Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 Tear off exist roof & replace w/ 15# felt & yr comp shingles on 17 sq ft sfd & att. Garage. Applicant: Jose Rodriguez | Permit status: Finaled | Completion date: May 29, 2013 | Permit id: 1302250075 | |||||
SCORE 100 Roof mounted solar panels(11) 2. 34kw. Applicant: Thai Bo | Permit status: Finaled | Completion date: October 17, 2013 | Permit id: 1307090060 | |||||
SCORE 88 Re-roof exist patio(6 sq.) hot mop Applicant: Jack Labachyan | Permit status: Finaled | Completion date: August 8, 2014 | Permit id: 1407150069 | |||||
SCORE 95 Replace (15) outlets & upgrade panel to 2 amps Date: February 25, 2013 Contractor: Jose Rodriguez Applicant: Jose Rodriguez | Permit status: Finaled | Completion date: May 29, 2013 | Permit id: 1302250044 | |||||
SCORE 100 (11) solar panels 2. 34 kw Date: July 26, 2013 Contractor: Grid Alternatives Applicant: Thai Bo | Permit status: Finaled | Completion date: October 17, 2013 | Permit id: 1307090049 | |||||
SCORE 88 1- outlet & 3-exhaust fans Date: July 15, 2014 Contractor: Jack Labachyan Applicant: Jack Labachyan | Permit status: Finaled | Completion date: August 8, 2014 | Permit id: 1407150036 | |||||
SCORE 100 C/o fau same location. Date: March 19, 2012 Contractor: Reliable Energy Management Inc Applicant: Juan Martinez | Permit status: Finaled | Completion date: March 26, 2012 | Permit id: 1203190002 | |||||
SCORE 95 Repipe portion of sfd (4) fixtures & new bathtub. Date: February 25, 2013 Contractor: Jose Rodriguez Applicant: Jose Rodriguez | Permit status: Finaled | Completion date: May 29, 2013 | Permit id: 1302250021 | |||||
Replace gas main Date: April 29, 2013 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 29, 2013 | Permit id: 1304290043 |