SCORE 95 Demolish existing structure and remove underground tanks per plan. Date: February 17, 2015 Contractor: Central Puget Sound Transit Applicant: Zeller, Gayle | Permit type: Demolition | Permit status: Application accepted | Current use: Commercial | Permit id: 6425274 | |||||
SCORE 95 Grading for soil remediation to existing parking lot, per plan. Applicant: Zeller, Gayle | Permit type: Site development | Permit status: Application accepted | Current use: Commercial | Permit id: 6444305 | |||||
SCORE 95 Grading, underground tank removal and soil remediation of approximately 5,8 cubic yards of material, per plans. Date: December 28, 2014 Contractor: Central Puget Sound Transit Applicant: Zeller, Gayle | Permit type: Site development | Permit status: Application accepted | Current use: Commercial | Permit id: 6430243 | |||||
SCORE 95 Grading, underground tank removal and soil remediation of approximately 5,8 cubic yards of material, per plans. Applicant: Zeller, Gayle | Permit type: Construction | Permit status: Permit issued | Current use: Commercial | Permit id: 6482192 | |||||
SCORE 95 Grading for soil remediation to existing parking lot, per plan. Soil nailing for support of excavation. Applicant: Zeller, Gayle | Permit type: Construction | Permit status: Permit issued | Current use: Commercial | Permit id: 6483923 | |||||
SCORE 98 Adding outlets & changing out 22 lights - ref plan review permit #6030983 Date: April 9, 2004 Contractor: Steele Corporation Permit type: Electrical | Permit status: Permit finaled | Completion date: May 11, 2004 | Expiration date: April 9, 2005 | Current use: Commercial | Permit id: 6033227 | |||||
SCORE 100 Installation of low voltage alarm & video equipment Date: March 26, 2004 Contractor: Diebold Incorporated Permit type: Electrical | Permit status: Permit finaled | Completion date: May 24, 2004 | Expiration date: March 26, 2005 | Current use: Commercial | Permit id: 6032464 | |||||
SCORE 98 Get started day conditional; reference 6030983. Date: March 1, 2004 Contractor: Steele Corporation Permit type: Electrical | Permit status: Permit finaled | Completion date: May 21, 2004 | Expiration date: March 1, 2005 | Current use: Commercial | Permit id: 6030984 | |||||
SCORE 95 Land use application to allow a temporary construction staging area for sound transit link light rail. Review includes 2,0 cu. Yds. Of grading (1,0 cu. Yds. Of cut, 1,0 cu. Yds. Of fill); removing an underground storage tank, and soil remediation. Parking for vehicles to be provided. Final environmental impact statement (november 1999) and the north link final supplemental environmental impact statement (april 2006) prepared by sound transit. Applicant: Zeller, Gayle | Permit type: Sepa threshold determination, temporary land use | Permit status: Permit issued | Current use: Commercial | Permit id: 3018878 | |||||
SCORE 99 Temporary dewatering connected to existing side sewer and cap existing side sewer Date: September 9, 2016 Contractor: Pellco Construction Inc Applicant: Pellco Construction Inc | Permit type: Side sewer | Permit status: Permit issued | Expiration date: March 9, 2018 | Current use: Commercial | Permit id: 6555810 | |||||
SCORE 100 Installing illuminated channel letter wall sign for performance bicycle Date: September 29, 2005 Contractor: Plumb Signs Inc Applicant: Plumb Signs Inc | Permit type: Sign/billboard/awning | Permit status: Permit finaled | Completion date: December 7, 2005 | Expiration date: March 29, 2007 | Current use: Commercial | Permit id: 6073086 | |||||
SCORE 100 Repair sewer line Date: May 14, 2004 Contractor: Johnson Backhoe Dozing Srv Inc Applicant: Johnson Backhoe/dozing Srv Inc | Permit type: Side sewer | Permit status: Permit finaled | Completion date: May 20, 2004 | Expiration date: August 14, 2004 | Current use: Commercial | Permit id: 6035248 | |||||
SCORE 95 Install (2) double side pole on 1 circuit, (2) wall signs on 1 circuit, & (6) non-illum ground signs (5 double sided & 1 single). Date: April 29, 2004 Contractor: Mikes Neon Signs Applicant: Mikes Neon Signs | Permit type: Sign/billboard/awning | Permit status: Permit finaled | Completion date: June 14, 2004 | Expiration date: October 29, 2005 | Current use: Commercial | Permit id: 6033800 | |||||
