SCORE 100 Install solar panels Date: August 13, 2015 Contractor: R. C. Hunt Electric IncPermit type: Solarpv | Permit status: Pass | Completion date: August 13, 2015 | Current use: Commercial | Permit id: Bld2015-06453 | |||||
SCORE 100 Install solar panels Date: August 13, 2015 Contractor: R. C. Hunt Electric IncPermit type: Solarpv | Permit status: Completed | Completion date: August 13, 2015 | Current use: Commercial | Permit id: Bld2015-06452 | |||||
SCORE 70 This is an expansion of the existing private car wash that serves the mark miller toyota dealership. It will be a metal building addition and new car wash equipment with sound dampening abilities. Date: May 4, 2015 Contractor: Ffkr ArchitectsPermit type: Accessory building | Permit status: Pass | Completion date: August 10, 2015 | Current use: Commercial | Permit id: Bld2015-03075 | |||||
SCORE 99 Tear off existing trocal roofing membrane, recover mil 327 feltback. No changes to sheathing or insulation. D-2 zone, not historic. A. S. Date: April 9, 2010 Contractor: Clarks Quality Roofing IncPermit type: Roofing | Permit status: In progress | Completion date: April 9, 2010 | Current use: Commercial | Permit id: Bld2010-02207 | |||||
SCORE 56 Car wash as an accessory use in the d-2 zone Date: January 20, 2015 Contractor: Ffkr Architectsmark Miller Car WashPermit type: Appeal application | Permit status: Complete | Completion date: February 9, 2015 | Current use: Appeal admin decision | Permit id: Plnapp2015-0003 | |||||
Zoning administration Date: December 29, 2014Permit status: Final draft | Completion date: January 28, 2015 | Current use: Administrative interpretation | Permit id: Plnzad2014-0090 | |||||
Install solar panels Date: August 13, 2015Permit type: Solarpv | Permit status: Pass | Completion date: August 13, 2015 | Current use: Commercial | Permit id: Bld2015-06453 | |||||
Install solar panels Date: August 13, 2015Permit type: Solarpv | Permit status: Accepted - standard | Completion date: August 13, 2015 | Current use: Commercial | Permit id: Bld2015-06452 | |||||
SCORE 64 This is an expansion of the existing private car wash that serves the mark miller toyota dealership. It will be a metal building addition and new car wash equipment with sound dampening abilities. Date: May 4, 2015Permit type: Accessory building | Permit status: Inspections | Completion date: September 3, 2015 | Current use: Commercial | Permit id: Bld2015-03075 | |||||
SCORE 64 To remove and dispose if the single ply membrane and clad metal; to install new mil s327 pvc fastened at 12 inch on center; to install new membrane coasted edge metal Date: October 14, 2013Permit type: Roofing | Permit status: Closed | Completion date: November 18, 2013 | Current use: Commercial | Permit id: Bld2013-07528 | |||||
SCORE 64 Install new sprinkler system in sod areas & planters. Thbere are 2 poc & 2 back flows and 14 1" valves. Spray heads -lawn. Drip in planter areas. Date: November 7, 2011 Contractor: Sage Valley Landscaping Incmark Miller ToyotaPermit type: Plumbing | Permit status: Closed | Completion date: July 23, 2012 | Current use: Commercial | Permit id: Bld2011-07254 | |||||
SCORE 64 Install new parking lot lights Date: October 21, 2011 Contractor: Robbins Central Electricmark Miller ToyotaPermit type: Electrical | Permit status: Closed | Completion date: December 20, 2011 | Current use: Commercial | Permit id: Bld2011-06864 | |||||
SCORE 64 New parking lot/parking lot reconstruction d. D. D-2 zone, vehicle sales lots per plnpcm2010-00610, per all notes on plans, dept. Reviews & approvals attached a. S. Date: October 14, 2011 Contractor: Morgan Asphalt Incmark Miller ToyotaPermit type: Parking lot | Permit status: Closed | Completion date: March 5, 2013 | Current use: Commercial | Permit id: Bld2011-06655 | |||||
SCORE 79 1 monument sign: 48 sqft 1 pole sign: sqft a. H. Bldg: k. A. Date: December 16, 2010 Contractor: Young Electric Sign Companymark Miller ToyotaPermit type: Sign | Permit status: Closed | Completion date: March 4, 2011 | Permit id: Bld2010-08682 | |||||
SCORE 79 Flat (bldg): 504 sqft flat (bldg): 223 sqft a. H. Date: October 20, 2010 Contractor: Young Electric Sign Companymark Miller ToyotaPermit type: Sign | Permit status: Completed | Completion date: March 10, 2011 | Permit id: Bld2010-07231 | |||||
SCORE 79 Flat (bldg): 225 sqft flat (bldg): 159 sqft flat (bldg): 2 sqft a. H. Date: October 20, 2010 Contractor: Young Electric Sign Companymark Miller ToyotaPermit type: Sign | Permit status: Closed | Completion date: March 4, 2011 | Permit id: Bld2010-07232 | |||||
SCORE 64 Replace several light, add receptacles, wire hoists. Add parking lot lights. Date: September 15, 2010 Contractor: Able Electric Co.Toyota Saturn Of Salt LakePermit type: Electrical | Permit status: Closed | Completion date: January 11, 2013 | Current use: Commercial | Permit id: Bld2010-06350 | |||||
SCORE 64 Tear off existing trocal roofing membrane, recover mil 327 feltback. No changes to sheathing or insulation. D-2 zone, not historic. A. S. Date: April 9, 2010Permit type: Roofing | Permit status: In progress | Completion date: April 9, 2010 | Current use: Commercial | Permit id: Bld2010-02207 | |||||
Converting an existing building to a carwash per petition #410-08-48; actual location of structure is off of 2 west Date: September 3, 2008Permit type: Permit | Permit status: Completed | Completion date: March 10, 2009 | Current use: Commercial | Permit id: Bld2008-01552 | |||||
SCORE 65 Exterior panel faade. Existing sign to be removed. Sign permit will be required. Date: June 16, 2016 Contractor: Steve SextonPermit status: Closed | Current use: Commercial | Permit id: Bld2016-03406 | |||||
SCORE 56 Converting an existing building to a carwash per petition #410-08-48; actual location of structure is off of 2 west Date: September 3, 2008 Contractor: Sahara Inc.Mark Miller CarwashPermit status: Closed | Completion date: March 10, 2009 | Current use: Commercial | Permit id: Bld2008-01552 | |||||
SCORE 59 Install solar panels Date: August 13, 2015 Contractor: R. C. Hunt Electric Inc.SolarPermit type: Solarpv | Permit status: Inspections | Completion date: August 13, 2015 | Current use: Commercial | Permit id: Bld2015-06453 | |||||
