (1) story masonry building. All permitted demolition activity to be in accordance with approved site safety demolition plan & such plan to be maintained on site at all times. Asbestos abatement to be completed prior to commencement of permitted work. Permitted demolition work to commence no earlier than 21 days past the date of permit issuance. Contractor to maintain an active street closure permit on site, if street closure permit expires, a new street closure permit is required prior to commencement of work see ap # 491379 for approved plans. Date: May 12, 2014 Contractor: Gama Wrecking Inc Client: Brinton Joanna Galego Brad | Permit type: Demolition permit | Permit status: Completed | Completion date: July 8, 2014 | Permit id: 535797 | |||||
For the relocation of lot lines to be (12) lots for the construction of (11) single family attached structures all three story with rooftop decks, full cellars and (1) car interior garage(off street parking) Date: September 5, 2012 Client: Mccann Brian | Permit type: Zoning permit | Permit status: Completed | Completion date: September 5, 2012 | Permit id: 405619 | |||||
For the erection of a three(3) story attached structure (maximum height nte 35 feet) with cellar, with a roof deck above acessed by a pilot house, for use as a single family dwelling with interior parking for one automobile. Date: February 20, 2013 Client: Mccann Brian | Permit type: Zoning/use permit | Permit status: Completed | Completion date: February 20, 2013 | Permit id: 450268 | |||||
SCORE 100 Install 5" curb trap 4" fai 4" main drain 1" water line pa20171101476 self certification no longer accepted all trenches in excess of 5 ft must have approved shoring at the time of inspection. Date: December 6, 2017 Contractor: Tommys Plumbing Client: Gap Group Llc | Permit type: Plumbing permit | Permit status: Active | Completion date: December 6, 2017 | Permit id: 837287 |