Plumbing permit Date: April 14, 2011Permit status: Completed | Permit id: 335814 | |||||
Electrical permit Date: April 14, 2011Permit status: Completed | Permit id: 335661 | |||||
Plumbing permit Date: April 14, 2010Permit status: Completed | Permit id: 272717 | |||||
Suppression permit Date: September 22, 2011Permit status: Completed | Permit id: 297389 | |||||
Zoning/use permit Date: March 5, 2010Permit status: Completed | Permit id: 254238 | |||||
Mechanical permit Date: August 10, 2010Permit status: Completed | Permit id: 295331 | |||||
New construction permit Date: June 28, 2011Permit status: Completed | Permit id: 266339 | |||||
Permit for the erection of a three (3) story attached structure (maximum height 37 feet) with roof deck and 42" protective railing and pilot house with cellar and for the erection of a 6 feet high fence for use as a two (2) family dwelling. Date: January 14, 2010Applicant: Shawn D. Ward, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: March 11, 2010 | Permit id: 10869 | |||||
Suppression permit Date: September 22, 2011Permit status: Completed | Permit id: 297389 | |||||
Plumbing permit Date: April 14, 2011Permit status: Completed | Permit id: 335814 | |||||
Mechanical permit Date: August 10, 2010Permit status: Completed | Permit id: 295331 | |||||
Electrical permit Date: April 14, 2011Permit status: Completed | Permit id: 335661 | |||||
Plumbing permit Date: April 14, 2010Permit status: Completed | Permit id: 272717 | |||||
Zoning use permit Date: March 5, 2010Permit status: Completed | Permit id: 254238 | |||||
New construction permit Date: June 28, 2011Permit status: Completed | Permit id: 266339 | |||||
Permit for the erection of a three (3) story attached structure (maximum height 37 feet) with roof deck and 42" protective railing and pilot house with cellar and for the erection of a 6 feet high fence for use as a two (2) family dwelling. Date: January 14, 2010Applicant: Shawn D. Ward, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: March 11, 2010 | Permit id: 10869 | |||||
New 3 story duplex w cellar and roof top deck Date: March 5, 2010Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 9, 2010 | Permit id: 254238 | |||||
SCORE 84 New construction of a duplex with roof top deck Date: June 28, 2011 Contractor: Clevland Development LlcPermit type: New construction permit | Permit status: Completed | Completion date: October 27, 2011 | Permit id: 266339 | |||||
SCORE 100 Install 2 heat pump units, including accessory ductwork (duplex) Date: August 10, 2010 Contractor: Talgar IncPermit type: Mechanical permit | Permit status: Completed | Completion date: November 1, 2011 | Permit id: 295331 | |||||
SCORE 100 3 4 wd,house trap,lateral Date: April 14, 2010 Contractor: J S Plumbing Company LlcPermit type: Plumbing permit | Permit status: Completed | Completion date: October 14, 2010 | Permit id: 272717 | |||||
SCORE 100 Install fire service, backflow and sprinkler system throughout. Date: September 22, 2011 Contractor: B. M. Consulting Services IncPermit type: Suppression permit | Permit status: Completed | Completion date: November 2, 2011 | Permit id: 297389 | |||||
SCORE 96 2 amp service, 42 receptacles, 6 gfcis, 15 lights, 12 switches, 6 smoke detectors, 2 heat pumps, 2 stoves, 2 hot water heaters, as per 2008 nec Date: April 14, 2011 Contractor: Williams Joseph TPermit type: Electrical permit | Permit status: Completed | Completion date: December 9, 2011 | Permit id: 335661 | |||||
SCORE 97 (2) kitchen sinks,(5)toilets,(5)bathtubs,(5) lav sinks,(2) laundry waste pipes,(2) water heaters Date: April 14, 2011 Contractor: Richard LawrencePermit type: Plumbing permit | Permit status: Completed | Completion date: November 2, 2011 | Permit id: 335814 |