SCORE 96 Water heater replacement Date: August 13, 2015 Contractor: Hansen Hvac ServicesPermit type: Plumbing | Permit status: Completed | Completion date: August 13, 2015 | Current use: Residential | Permit id: Bld2015-06459 | |||||
SCORE 80 28. 67kw roof mounted non penetrating solar array Date: July 20, 2015 Contractor: Big Dog SolarPermit type: Solarpv | Permit status: Completed | Completion date: August 19, 2015 | Current use: Commercial | Permit id: Bld2015-05513 | |||||
SCORE 64 28. 67kw roof mounted non penetrating solar array Date: July 20, 2015 Contractor: Big Dog Solargarff Slc NissanPermit type: Solarpv | Permit status: Closed | Completion date: September 4, 2015 | Current use: Commercial | Permit id: Bld2015-05513 | |||||
SCORE 64 Install electric car charging station Date: December 11, 2013 Contractor: Capital Electriccar ChargerPermit type: Electrical | Permit status: Closed | Completion date: December 26, 2013 | Current use: Commercial | Permit id: Bld2013-09105 | |||||
Remodel Date: January 10, 2011Permit type: Electrical | Permit status: Pass | Completion date: July 11, 2011 | Current use: Commercial | Permit id: Bld2011-00187 | |||||
SCORE 56 Remodel Date: January 10, 2011 Contractor: Jordan Valley Electric Inc.Ken Garff HyundaiPermit type: Electrical | Permit status: Closed | Completion date: July 11, 2011 | Current use: Commercial | Permit id: Bld2011-00187 | |||||
SCORE 91 Remodel of existing building. Includes adding new hvac for entire building. Date: April 30, 2015 Contractor: Air Systems IncorporatedPermit type: Mechanical | Permit status: Reviews not require | Completion date: April 30, 2015 | Current use: Commercial | Permit id: Bld2015-02986 | |||||
SCORE 96 Fire detection alarm system. Date: March 19, 2015 Contractor: System Service Specialist IncPermit type: Fire | Permit status: Applicant communication | Completion date: September 2, 2015 | Current use: Commercial | Permit id: Bld2015-01797 | |||||
SCORE 72 We are performing plumbing work on a building remodel project with pentalon construction. We are subcontracted by pentalon construction who is the project general contractor. The plans were developed by ensign utah and were approved by salt lake city on 12 01 2014. Date: March 5, 2015 Contractor: Archer Mechanical IncPermit type: Plumbing | Permit status: Accepted | Completion date: March 5, 2015 | Current use: Commercial | Permit id: Bld2015-01459 | |||||
SCORE 100 Remodel existing sprinkler system on lower levels. Furnish and install new sprinkler system on upper levels. Date: March 2, 2015 Contractor: Delta Fire Systems IncPermit type: Fire | Permit status: Completed | Completion date: April 1, 2015 | Current use: Commercial | Permit id: Bld2015-01277 | |||||
SCORE 100 Conversion of the old mark miller car sales and repair building into a new professional office building. This is not a school, they develop training materials to school districts to help increase and standardize teaching methods. Date: June 3, 2014 Contractor: Pentalon Construction IncPermit type: Permit | Permit status: Completed | Completion date: December 16, 2014 | Current use: Commercial | Permit id: Bld2014-03840 | |||||
SCORE 64 Remodel of existing building. Includes adding new hvac for entire building. Date: April 30, 2015Permit type: Mechanical | Permit status: Inspections | Completion date: April 30, 2015 | Current use: Commercial | Permit id: Bld2015-02986 | |||||
Fire detection/alarm system. Date: March 19, 2015Permit type: Fire | Permit status: Applicant communication | Completion date: September 2, 2015 | Current use: Commercial | Permit id: Bld2015-01797 | |||||
SCORE 64 We are performing plumbing work on a building remodel project with pentalon construction. We are subcontracted by pentalon construction who is the project general contractor. The plans were developed by ensign utah and were approved by salt lake city on 12/01/2014. Date: March 5, 2015 Contractor: Archer Mechanical Inc.School Improvement NetworkPermit type: Plumbing | Permit status: Inspections | Completion date: March 5, 2015 | Current use: Commercial | Permit id: Bld2015-01459 | |||||
Remodel existing sprinkler system on lower levels. Furnish and install new sprinkler system on upper levels. Date: March 2, 2015Permit type: Fire | Permit status: Completed | Completion date: April 1, 2015 | Current use: Commercial | Permit id: Bld2015-01277 | |||||
SCORE 64 Conversion of the old mark miller car sales and repair building into a new professional office building. This is not a school, they develop training materials to school districts to help increase and standardize teaching methods. Date: June 3, 2014Permit type: Permit | Permit status: Inspections | Completion date: December 16, 2014 | Current use: Commercial | Permit id: Bld2014-03840 | |||||
SCORE 61 Conversion of the old mark miller car sales and repair building into a new professional office building. This is not a school, they develop training materials to school districts to help increase and standardize teaching methods. Date: March 8, 2016 Contractor: School Improvement Networktroy BrinkerhoffPermit status: Closed | Current use: Commercial | Permit id: Bld2014-03840 | |||||
Conversion of the old mark miller car sales and repair building into a new professional office building. This is not a school, they develop training materials to school districts to help increase and standardize teaching methods. Date: March 8, 2016Permit status: Closed | Current use: Commercial | Permit id: Bld2014-03840 | |||||
Remodel existing sprinkler system on lower levels. Furnish and install new sprinkler system on upper levels. Date: March 2, 2015Permit type: Fire | Permit status: Inspections | Completion date: April 1, 2015 | Current use: Commercial | Permit id: Bld2015-01277 | |||||
SCORE 59 Fire detection/alarm system. Date: March 19, 2015Permit type: Fire | Permit status: In for review | Completion date: September 2, 2015 | Current use: Commercial | Permit id: Bld2015-01797 | |||||
SCORE 100 Fire sprinkler Date: February 27, 2015 Contractor: Interstate Fire Sales And Service LlcPermit type: Fire | Permit status: Accepted - standard | Completion date: February 27, 2015 | Current use: Commercial | Permit id: Bld2015-01318 | |||||