Construction foundations for installation of factory-built structure for construction trailer use. Applicant: Siebel, Nicole | Permit type: Construction | Permit status: Initial information colle | Current use: Commercial | Permit id: 6575300 | |||||
SCORE 95 Land use application to allow a temporary construction staging area for sound transit link light rail. Review includes 4,2 cu. Yds. Of grading and soil remediation (2,1 cu. Yds. Of cut, 2,1 cu. Yds. Of fill); removing underground storage tank and demolishing existing building (3,4 sq. Ft. Office and awning). A 5,7 sq. Ft. Temporary office trailer and 6 parking spaces will be installed. Final environmental impact statement (november 1999) and the north link final supplemental environmental impact statement (april 2006) prepared by sound transit. Applicant: Zeller, Gayle | Permit type: Sepa threshold determination, temporary land use | Permit status: Permit issued | Current use: Commercial | Permit id: 3018300 | |||||
SCORE 95 Temp power to job trailers. Assoc. Building permit 65753 veca job number 819306 [related project number: 6575300] Permit type: Electrical | Permit status: Permit closed | Completion date: July 25, 2017 | Expiration date: June 15, 2018 | Current use: Commercial | Permit id: 6597984 | |||||
SCORE 100 Low voltage terminate panel Date: October 17, 2017 Contractor: Allied Fire And Security Permit type: Electrical | Permit status: Permit closed | Completion date: October 19, 2017 | Expiration date: October 17, 2018 | Current use: Commercial | Permit id: 6624877 | |||||
SCORE 100 Installation of temporary heat trace on water lines at the trailers. 831382 10 4 17 hkh; address change from 401 s jackson st 12 12 17 ym adding (2) 1 amp circuit Date: September 22, 2017 Contractor: E C Company Permit type: Electrical | Permit status: Permit issued | Expiration date: September 22, 2018 | Current use: Commercial | Permit id: 6620487 | |||||
SCORE 95 Underground pvc conduit and 20a circuit to 1 hp grinder pump Date: May 3, 2017 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit issued | Expiration date: May 3, 2018 | Current use: Commercial | Permit id: 6595243 | |||||
SCORE 95 Underground pvc conduit and 20a ckt to 1hp grinder pump. (veca job 819306) Date: May 3, 2017 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit issued | Expiration date: May 3, 2018 | Current use: Commercial | Permit id: 6595249 | |||||
SCORE 95 Install temporary, factory-built office structures for construction offices for sound transit construction, per plans. Applicant: Siebel, Nicole | Permit type: Construction | Permit status: Permit issued | Expiration date: November 16, 2018 | Current use: Commercial | Permit id: 6575300 | |||||
SCORE 100 2 heat trace circuits for work trailers job 830905 Date: June 12, 2017 Contractor: E C Company Permit type: Electrical | Permit status: Permit closed | Completion date: July 24, 2017 | Expiration date: June 12, 2018 | Current use: Commercial | Permit id: 6602278 | |||||
SCORE 99 Add/alt to install inlets and modify drain lines that discharge to the existing storm drain service Date: September 9, 2016 Contractor: Pellco Construction Inc Applicant: Pellco Construction Inc | Permit type: Side sewer | Permit status: Permit issued | Completion date: November 14, 2016 | Expiration date: March 9, 2018 | Current use: Commercial | Permit id: 6555805 | |||||
SCORE 95 Temp data cabling for 3 trailers. Veca job # 819306 Date: June 12, 2017 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: July 21, 2017 | Expiration date: June 12, 2018 | Current use: Commercial | Permit id: 6602120 | |||||
SCORE 95 Day get started for branch circuits only. Assoc permit 6597984 Date: May 26, 2017 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: June 15, 2017 | Expiration date: June 26, 2017 | Current use: Commercial | Permit id: 6599457 | |||||
Reconnect sanitary and drainage (if needed) for sound transit staging facility. Trailer to be installed under 65758300. No drainage review. Date: March 15, 2017 Applicant: Wong, Nicholas | Permit type: Side sewer | Permit status: Permit closed | Completion date: July 24, 2017 | Expiration date: September 15, 2018 | Current use: Commercial | Permit id: 6586125 | |||||
SCORE 100 Install voice/data locations Date: March 29, 2004 Contractor: Teldata Systems Incorporated Permit type: Electrical | Permit status: Permit finaled | Completion date: April 13, 2005 | Expiration date: March 29, 2005 | Current use: Commercial | Permit id: 6032522 |