SCORE 100 Replacing & adding roof drains Date: January 8, 2015 Contractor: Told PlumbingPermit type: Plumbing | Permit status: Reviews not require | Completion date: January 8, 2015 | Current use: Commercial | Permit id: Bld2015-00123 | |||||
SCORE 69 1-ductwork, 10-air handlers, 2-rtus Date: December 2, 2014 Contractor: Zion Plumbing IncPermit type: Mechanical | Permit status: On-line ready | Completion date: December 2, 2014 | Current use: Commercial | Permit id: Bld2014-08847 | |||||
SCORE 69 36-fixtures Date: December 2, 2014 Contractor: Zion Plumbing IncPermit type: Plumbing | Permit status: Reviews not require | Completion date: December 2, 2014 | Current use: Commercial | Permit id: Bld2014-08845 | |||||
SCORE 100 Fire alarm elevator recall. Date: November 3, 2014 Contractor: Interstate Fire Sales And Service LlcPermit type: Low voltage | Permit status: Completed | Completion date: November 6, 2014 | Current use: Commercial | Permit id: Bld2014-08052 | |||||
SCORE 100 Fire alarm and related alarm work authorized through seperate permit. Replace existing disconnects feeding (2) elevators and install new shunt trip style disconnects tied into fire alarm system. Date: October 14, 2014 Contractor: Capital Electric IncPermit type: Electrical | Permit status: Applicant info required | Completion date: October 14, 2014 | Current use: Commercial | Permit id: Bld2014-07469 | |||||
SCORE 66 Interior finish remodel of existing hotel lobby. Addition of new decorative stair and guest rooms. Date: October 8, 2014 Contractor: Joe Burgess Construction IncPermit type: Permit | Permit status: Pass | Completion date: November 20, 2014 | Current use: Commercial | Permit id: Bld2014-07314 | |||||
SCORE 100 Building is to be updated with a new exterior skin of e. F. I. S. And stucco. New guardrails installed at the balconies and the two stair towers. A new porte cochere will added to the front of the building Date: July 22, 2014 Contractor: Pentalon Construction IncPermit type: Permit | Permit status: Completed | Completion date: October 15, 2014 | Current use: Commercial | Permit id: Bld2014-05244 | |||||
SCORE 100 We would like to phase the project. The first phase is to remove old architectural features and eliminate two door, and the exterior elevator system. The exterior balcony guardrails are broken and not excepted by the parent company. Date: July 17, 2014 Contractor: Pentalon Construction IncPermit type: Permit | Permit status: Completed | Completion date: August 25, 2014 | Current use: Commercial | Permit id: Bld2014-05091 | |||||
Spliting the parcel to have the hotel building separate from the parking structure. Date: March 6, 2015Permit type: Subdivision and condominium | Permit status: Complete | Completion date: May 27, 2015 | Current use: Preliminary subdiv | Permit id: Plnsub2015-0015 | |||||
SCORE 64 Fire sprinkler Date: February 27, 2015 Contractor: Interstate Fire Sales And Service Llcholiday InnPermit type: Fire | Permit status: Accepted - standard | Completion date: February 27, 2015 | Current use: Commercial | Permit id: Bld2015-01318 | |||||
SCORE 64 Replacing & adding roof drains Date: January 8, 2015 Contractor: Told Plumbingshilo InnPermit type: Plumbing | Permit status: Inspections | Completion date: January 8, 2015 | Current use: Commercial | Permit id: Bld2015-00123 | |||||
SCORE 64 Remodel exterior Date: December 18, 2014 Contractor: Marathon Electric Llcshilo InnPermit type: Electrical | Permit status: Closed | Completion date: June 5, 2015 | Current use: Commercial | Permit id: Bld2014-09289 | |||||
Commercial electrical remodel Date: December 2, 2014Permit type: Electrical | Permit status: Pass | Completion date: June 5, 2015 | Current use: Commercial | Permit id: Bld2014-08848 | |||||
SCORE 74 1-ductwork, 10-air handlers, 2-rtus Date: December 2, 2014 Contractor: Zion Plumbing Incholiday Inn Express LobbyPermit type: Mechanical | Permit status: On-line ready | Completion date: December 2, 2014 | Current use: Commercial | Permit id: Bld2014-08847 | |||||
SCORE 74 36-fixtures Date: December 2, 2014 Contractor: Zion Plumbing Incholiday Inn Express LobbyPermit type: Plumbing | Permit status: Reviews not require | Completion date: December 2, 2014 | Current use: Commercial | Permit id: Bld2014-08845 | |||||
SCORE 64 2 wall signs & 1 pole sign Date: November 17, 2014 Contractor: Yesco Llcholiday Inn ExpressPermit type: Sign | Permit status: Closed | Completion date: February 5, 2015 | Permit id: Bld2014-08465 | |||||
SCORE 64 Fire alarm elevator recall. Date: November 3, 2014 Contractor: Interstate Fire Sales And Service Llcshilo InnPermit type: Low voltage | Permit status: Inspections | Completion date: November 6, 2014 | Current use: Commercial | Permit id: Bld2014-08052 | |||||
Billboard demolition permit k. B. Date: October 30, 2014Permit type: Sign | Permit status: Pass | Completion date: April 22, 2015 | Permit id: Bld2014-07936 | |||||
Fire alarm and related alarm work authorized through seperate permit. Replace existing disconnects feeding (2) elevators and install new shunt trip style disconnects tied into fire alarm system. Date: October 14, 2014Permit type: Electrical | Permit status: Completed | Completion date: October 14, 2014 | Current use: Commercial | Permit id: Bld2014-07469 | |||||
SCORE 64 Interior finish remodel of existing hotel lobby. Addition of new decorative stair and guest rooms. Date: October 8, 2014Permit type: Permit | Permit status: Inspections | Completion date: November 20, 2014 | Current use: Commercial | Permit id: Bld2014-07314 | |||||
SCORE 64 Building is to be updated with a new exterior skin of e. F. I. S. And stucco. New guardrails installed at the balconies and the two stair towers. A new porte cochere will added to the front of the building Date: July 22, 2014 Contractor: Pentalon Construction Incshilo InnPermit type: Permit | Permit status: Inspections | Completion date: October 15, 2014 | Current use: Commercial | Permit id: Bld2014-05244 | |||||
We would like to phase the project. The first phase is to remove old architectural features and eliminate two door, and the exterior elevator system. The exterior balcony guardrails are broken and not excepted by the parent company. Date: July 17, 2014Permit type: Permit | Permit status: Completed | Completion date: August 25, 2014 | Current use: Commercial | Permit id: Bld2014-05091 | |||||
SCORE 64 Guestroom renovation Date: May 21, 2014 Contractor: Joe Burgess Construction Incholiday Inn ExpressPermit type: Permit | Permit status: Closed | Completion date: June 3, 2015 | Current use: Commercial | Permit id: Bld2014-03460 | |||||
SCORE 61 Guestroom renovation Date: June 3, 2015 Contractor: Holiday Inn Expressdave JeffsPermit status: Closed | Current use: Commercial | Permit id: Bld2014-03460 | |||||
SCORE 61 Interior finish remodel of existing hotel lobby. Addition of new decorative stair and guest rooms. Date: November 20, 2014 Contractor: Holiday Inn Express Lobbydave JeffsPermit status: Inspections | Current use: Commercial | Permit id: Bld2014-07314 | |||||
SCORE 61 Building is to be updated with a new exterior skin of e. F. I. S. And stucco. New guardrails installed at the balconies and the two stair towers. A new porte cochere will added to the front of the building Date: October 15, 2014 Contractor: Shilo Inns JohansenPermit status: Inspections | Current use: Commercial | Permit id: Bld2014-05244 | |||||
We would like to phase the project. The first phase is to remove old architectural features and eliminate two door, and the exterior elevator system. The exterior balcony guardrails are broken and not excepted by the parent company. Date: August 25, 2014Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-05091 | |||||
SCORE 59 Fire alarm and related alarm work authorized through seperate permit. Replace existing disconnects feeding (2) elevators and install new shunt trip style disconnects tied into fire alarm system. Date: October 14, 2014Permit type: Electrical | Permit status: Inspections | Completion date: October 14, 2014 | Current use: Commercial | Permit id: Bld2014-07469 | |||||
SCORE 56 Billboard demolition permit k. B. Date: October 30, 2014Permit type: Sign | Permit status: Closed | Completion date: April 22, 2015 | Permit id: Bld2014-07936 | |||||
SCORE 56 Commercial electrical remodel Date: December 2, 2014 Contractor: Reliance Electric Inc.Holiday Inn Express LobbyPermit type: Electrical | Permit status: Closed | Completion date: June 5, 2015 | Current use: Commercial | Permit id: Bld2014-08848 | |||||
SCORE 91 Fire alarm system Date: September 17, 2014 Contractor: Professional Systems Technology IncPermit type: Low voltage | Permit status: Completed | Completion date: October 1, 2014 | Current use: Commercial | Permit id: Bld2014-06784 | |||||
SCORE 91 Att distributive antenna system--head end equipment, to be installed at the salt palace Date: April 30, 2014 Contractor: D Kent MaughanPermit type: Permit | Permit status: Completed | Completion date: July 18, 2014 | Current use: Commercial | Permit id: Bld2014-02884 | |||||
SCORE 100 Hvac rtu installation, structural to reinforce roof joist l. L. D-4 zone, not historic, mech equip on roof a. S. Date: March 22, 2012 Contractor: Cci Mechanical IncPermit type: Permit | Permit status: Applicant info required | Completion date: May 30, 2012 | Current use: Commercial | Permit id: Bld2012-02150 | |||||
SCORE 99 Control valve replacement Date: April 20, 2011 Contractor: Kemp And Hilton IncPermit type: Mechanical | Permit status: Completed | Completion date: April 20, 2011 | Current use: Commercial | Permit id: Bld2011-02232 | |||||
SCORE 83 Upgrade hvac controls, damper motor control valve hookup Date: April 20, 2011 Contractor: Utah Controls IncPermit type: Mechanical | Permit status: Reviews not require | Completion date: April 20, 2011 | Current use: Commercial | Permit id: Bld2011-02231 | |||||
SCORE 99 Replace existing fire line. Date: April 13, 2010 Contractor: First Fire Protection IncPermit type: Fire | Permit status: Completed | Completion date: September 28, 2010 | Current use: Commercial | Permit id: Bld2010-02310 | |||||
Fire alarm system Date: September 17, 2014Permit type: Low voltage | Permit status: Completed | Completion date: October 1, 2014 | Current use: Commercial | Permit id: Bld2014-06784 | |||||
SCORE 64 Fire sprinklers Date: August 25, 2014Permit type: Fire | Permit status: Closed | Completion date: December 18, 2014 | Current use: Commercial | Permit id: Bld2014-06145 | |||||
SCORE 74 Electrical permit Date: July 18, 2014 Contractor: D Kent Maughanat And T Das SystemPermit type: Electrical | Permit status: Closed | Completion date: February 18, 2015 | Current use: Commercial | Permit id: Bld2014-05143 | |||||
SCORE 74 Att distributive antenna system--head end equipment, to be installed at the salt palace Date: April 30, 2014 Contractor: D Kent Maughanat And T Das SystemPermit type: Permit | Permit status: Inspections | Completion date: July 18, 2014 | Current use: Commercial | Permit id: Bld2014-02884 | |||||
Construct 117" x 84" room inside salt palace parking structure, elec permit reqd r. M. D-4 zone int work only a. H. Date: December 11, 2013Permit type: Permit | Permit status: Pass | Completion date: March 14, 2014 | Current use: Commercial | Permit id: Bld2013-09100 | |||||
SCORE 64 Fire sprinklers Date: December 11, 2013Permit type: Fire | Permit status: Completed | Completion date: February 20, 2015 | Current use: Commercial | Permit id: Bld2013-09115 | |||||
SCORE 64 Plumbing work ;being done out at the salt palace Date: December 4, 2013 Contractor: Envision Mechancialsalt Palace EscalatorPermit type: Plumbing | Permit status: No certificate req | Completion date: February 20, 2015 | Current use: Commercial | Permit id: Bld2013-08922 | |||||
SCORE 64 Install (2) heating coils, duct, grilles. Date: December 3, 2013 Contractor: United Team Mechanicalsalt Palace EscalatorPermit type: Mechanical | Permit status: Completed | Completion date: February 20, 2015 | Current use: Commercial | Permit id: Bld2013-08909 | |||||
SCORE 64 Fire alarm device wiring Date: December 3, 2013Permit type: Low voltage | Permit status: No certificate req | Completion date: February 20, 2015 | Current use: Commercial | Permit id: Bld2013-08895 | |||||
SCORE 64 Electrical permit, job bid 118,304. Date: December 3, 2013Permit type: Electrical | Permit status: Completed | Completion date: February 20, 2015 | Current use: Commercial | Permit id: Bld2013-08904 | |||||
SCORE 64 Add (6) new escalators to the existing salt palace convention center. Date: September 23, 2013Permit type: Permit | Permit status: Certificate of completion | Completion date: February 20, 2015 | Current use: Commercial | Permit id: Bld2013-06929 | |||||
Power to bike kiosk Date: March 6, 2013Permit type: Electrical | Permit status: Pass | Completion date: March 21, 2013 | Current use: Commercial | Permit id: Bld2013-01306 | |||||
Fire department approval required. Installing temporary structure. Salt palace outdoor retailers Date: July 11, 2012Permit type: Temporary use | Permit status: Pass | Completion date: January 26, 2015 | Permit id: Bld2012-04993 | |||||
SCORE 64 Hvac rtu installation, structural to reinforce roof joist l. L. D-4 zone, not historic, mech equip on roof a. S. Date: March 22, 2012 Contractor: Cci Mechanical Incsalt Palace Convention CenterPermit type: Permit | Permit status: Applicant info required | Completion date: May 30, 2012 | Current use: Commercial | Permit id: Bld2012-02150 | |||||
SCORE 64 Install photovoltaic system Date: December 7, 2011Permit type: Electrical | Permit status: Closed | Completion date: April 16, 2012 | Current use: Commercial | Permit id: Bld2011-08012 | |||||
SCORE 64 Install photovoltaics on salt palace roof, elec permit reqd k. A. K. B. T. I. Date: October 19, 2011 Contractor: Bella Energy Incsalt Palace Convention CenterPermit type: Permit | Permit status: Closed | Completion date: April 18, 2012 | Current use: Commercial | Permit id: Bld2011-06762 | |||||
SCORE 64 Upgrade hvac controls, damper motor control valve hookup Date: April 20, 2011 Contractor: Utah Controls Inc.Salt Palace Convention CenterPermit type: Mechanical | Permit status: Inspections | Completion date: April 20, 2011 | Current use: Commercial | Permit id: Bld2011-02231 | |||||
SCORE 64 Control valve replacement Date: April 20, 2011Permit type: Mechanical | Permit status: Reviews not require | Completion date: April 20, 2011 | Current use: Commercial | Permit id: Bld2011-02232 | |||||
SCORE 82 Salt palace convention. Annual event, outdoor retailers. Repeat event, fire dept approval reqd. A. H. Date: July 30, 2010 Contractor: Diamond Rentalsalt PalacePermit type: Temporary use | Permit status: In progress | Completion date: July 30, 2010 | Permit id: Bld2010-05174 | |||||
Partial reroof. D. D. D-4 zone. Re-roof - no zoning issues. A. M. Date: July 2, 2010Permit type: Permit | Permit status: Pass | Completion date: February 23, 2011 | Current use: Commercial | Permit id: Bld2010-04501 | |||||
SCORE 82 Private part on patio. Repeat annual event. A. H. Date: May 24, 2010 Contractor: Diamond Rentalsalt PalacePermit type: Temporary use | Permit status: No certificate req | Completion date: July 8, 2010 | Permit id: Bld2010-03440 | |||||
SCORE 64 Replace existing fire line. Date: April 13, 2010 Contractor: First Fire Protection Incsalt PalacePermit type: Fire | Permit status: Inspections | Completion date: September 28, 2010 | Current use: Commercial | Permit id: Bld2010-02310 | |||||
SCORE 82 Awning for walkway. Repeat event, fire dept approval reqd. Date: July 17, 2009 Contractor: Diamond Rentalsalt PalacePermit type: Temporary use | Permit status: No certificate req | Completion date: July 14, 2010 | Permit id: Bld2009-04218 | |||||
SCORE 56 Partial reroof. D. D. D-4 zone. Re-roof - no zoning issues. A. M. Date: July 2, 2010 Contractor: Onyx Construction Llcsalt PalacePermit status: Closed | Completion date: February 23, 2011 | Current use: Commercial | Permit id: Bld2010-04501 | |||||
SCORE 61 Att distributive antenna system--head end equipment, to be installed at the salt palace Date: July 18, 2014 Contractor: At And T Das Systemjames ClardPermit status: Inspections | Current use: Commercial | Permit id: Bld2014-02884 | |||||
Fire department approval required. Installing temporary structure. Salt palace outdoor retailers Date: July 11, 2012Permit type: Temporary use | Permit status: Closed | Completion date: January 26, 2015 | Permit id: Bld2012-04993 | |||||
SCORE 69 Power to bike kiosk Date: March 6, 2013 Contractor: Capital Electric Inc.City Bike KioskPermit type: Electrical | Permit status: Closed | Completion date: March 21, 2013 | Current use: Commercial | Permit id: Bld2013-01306 | |||||
Construct 117" x 84" room inside salt palace parking structure, elec permit reqd r. M. D-4 zone int work only a. H. Date: December 11, 2013Permit status: Closed | Completion date: March 14, 2014 | Current use: Commercial | Permit id: Bld2013-09100 | |||||
SCORE 56 Fire alarm system Date: September 17, 2014Permit type: Low voltage | Permit status: Inspections | Completion date: October 1, 2014 | Current use: Commercial | Permit id: Bld2014-06784 | |||||
SCORE 95 Reface existing pole sign a. H. Date: August 8, 2014 Contractor: Yesco LlcPermit type: Sign | Permit status: Accepted - standard | Completion date: August 8, 2014 | Current use: Na | Permit id: Bld2014-05694 | |||||
SCORE 64 Reface existing pole sign a. H. Date: August 8, 2014 Contractor: Yesco Llcsupersonic Car WashPermit type: Sign | Permit status: Accepted - standard | Completion date: August 8, 2014 | Permit id: Bld2014-05694 | |||||
SCORE 56 New 6 high max solid wood fencing in the rear yard, includes gates a. H. Date: April 16, 2014 Contractor: Alvarez Ingrid WPermit type: Fencing | Permit status: In progress | Completion date: April 16, 2014 | Current use: Residential | Permit id: Bld2014-02505 | |||||
New 6 high max solid wood fencing in the rear yard, includes gates a. H. Date: April 16, 2014Permit type: Fencing | Permit status: Completed | Completion date: April 16, 2014 | Current use: Residential | Permit id: Bld2014-02505 | |||||
SCORE 56 New 6 high max solid wood fencing in the rear yard, includes gates a. H. Date: April 16, 2014 Contractor: Alvarez Ingrid Walvarez Ingrid WPermit type: Fencing | Permit status: Inspections | Completion date: April 16, 2014 | Current use: Residential | Permit id: Bld2014-02505 | |||||
SCORE 89 Construct 24 x detached garage. Zone - cc zone, not historic, accessory structure, garage using alley access and concrete apron. R. M. A. S. Date: December 14, 2012 Contractor: John Erickson Construction IncPermit type: Permit | Permit status: Pass | Completion date: December 14, 2012 | Current use: Residential | Permit id: Bld2012-09164 | |||||
SCORE 66 Exterior vinyl siding, concrete overlay floor in bsmt, bathroom vanity w lav. L. L. Zone: cc zone, interior work in residence. A. S. Date: September 22, 2010 Contractor: Malik ResidencePermit type: Permit | Permit status: In progress | Completion date: September 22, 2010 | Current use: Residential | Permit id: Bld2010-06504 | |||||
SCORE 56 Hobby shop for wood working, basic car repair, and metal working. Not a business. For individual use. Date: January 21, 2015 Contractor: 1153 S West Temple Hobby ShopPermit type: Planning commission | Permit status: Complete | Completion date: February 10, 2015 | Current use: Special exception | Permit id: Plnpcm2015-0003 | |||||
SCORE 74 Construct 24 x detached garage. Zone - cc zone, not historic, accessory structure, garage using alley access and concrete apron. R. M. A. S. Date: December 14, 2012 Contractor: John Erickson Construction Incmark BreinholtPermit type: Permit | Permit status: Inspections | Completion date: December 14, 2012 | Current use: Residential | Permit id: Bld2012-09164 | |||||
SCORE 74 Electrical work as per bld2012-09164 Date: December 14, 2012 Contractor: John Erickson Construction Incmark BreinholtPermit type: Electrical | Permit status: Closed | Completion date: November 5, 2013 | Current use: Residential | Permit id: Bld2012-09165 | |||||
SCORE 64 Install footing & foundation & slab only 24 x r. M. Cc zone a. H. Date: November 29, 2012 Contractor: John Erickson Construction Incmarks New GaragePermit type: Accessory building | Permit status: Closed | Completion date: April 6, 2015 | Current use: Residential | Permit id: Bld2012-08745 | |||||
SCORE 64 Exterior vinyl siding, concrete overlay floor in bsmt, bathroom vanity w/ lav. L. L. Zone: cc zone, interior work in residence. A. S. Date: September 22, 2010 Contractor: Malik Residencemalik ResidencePermit type: Permit | Permit status: Inspections | Completion date: September 22, 2010 | Current use: Residential | Permit id: Bld2010-06504 | |||||
SCORE 66 Elec serv change for sfd Date: July 21, 2010 Contractor: Malik ResidencePermit type: Electrical | Permit status: Closed | Completion date: September 14, 2010 | Current use: Residential | Permit id: Bld2010-04954 | |||||
SCORE 100 Install 42 fixtures for remodel Date: June 11, 2012 Contractor: B K V Mechanical L.CPermit type: Plumbing | Permit status: Accepted | Completion date: June 11, 2012 | Current use: Commercial | Permit id: Bld2012-04271 | |||||
SCORE 64 Low voltage alarm Date: September 5, 2012Permit type: Low voltage | Permit status: Closed | Completion date: December 12, 2012 | Current use: Commercial | Permit id: Bld2012-06566 | |||||
SCORE 64 Install 42 fixtures for remodel Date: June 11, 2012Permit type: Plumbing | Permit status: Inspections | Completion date: June 11, 2012 | Current use: Commercial | Permit id: Bld2012-04271 | |||||
Remodel rooms d. D. K. B. T. I. Date: December 20, 2011Permit type: Permit | Permit status: Pass | Completion date: May 14, 2013 | Current use: Commercial | Permit id: Bld2011-08341 | |||||
SCORE 56 Remodel rooms d. D. K. B. T. I. Date: December 20, 2011Permit status: Closed | Completion date: May 14, 2013 | Current use: Commercial | Permit id: Bld2011-08341 | |||||
SCORE 91 New 6 ft high max. Solid wood fence in the side yard and rear yard. Zone d-2 zone. Date: May 8, 2012 Contractor: Powers Builders LlcPermit type: Fencing | Permit status: In progress | Completion date: May 8, 2012 | Current use: Residential | Permit id: Bld2012-03342 | |||||
SCORE 74 New 6 ft high max. Solid wood fence in the side yard and rear yard. Zone d-2 zone. Date: May 8, 2012 Contractor: Powers Builders Llcvacant LandPermit type: Fencing | Permit status: Accepted - standard | Completion date: May 8, 2012 | Current use: Residential | Permit id: Bld2012-03342 | |||||
SCORE 95 Electrical permit required. A. H. One wall sign one entrance sign Date: February 17, 2012 Contractor: Yesco LlcPermit type: Sign | Permit status: Accepted - standard | Completion date: February 17, 2012 | Current use: Na | Permit id: Bld2012-01388 | |||||
SCORE 95 1 marque sign k. B. Date: January 23, 2012 Contractor: Yesco LlcPermit type: Sign | Permit status: Accepted - standard | Completion date: January 23, 2012 | Current use: Na | Permit id: Bld2012-00570 | |||||
Electrical permit required. A. H. One wall sign one entrance sign Date: February 17, 2012Permit type: Sign | Permit status: Completed | Completion date: February 17, 2012 | Permit id: Bld2012-01388 | |||||
SCORE 77 1 marque sign k. B. Date: January 23, 2012 Contractor: Yesco LlcnordstromPermit type: Sign | Permit status: Accepted - standard | Completion date: January 23, 2012 | Permit id: Bld2012-00570 | |||||
SCORE 64 Power to panel permit pending power to panel agreement and payment of balance due. Date: October 13, 2011 Contractor: Dynalectric Companynordstrom 6th And Pine CafePermit type: Electrical | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06626 | |||||
SCORE 64 This is a tenant finish inside the nordstrom space. It is a cafe. Piping is sized exactly how the nordstrom space had been previously calculated at. Date: September 29, 2011 Contractor: Western Automatic Sprinkler In6th And PinePermit type: Fire | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06245 | |||||
SCORE 64 1 rtu, 3 fit boxs, 3 hoods, 4 exhuast fans and duct. 1 transfer fan Date: September 22, 2011 Contractor: Psf Mechanical Inc.Nordstrom 6th And Pine CafePermit type: Mechanical | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06098 | |||||
1 exhaust fan, 4 appliances, 2 heatpumps and assoc duct Date: September 22, 2011Permit type: Mechanical | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06101 | |||||
SCORE 77 6 flat signs a. S. Date: August 26, 2011 Contractor: Yesco LlcnordstromPermit type: Sign | Permit status: Accepted - standard | Completion date: August 26, 2011 | Permit id: Bld2011-05417 | |||||
Install 36 fixtures, 1 water heater, 1 water softener, 1 dist piping, 1 waterline, 18 drains, 4 hose bibbs, 2 backflow preventers, 1 sump pump Date: July 29, 2011Permit type: Plumbing | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04699 | |||||
SCORE 64 6 furnaces, ductwork over 1,000, 15 exhaust fans, 4 hoods, 16 appliances, 12 ac units. Date: July 27, 2011 Contractor: Psf Mechanical IncnordstromPermit type: Mechanical | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04636 | |||||
SCORE 64 Connecting to existing pump. Date: July 14, 2011 Contractor: Western Automatic Sprinkler InnordstromPermit type: Fire | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04324 | |||||
SCORE 64 Low voltage fire alarm. Date: July 7, 2011Permit type: Low voltage | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04161 | |||||
SCORE 64 Restaurant d. D. A. H. D. W. Date: June 13, 2011Permit type: Permit | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-03392 | |||||
Interior tenant improvement, mech, elec & plmbg permits reqd k. A. A. H. D. W. Date: June 13, 2011Permit type: Permit | Permit status: Pass | Completion date: February 17, 2012 | Current use: Commercial | Permit id: Bld2011-03391 | |||||
SCORE 64 Nordstrom tenant improvement. Date: April 8, 2011Permit type: Permit | Permit status: Closed | Completion date: February 28, 2012 | Current use: Commercial | Permit id: Bld2011-02029 | |||||
SCORE 76 Electrical for tenant improvement for restaurant. Date: February 9, 2010Permit type: Electrical | Permit status: Closed | Completion date: May 18, 2010 | Current use: Commercial | Permit id: Bld2010-00659 | |||||
SCORE 64 New stub into bldg test & flush, p-1 level on south side. Date: July 23, 2009Permit type: Fire | Permit status: Closed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2009-04323 | |||||
SCORE 64 New stub into bldg test & flush, p-1 level on west side. Date: July 23, 2009Permit type: Fire | Permit status: Closed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2009-04322 | |||||
SCORE 64 Structural steel only for nordstrom on block 76. Issued 6/24: larry lincoln-the contractor has submitted structural plans to erect (2) bays of structural steel prior to the removal of the track crane located on the parking deck. The use of this crane to set this steel in this specific location is needed due to the limted reach of subsequent cranes when this track crane is removed. The contractor proceeds at his own risk due to the incompleteness of the architectual plans submitted. Ken brown-proposal involves erection of two (2) bays of structural steel prior to the removal of the track crane. Contractor proceeding at his own risk regarding the 40% glass requirement public way encroachments, etc. Impact fees will be collected at the core and shell stage. Chris kimball-approved. Date: May 27, 2009Permit type: Permit | Permit status: Closed | Completion date: February 17, 2012 | Current use: Commercial | Permit id: Bld2009-03080 | |||||
Interior tenant improvement, mech, elec & plmbg permits reqd k. A. A. H. D. W. Date: June 13, 2011Permit status: Closed | Completion date: February 17, 2012 | Current use: Commercial | Permit id: Bld2011-03391 | |||||
SCORE 56 Elec work for tenant improvement. Permit issued to accomidate inspection associated with a concrete pour, actual elec work for the tenant finish may not proceed until building bld2011-03392 is issued. Date: June 14, 2011Permit type: Electrical | Permit status: Closed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-03460 | |||||
SCORE 56 Install 36 fixtures, 1 water heater, 1 water softener, 1 dist piping, 1 waterline, 18 drains, 4 hose bibbs, 2 backflow preventers, 1 sump pump Date: July 29, 2011 Contractor: Cci Mechanical Inc.Nordstrom City Creek PlumbingPermit type: Plumbing | Permit status: Closed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04699 | |||||
1 exhaust fan, 4 appliances, 2 heatpumps and assoc duct Date: September 22, 2011Permit type: Mechanical | Permit status: Closed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06101 | |||||
SCORE 66 Addition of two kitchen hood systems in nordstrom Date: September 28, 2011 Contractor: Simplexgrinnellnordstrom Kitchen HoodsPermit type: Fire | Permit status: Closed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06217 | |||||
SCORE 66 Ebar- this is just by the nordstrom space. It is called ebar. We have sent a hydraulic calc in and it feeds off the same nordstrom pump. Date: September 29, 2011 Contractor: EbarPermit type: Fire | Permit status: Closed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06246 | |||||
Electrical permit required. A. H. One wall sign one entrance sign Date: February 17, 2012Permit type: Sign | Permit status: Inspections | Completion date: February 17, 2012 | Permit id: Bld2012-01388 | |||||
SCORE 100 2 flat signs a. S. Date: January 13, 2012 Contractor: Hightech Signs IncPermit type: Sign | Permit status: Pass | Completion date: January 13, 2012 | Current use: Na | Permit id: Bld2012-00340 | |||||
SCORE 64 Run power from existing circuit fed from the utah museum of contemporary art to relocated greenbike kiosk located at sidewalk. May need to run a new circuit inside the museum Date: July 2, 2014 Contractor: Greenbike KioskPermit type: Electrical | Permit status: Closed | Completion date: August 4, 2014 | Current use: Commercial | Permit id: Bld2014-04669 | |||||
SCORE 77 Temp use for fundraiser event annual gala 2012 - repeat event Date: May 25, 2012 Contractor: Diamond Rentalsalt Lake Arts CenterPermit type: Temporary use | Permit status: Completed | Completion date: May 31, 2012 | Permit id: Bld2012-03889 | |||||
SCORE 64 2 flat signs a. S. Date: January 13, 2012 Contractor: Hightech Signs Incsalt Lake Arts CenterPermit type: Sign | Permit status: Accepted - standard | Completion date: January 13, 2012 | Permit id: Bld2012-00340 | |||||
SCORE 64 Add outlets in back room on the first floor for the new lay-out Date: September 21, 2011 Contractor: Sierra Electric Lcslc ArtPermit type: Electrical | Permit status: Closed | Completion date: October 5, 2011 | Current use: Commercial | Permit id: Bld2011-06070 | |||||
SCORE 64 Install new metal framed walls & elec plug outlets, elec permit reqd k. A. No zoning issues a. M. Date: September 14, 2011 Contractor: Heath Constructionslc ArtPermit type: Permit | Permit status: Closed | Completion date: October 5, 2011 | Current use: Commercial | Permit id: Bld2011-05823 | |||||
SCORE 77 Temp use for fundraiser event Date: June 1, 2011 Contractor: Diamond Rentalsalt Lake Arts CenterPermit type: Temporary use | Permit status: Completed | Completion date: June 2, 2011 | Permit id: Bld2011-03170 | |||||
SCORE 64 Demo and relocate switches. Date: March 21, 2011 Contractor: Sierra Electric Lcslc Art CenterPermit type: Electrical | Permit status: Applicant info required | Completion date: March 21, 2011 | Current use: Commercial | Permit id: Bld2011-01618 | |||||
Demo of non-bearing partition wall & door. Interior only. L. L. Zone: a. H. Date: March 18, 2011Permit type: Permit | Permit status: Pass | Completion date: March 29, 2011 | Current use: Commercial | Permit id: Bld2011-01592 | |||||
SCORE 56 Demo of non-bearing partition wall & door. Interior only. L. L. Zone: a. H. Date: March 18, 2011 Contractor: Heath Construction Inc.Slc Art CenterPermit status: Closed | Completion date: March 29, 2011 | Current use: Commercial | Permit id: Bld2011-01592 | |||||
SCORE 100 Relocate & add new sprinklers to corridor remodel Date: October 16, 2009 Contractor: Fire Engineering Company IncPermit type: Fire | Permit status: Applicant info required | Completion date: October 26, 2009 | Current use: Commercial | Permit id: Bld2009-06373 | |||||
SCORE 64 Interior demolition interior nonstructural demolition. D. D. A. H. Date: June 14, 2012Permit type: Demolition | Permit status: Closed | Completion date: March 20, 2013 | Current use: Commercial | Permit id: Bld2012-04390 | |||||
SCORE 64 Change out existing lighting to new energy efficient lighting Date: November 1, 2013 Contractor: Electrical Contractormarriott Lobby RenovationPermit type: Electrical | Permit status: Closed | Completion date: April 16, 2015 | Current use: Commercial | Permit id: Bld2013-08115 | |||||
SCORE 64 Hotel lobby renovation l. L. K. B. D. W. Date: July 30, 2013 Contractor: New Star General Contractors Incmarriott HotelPermit type: Permit | Permit status: Closed | Completion date: December 4, 2013 | Current use: Commercial | Permit id: Bld2013-05286 | |||||
Electrical work up to 250,000. Job bid 172,000. Remodel meeting rooms. Date: March 25, 2013Permit type: Electrical | Permit status: Pass | Completion date: March 29, 2013 | Current use: Commercial | Permit id: Bld2013-01717 | |||||
SCORE 64 Remodel meeting rooms, mech/elec permits reqd t. B. A. H. Date: January 15, 2013 Contractor: New Star General Contractors IncmarriottPermit type: Permit | Permit status: Closed | Completion date: May 1, 2013 | Current use: Commercial | Permit id: Bld2013-00281 | |||||
Adding rru amplifiers on each of the three sectors. These will be added below the antennae line the they are not visible. From the ground below. Date: October 18, 2012Permit type: Permit | Permit status: Pass | Completion date: October 1, 2013 | Current use: Commercial | Permit id: Bld2012-07740 | |||||
SCORE 64 Ballroom renovation zone - interior work only. Date: May 1, 2012Permit type: Permit | Permit status: Closed | Completion date: July 12, 2012 | Current use: Commercial | Permit id: Bld2012-03109 | |||||
SCORE 64 Clean and restore exterior surfaces. G. S. For d. D. Zone: k. B. Date: June 24, 2011Permit type: Permit | Permit status: Closed | Completion date: October 20, 2011 | Current use: Commercial | Permit id: Bld2011-03883 | |||||
New 45 kva transformer & panel. Replace existing 15 kva Date: September 14, 2010Permit type: Electrical | Permit status: Pass | Completion date: September 15, 2010 | Current use: Commercial | Permit id: Bld2010-06303 | |||||
Remove existing tar & gravel roof to structure, install new tpo system per attached icc report. Date: September 9, 2010Permit type: Roofing | Permit status: Pass | Completion date: November 17, 2010 | Current use: Commercial | Permit id: Bld2010-06211 | |||||
Install (3) skid-mounted cell antonnae. T. B. New t-mobile roof-top antennas. A. M. Date: August 13, 2010Permit type: Permit | Permit status: Pass | Completion date: January 18, 2012 | Current use: Commercial | Permit id: Bld2010-05528 | |||||
SCORE 64 Relocate & add new sprinklers to corridor remodel Date: October 16, 2009 Contractor: Fire Engineering Company Incmarriot HotelPermit type: Fire | Permit status: Applicant info required | Completion date: October 26, 2009 | Current use: Commercial | Permit id: Bld2009-06373 | |||||
SCORE 66 Permit Date: August 8, 2008Permit status: Pass | Completion date: October 8, 2010 | Current use: Commercial | Permit id: Bld2008-00946 | |||||
SCORE 66 Date: August 8, 2008Permit status: Closed | Completion date: October 8, 2010 | Current use: Commercial | Permit id: Bld2008-00946 | |||||
Install (3) skid-mounted cell antonnae. T. B. New t-mobile roof-top antennas. A. M. Date: August 13, 2010Permit status: Closed | Completion date: January 18, 2012 | Current use: Commercial | Permit id: Bld2010-05528 | |||||
SCORE 56 Remove existing tar & gravel roof to structure, install new tpo system per attached icc report. Date: September 9, 2010 Contractor: Roof Systems Inc.Marriott HotelPermit type: Roofing | Permit status: Closed | Completion date: November 17, 2010 | Current use: Commercial | Permit id: Bld2010-06211 | |||||
SCORE 56 New 45 kva transformer & panel. Replace existing 15 kva Date: September 14, 2010 Contractor: T S Electric Inc.Marriott HotelPermit type: Electrical | Permit status: Closed | Completion date: September 15, 2010 | Current use: Commercial | Permit id: Bld2010-06303 | |||||
Adding rru amplifiers on each of the three sectors. These will be added below the antennae line the they are not visible. From the ground below. Date: October 18, 2012Permit status: Closed | Completion date: October 1, 2013 | Current use: Commercial | Permit id: Bld2012-07740 | |||||
SCORE 56 Electrical work up to 250,000. Job bid 172,000. Remodel meeting rooms. Date: March 25, 2013 Contractor: T S Electric Inc.MarriottPermit type: Electrical | Permit status: Closed | Completion date: March 29, 2013 | Current use: Commercial | Permit id: Bld2013-01717 |